Firm-fixed-price, level-of-effort term contracts

Started by rae.story · Oct 16, 2013 · 1 replies

  1. r

    rae.story

    Oct 16, 2013 · 12y ago

    Original post

    I am attempting to validate as to whether or not a Prime, if awarded a FFP contract, may issue a FFP-LOE SubK knowing the work that is to be performed by the subcontractor will exceed the $150k limitation per FAR 16.207.3 (Limitations of firm-fixed-price, level-of-effort term contracts)?

    Thank you in advance for your time.

  2. G

    Guest Vern Edwards

    Oct 17, 2013 · 12y ago

    The limitation in FAR does not apply to contractors and to the award of subcontracts. It limits the Government's use of FFP-LOE contracts, not a contractor's use.