    Experts,

    We are currently performing under a DoD CPFF research contract. I would like to award a FFP subcontract to perform a study for us, which ideally would be over a 9 month period. However, the CPFF contract is intermittently funded, and at the time of placing the FFP subcontract, we would not have the funds for the full 9 months. Thinking outside of the box (but still within the FAR), how could I do this? Could I do it in three month periods, with two additional options? Each period would have a final report deliverable. Perhaps I could award a FFP-LOE with subclins, however I do want to avoid the impression that I'm essentially faking a T&M subcontract.

    Our contract does have FAR 52.244-2 Subcontracts (2020), and with regards to (c)(2)(I), the overall value would be less than 5% of the total cost of the contract.

  2. V

    Vern Edwards

    Jul 10, 2024 · 1y ago

    Break the study into logical phases. Award a contract for the first phase that includes priced options for each of the subsequent phases. Coordinate the conduct of each phase with your CPFF contract funding schedule. Require submission of a results/status report at the end of each phase.

  3. D

    DE13151719

    Jul 10, 2024 · 1y ago

    Thank you Vern! Hope you're doing well.

  4. R

    Retreadfed

    Jul 11, 2024 · 1y ago

    DE13151719 said:

    the CPFF contract is intermittently funded,

    What does this mean?  Is the contract an indefinite delivery contract or is it incrementally funded or something else?

  5. D

    DE13151719

    Jul 19, 2024 · 1y ago

    Retreadfed, yes I mispoke. I wrote intermittently funded when I meant incrementally funded.