Novations
Started by MWL · Jul 17, 2024 · 2 replies
- MOriginal post
MWL
Jul 17, 2024 · 1y ago
A contractor provided a list of orders/ contracts affected by a recent novation in their novation package; however, one order was omitted. If the order was not included in the original listing, does the novation cover the omitted order/contract?
- C
C Culham
Jul 18, 2024 · 1y ago
MWL said:
A contractor provided a list of orders/ contracts affected by a recent novation in their novation package; however, one order was omitted. If the order was not included in the original listing, does the novation cover the omitted order/contract?
My first thought is what does the contractor think/intend? Or in other words ask the contractor why the one order is not "in" their package.
- j
joel hoffman
Jul 18, 2024 · 1y ago
C Culham said:
My first thought is what does the contractor think/intend? Or in other words ask the contractor why the one order is not "in" their package.
Yes, I’d start there first. That ought to be obvious.
Of course, I realize that direct communications (especially oral communications) between contract administrators/KO and contractors is often an anomaly these days.