Multi-year Contracts Cancellation fee
Started by Locke · Sep 13, 2013 · 2 replies
- LOriginal post
Locke
Sep 13, 2013 · 12y ago
If you have a multi-year contract for three years for the initial performance and include two option years to round out the 5 year PoP, does the cancellation fee only apply for the program years 2 and 3?
FAR Clause 52.217-2(d)states:
(1) Cost--
(i) Incurred by the Contractor and/or subcontractor;
(ii) Reasonably necessary for performance of the contract; and
(iii) That would have been equitably amortized over the entire multi-year contract period but, because of the cancellation, are not so amortized; and
(2) A reasonable profit or fee on the costs.
* Does over the entire multi-year contract period include any options or just the program years?
- N
Navy_Contracting_4
Sep 13, 2013 · 12y ago
Yes, the cancellation charge will only apply for program years 2 and 3.
You say you have a 3-year multi-year, so "over the entire multiyear contract period" includes only the period for those three years of requirements. The options are beyond the "multiyear period."
- L
Locke
Sep 14, 2013 · 12y ago
Thank you.
That was my assumption.