DD 1861 required without claim COM?

Started by Former_DCAA · Nov 2, 2023 · 6 replies

  1. F

    Former_DCAA

    Nov 2, 2023 · 2y ago

    Original post

    We submitted a proposal without claiming any cost of money. The cost/price analyst from DCMA is asking us to complete form DD-1861 and says it’s so they can evaluate profit.   

    Has anyone ever encountered this and can provide some guidance on why it would be required.

  2. C

    C Culham

    Nov 2, 2023 · 2y ago

    Former_DCAA said:

    We submitted a proposal without claiming any cost of money. The cost/price analyst from DCMA is asking us to complete form DD-1861 and says it’s so they can evaluate profit.   

    Has anyone ever encountered this and can provide some guidance on why it would be required.

    So did the solicitation ask for the form?

  3. j

    joel hoffman

    Nov 3, 2023 · 2y ago

    Former_DCAA said:

    We submitted a proposal without claiming any cost of money. The cost/price analyst from DCMA is asking us to complete form DD-1861 and says it’s so they can evaluate profit.   

    Has anyone ever encountered this and can provide some guidance on why it would be required.

    See https://www.acquisition.gov/dfarspgi/pgi-215.404-71-4-facilities-capital-employed.

    The KO or ACO is responsible to complete the form DD-1861…

  4. F

    Former_DCAA

    Nov 3, 2023 · 2y ago

    joel hoffman said:

    See https://www.acquisition.gov/dfarspgi/pgi-215.404-71-4-facilities-capital-employed.

    The KO or ACO is responsible to complete the form DD-1861…

    They don't have the accounting information required to complete it. I'm just confused why they need the form if no COM is being claimed, how does it play into profit?

  5. C

    C Culham

    Nov 3, 2023 · 2y ago

    Former_DCAA said:

    They don't have the accounting information required to complete it. I'm just confused why they need the form if no COM is being claimed, how does it play into profit?

    Therefore my question.    Paragraph (C) of the citation Joel provided -

    "The contracting officer could request the data through a solicitation provision."

  6. F

    Former_DCAA

    Nov 3, 2023 · 2y ago

    C Culham said:

    Therefore my question.    Paragraph (C) of the citation Joel provided -

    "The contracting officer could request the data through a solicitation provision."

    I wasn't ignoring your question, I'm just getting involved at the end and haven't seen the solicitation yet.

  7. A

    AlsoExDCAA

    Nov 6, 2023 · 2y ago

    On 11/3/2023 at 3:46 PM, Former_DCAA said:

    They don't have the accounting information required to complete it. I'm just confused why they need the form if no COM is being claimed, how does it play into profit?

    "Facilities Capital Employed" is one of the four profit factors a contracting officer looks at in the weighted guidelines method approach for determining a prenegotiation profit/fee objective on negotiated actions requiring certified cost and pricing (excl CPAF). See https://www.acq.osd.mil/dpap/dars/dfars/html/current/215_4.htm#215.404-71

    The KO is following the PGI on their end to obtain the info necessary as part of the weighted-average guideline calculation. The instruction under PGI 215.404-71-4(b),(c) specifically calls for info from the DD-1861. 

    Granted the DD-1861 is supposed to be completed by the KO, and if they wanted it from the contractor they should have specifically requested it as a solicitation instruction, but this is really what they're trying to accomplish here.