Change from G&A to Direct Charge
Started by Sheri Jordan · Nov 7, 2024 · 3 replies
- SOriginal post
Sheri Jordan
Nov 7, 2024 · 1y ago
We are looking to change our finance analysts and contracts team to direct charge from G&A. What steps need to be taken to accommodate this change - any feedback is welcomed
- h
here_2_help
Nov 7, 2024 · 1y ago
Are you CAS-covered?
Do you have a Disclosure Statement?
If you make the change, what is the impact to existing contracts where you didn't bid the efforts as direct labor and, therefore, do not have budgets established?
- R
Retreadfed
Nov 11, 2024 · 1y ago
Sheri, Have you considered FAR 31.202 and 203 as well as 31.201-4 to determine if this change is consistent with the regulations?
- h
here_2_help
Nov 12, 2024 · 1y ago
Rule 17?