Extensions of Time under Time and Material (non-commercial) contracts
Started by Tzarina of Compliance · Nov 17, 2023 · 21 replies
- TOriginal post
Tzarina of Compliance
Nov 17, 2023 · 2y ago
What are the options to extend the period of performance under a T&M contract for non-commercial services without an increase in ceiling on $$ or LOE? There are no pre-priced options in the contract and no excusable delays. Would a CO be authorized to grant the extension without a J&A?
- R
Retreadfed
Nov 17, 2023 · 2y ago
What is the contract for and why is an extension needed? There could be various options depending on what the facts are. By the way, a T&M contract does not require a level of effort if that is what you meant by LOE. In my several decades of experience, I have never seen such a contract.
- C
C Culham
Nov 18, 2023 · 2y ago
Tzarina of Compliance said:
Would a CO be authorized to grant the extension without a J&A?
Thoughts
J&A? Or creation of and approval of a JOFOC? Neither. Maybe a just memo to the file that explains the extension.
Mutual agreement of the parties - Yes I know it is non-commercial but remember the parties to a contract can mutually agree to a change without the need of a clause to do so.
Consideration? If I were the CO I would want consideration.
Pursuant to FAR 16.601(c) one could imagine the possible need to extend the period of performance of a T&M contract. Emphasis added "Application. A time-and-materials contract may be used only when it is not possible at the time of placing the contract to estimate accurately the extent or duration of the work or to anticipate costs with any reasonable degree of confidence."
Scope? If the need for extension is to pursue some type of result (the work) that was reasonably anticipated by the procurement it would seem scope is not an issue.
Some of my thoughts came from this based on the idea that a T&M contract is sometimes referred to as a hybrid of a cost reimbursement/fixed price contract.
- T
Tzarina of Compliance
Nov 18, 2023 · 2y ago
C Culham said:
Thoughts
J&A? Or creation of and approval of a JOFOC? Neither. Maybe a just memo to the file that explains the extension.
Mutual agreement of the parties - Yes I know it is non-commercial but remember the parties to a contract can mutually agree to a change without the need of a clause to do so.
Consideration? If I were the CO I would want consideration.
Pursuant to FAR 16.601(c) one could imagine the possible need to extend the period of performance of a T&M contract. Emphasis added "Application. A time-and-materials contract may be used only when it is not possible at the time of placing the contract to estimate accurately the extent or duration of the work or to anticipate costs with any reasonable degree of confidence."
Scope? If the need for extension is to pursue some type of result (the work) that was reasonably anticipated by the procurement it would seem scope is not an issue.
Some of my thoughts came from this based on the idea that a T&M contract is sometimes referred to as a hybrid of a cost reimbursement/fixed price contract.
Interesting. I know there is no LOE in T&M, but for some reason, the contract included a limitation on specific labor categories by the level of effort (eye roll). So the contract is basically expiring and there is still a ton of money left. The work was delayed due to a potential Government shut down due to the unavailability of Government staff, but since the shutdown never happened, the GC is not agreeing to excusable delays. The extension will not need to add money just to bridge the work before the new contract kicks in. So are you saying that a mutual extension agreement is sufficient? I love that.
- T
Tzarina of Compliance
Nov 18, 2023 · 2y ago
C Culham said:
Thoughts
J&A? Or creation of and approval of a JOFOC? Neither. Maybe a just memo to the file that explains the extension.
Mutual agreement of the parties - Yes I know it is non-commercial but remember the parties to a contract can mutually agree to a change without the need of a clause to do so.
Consideration? If I were the CO I would want consideration.
Pursuant to FAR 16.601(c) one could imagine the possible need to extend the period of performance of a T&M contract. Emphasis added "Application. A time-and-materials contract may be used only when it is not possible at the time of placing the contract to estimate accurately the extent or duration of the work or to anticipate costs with any reasonable degree of confidence."
Scope? If the need for extension is to pursue some type of result (the work) that was reasonably anticipated by the procurement it would seem scope is not an issue.
Some of my thoughts came from this based on the idea that a T&M contract is sometimes referred to as a hybrid of a cost reimbursement/fixed price contract.
Oh and wouldn't T&M be severable?
- C
C Culham
Nov 18, 2023 · 2y ago
Tzarina of Compliance said:
GC
CO? Or General Contractor? Raised to make sure we are talking Government to Prime.
Tzarina of Compliance said:
new contract
Tzarina of Compliance said:
T&M be severable
Maybe yes maybe no but your indication of new suggests so but it depends on what is to be accomplished.
Tzarina of Compliance said:
So are you saying that a mutual extension agreement is sufficient?
Yes as long the matter of scope is not an issue.
- j
joel hoffman
Nov 19, 2023 · 2y ago
On 11/17/2023 at 9:49 PM, Tzarina of Compliance said:
Oh and wouldn't T&M be severable?
Depends upon the circumstances.
Recommend reading, for instance, the WIFCON Legal pages for the Bonafide Needs Rule.
Also appears that you are saying that this will be a bridge for period prior to award of or start of a follow on T&M services contract for similar efforts.
- R
Retreadfed
Nov 20, 2023 · 2y ago
On 11/17/2023 at 10:44 PM, Tzarina of Compliance said:
The work was delayed due to a potential Government shut down due to the unavailability of Government staff, but since the shutdown never happened, the GC is not agreeing to excusable delays.
I'm somewhat confused. Was the work actually delayed or is the need for the extension needed because the government has not been able to award a follow-on contract o that the extension is, in effect, a bridge contract?
- T
Tzarina of Compliance
Nov 21, 2023 · 2y ago
Retreadfed said:
I'm somewhat confused. Was the work actually delayed or is the need for the extension needed because the government has not been able to award a follow-on contract o that the extension is, in effect, a bridge contract?
It is to bridge the time before the new award is finalized.
- R
Retreadfed
Nov 22, 2023 · 2y ago
In this case, it seems to me that the government should follow the procedures for award of a sole source contract.
- f
formerfed
Nov 22, 2023 · 2y ago
I think Carl Culhane already answered this last Friday in the 3rd post in this thread. Unless I’m not fully understanding the issue, a no cost extension by mutual agreement is all that’s needed. That’s assuming existing funds are sufficient to carry work until the new contract is in place. If additional funding is needed, that portion of the extension needs documented and justified as a sole source action as Retreadfed says in the post above.
- R
Retreadfed
Nov 27, 2023 · 2y ago
On 11/22/2023 at 4:18 PM, formerfed said:
I think Carl Culhane already answered this last Friday in the 3rd post in this thread. Unless I’m not fully understanding the issue, a no cost extension by mutual agreement is all that’s needed.
I'm not so sure about this. We don't know what the contract required the contractor to do. The contractor may have completed the contract as written, but the government has not awarded a follow on contract. In this case, to me, the extension would be new work that requires a new contract.
- f
formerfed
Nov 27, 2023 · 2y ago
Retreadfed said:
The contractor may have completed the contract as written, but the government has not awarded a follow on contract. In this case, to me, the extension would be new work that requires a new contract.
If that’s the case, good point
- C
C Culham
Nov 28, 2023 · 2y ago
Retreadfed said:
I'm not so sure about this. We don't know what the contract required the contractor to do. The contractor may have completed the contract as written, but the government has not awarded a follow on contract. In this case, to me, the extension would be new work that requires a new contract.
Or a JOFOC that follows due process of synopsis and could therefore result in a modification to the existing contract. It is an available alternative approach!
- R
Retreadfed
Nov 28, 2023 · 2y ago
C Culham said:
Or a JOFOC that follows due process of synopsis and could therefore result in a modification to the existing contract. It is an available alternative approach!
Agreed. Even though the procedures for award of a sole source contract are followed, that does not mean that a new contract document needs to be created. The new contract can be added to the existing contract as a modification.
- j
joel hoffman
Nov 29, 2023 · 2y ago
On 11/28/2023 at 12:22 PM, Retreadfed said:
Agreed. Even though the procedures for award of a sole source contract are followed, that does not mean that a new contract document needs to be created. The new contract can be added to the existing contract as a modification.
But if the bonafide need for the existing funds has been satisfied, are the surplus funds still available for a new purpose in a new fiscal year?
- j
joel hoffman
Nov 29, 2023 · 2y ago · edited 2y ago
On 11/28/2023 at 9:36 AM, C Culham said:
Or a JOFOC that follows due process of synopsis and could therefore result in a modification to the existing contract. It is an available alternative approach!
But if the bonafide need for the existing funds has been satisfied, are the surplus funds still available for a new purpose in a new fiscal year?
It would seem that the next year funding, which would be available for the new year’s efforts, should be used if there is a delay in awarding the new contract for the same work that an extension of the existing contract will accomplish??
EDIT: As the Tzarina eventually explained , she wants to use leftover funding for work that was completed in the past fiscal year to fund a bridge effort in the next FY until a delayed new contract can be awarded.
- C
C Culham
Nov 30, 2023 · 2y ago
joel hoffman said:
But if the bonafide need for the existing funds has been satisfied, are the surplus funds still available for a new purpose in a new fiscal year?
Is not this almost a full circle question as one would need to know if the service is severable or not?
joel hoffman said:
It would seem that the next year funding, which would be available for the new year’s efforts, should be used if there is a delay in awarding the new contract for the same work that an extension of the existing contract will accomplish??
Yes but I do not see it an issue. Or stated another way if it is acknowledged as an out of scope add via a modification (the context in which I made my statement) does it matter where the money comes from? I do not think so but I could be convinced otherwise I guess.
- R
Retreadfed
Nov 30, 2023 · 2y ago
joel hoffman said:
But if the bonafide need for the existing funds has been satisfied, are the surplus funds still available for a new purpose in a new fiscal year?
We don't know what type of funds were used on the original contract so we can't answer that question. For example, what if the funds are no year funds?
- j
joel hoffman
Dec 1, 2023 · 2y ago
Retreadfed said:
We don't know what type of funds were used on the original contract so we can't answer that question. For example, what if the funds are no year funds?
True enough…
- j
joel hoffman
Dec 1, 2023 · 2y ago · edited 2y ago
On 11/30/2023 at 8:15 AM, C Culham said:
Is not this almost a full circle question as one would need to know if the service is severable or not?
Yes but I do not see it an issue. Or stated another way if it is acknowledged as an out of scope add via a modification (the context in which I made my statement) does it matter where the money comes from? I do not think so but I could be convinced otherwise I guess.
I agree that an out of scope mod could use whatever funds are appropriate. Yes it matters where the funds come from. The Tzarina was asking whether they could use the leftover funding. Maybe, maybe not, depending upon the type of funds left over from the completed efforts for a new effort in a new fiscal year..
- C
C Culham
Dec 1, 2023 · 2y ago
joel hoffman said:
The Tzarina was asking whether they could use the leftover funding.
Good point. Maybe its a matter for the IG as it is interesting to say the least that the contract has reached its limit on labor catagories but there is a "ton" of money left on the contract. Eithere someone is not very good at math or maybe its hidy holing some money! Lots of unanswered questions to assist in a specific answer but one could conclude that the OP (who I think is not a CO but industry) has gotten adeuqate general thougths to help solve the matter.