Is this a claim?
Started by Don Mansfield · Mar 19, 2014 · 38 replies
- DOriginal post
Don Mansfield
Mar 19, 2014 · 12y ago
Is this a claim?
“This letter serves as our request for cost modification in the amount of $50,325.00 for extended overhead due to delays outlined in our request for time extension letters dated 25 February 2005.”
That's all. Don't look up or cite any cases, just look at the statement and compare it to the definition of "claim":
“Claim” means a written demand or written assertion by one of the contracting parties seeking, as a matter of right, the payment of money in a sum certain, the adjustment or interpretation of contract terms, or other relief arising under or relating to the contract. However, a written demand or written assertion by the contractor seeking the payment of money exceeding $100,000 is not a claim under the Contract Disputes Act of 1978 until certified as required by the Act. A voucher, invoice, or other routine request for payment that is not in dispute when submitted is not a claim. The submission may be converted to a claim, by written notice to the contracting officer as provided in 33.206(a), if it is disputed either as to liability or amount or is not acted upon in a reasonable time.
- G
Guest jrt132
Mar 19, 2014 · 12y ago
Yes based on the definition of a claim. The request is a written demand seeking payment of a certain sum. The request is using delays as the "matter of right."
- C
Cajuncharlie
Mar 20, 2014 · 12y ago
Maybe I'm quibbling, but I respectfully disagree with jrt132 based on the plain meaning of the words in the letter. This is, by its own terms, a "request" and neither a "demand" nor an "assertion." The contractor is asking, not insisting and not telling.
With almost no context, it's a tough call, but I would say it could go either way. A key question is: does the Contracting Officer want to handle it as a claim or not?
On one hand, if a contractor wants to submit a claim, it is incumbent on the contractor to make its case using clear, explicit, and unambiguous language. This letter doesn't quite get there. In my experience it's best to write to a Contracting Officer using words straight out of the contract clauses and the governing FAR guidance, framing the issues in terms I choose, to point toward an answer I want.
On the other hand, this letter is a follow-up to previous requests, so it could be seen as taking the situation out of the land of equitable adjustments and into the land of claims, possibly imposing a duty on the Contracting Officer to handle it as a claim, or maybe simply motivating the Contracting Officer to close this matter with a Final Decision.
Either way, I would document the file with my take on the request and the reasons for it, and go from there.
Before documenting the file, my next step would be, as is my wont, to look this up, first to RTFC (in polite language, read the f-f-f-full contract), then the pertinent points in the rest of the FAR and any applicable agency supplements, and if that's not enough, hit the rest of the books. But that's beyond the scope of this discussion.
- j
joel hoffman
Mar 20, 2014 · 12y ago
This is not a routine request for payment. It may be a trick question due to the fact that the request is based upon letters that are dated 2005, which is over 9 years ago. Assuming that the dates are not relevant here for Don's question and assuming that there hasn't been some recent case law that redefines a claim, I think that this is a claim. See this archived thread from the Forum in 2000 at /legacy/reg/6c8da9854e149cf4.html
Ok, Don said not to look up any cases but to just look at the definition. Assuming that the dates matter, It may be a continuing chain of correspondence for a nine year old claim or it may be an attempt to claim nine years after the fact.
- j
ji20874
Mar 20, 2014 · 12y ago
My first thought? Not a claim...
Like Cajuncharlie, it is a request, not a demand or assertion. But even though it is styled as a request, it might stil be a claim depending on the history.
If there is no history, and if this submission came in out of the blue, so to speak, well, the matter of right is not is not established. If the contractor's right to payment is covered by a contract clause, one supposes the "claim" would reference that clause. Is the entitlement under the Government Delay of Work clause? The "claim" doesn't establish this as its matter of right. If it did, para. ( B ) of the clause at FAR 52.242-17 might preclude payment.
Was the matter in dispute when the submission was made? If not, this isn't a claim.
Given no other information, as a contracting officer I would try to discern if maybe this is merely an issue in controversy, as that term is defined in FAR Subpart 33.2.
- G
Guest Vern Edwards
Mar 20, 2014 · 12y ago
I've always said that the average CO wouldn't know and be able to acknowledge a claim if it jumped up and bit him on the butt. Right again.
There's no trick. Read Don's instruction: "[J]ust look at the statement and compare it to the definition of 'claim'," because that's what the courts and boards do and so should COs, since the definition is in every contract that includes the Disputes clause, and is contractually binding.
- G
Guest Vern Edwards
Mar 20, 2014 · 12y ago
Yes based on the definition of a claim. The request is a written demand seeking payment of a certain sum. The request is using delays as the "matter of right."
The letter is not seeking payment. It is asking for an adjustment to the contract price.
- G
Guest Vern Edwards
Mar 20, 2014 · 12y ago
A key question is: does the Contracting Officer want to handle it as a claim or not?
A CO doesn't get to choose how to handle it. If it's a claim, then the CO must handle it as a claim, because he's contractually obligated to do so. If it's not a claim, then he need not handle it as a claim.
- G
Guest Vern Edwards
Mar 20, 2014 · 12y ago
See this archived thread from the Forum in 2000 at /legacy/reg/6c8da9854e149cf4.html
Ok, Don said not to look up anything but to just looks at the definition.
He violates Don's instruction in one sentence then reminds us of it in the next.
- D
DingoesAteMyBaby
Mar 20, 2014 · 12y ago
I would say no, it is not a claim, but quite close. Well, it doesn't appear to me that it requests a decision of the Contracting Officer, which is something that I typically expect to see in a claim. Although implicit by the fact that they sent a letter, when it comes down to it, they don't actually request a Contracting Officer's decision.
- G
Guest Vern Edwards
Mar 21, 2014 · 12y ago
Does anyone read books about our work? Like, say, Administration of Government Contracts, 4th ed.?
- j
joel hoffman
Mar 21, 2014 · 12y ago
It isn't a claim if the contractor didn't request the cost modification for more than 9 years after it requested a time extension in February 2005, which is most likely more than 6 years after the accrual of the "claim". It is now March 2014. There is no other information provided to assume when the claim was submitted.
Don provided this link in his initial post: 3.206(a), which is "Initiation of a Claim".
"(a) Contractor claims shall be submitted, in writing, to the contracting officer for a decision within 6 years after accrual of a claim, unless the contracting parties agreed to a shorter time period. This 6-year time period does not apply to contracts awarded prior to October 1, 1995. The contracting officer shall document the contract file with evidence of the date of receipt of any submission from the contractor deemed to be a claim by the contracting officer."
- G
Guest Vern Edwards
Mar 21, 2014 · 12y ago
Don said to compare the letter to the definition of claim.
Does the definition of claim say anything about a written demand or assertion having to be submitted to the CO within a specified period of time? No.
Does FAR 33.206 say that a written demand or assertion that meets the criteria for a claim in the definition of claim is not a claim if not submitted within six years after accrual? No.
It might be an untimely claim, or late claim, but if it meets the criteria in the definition it's a claim.
- R
Retreadfed
Mar 22, 2014 · 12y ago
Vern, going back to your post #7, if this is a claim seeking the adjustment of contract terms, would this claim have to be certified?
- G
Guest Vern Edwards
Mar 22, 2014 · 12y ago
Retread:
Yes, it would have to be certified, but not based on the language of the FAR definition. The FAR definition says that demands or assertions "seeking the payment of money" have to be certified, thus, the plain language excludes demands or assertions for price adjustments.
But the Contract Disputes Act of 1978 does not use the phrase "seeking the payment of money", and it does not say that a written demand or request exceeding $100,000 is not a claim until certified. The statute, at 41 U.S.C. § 7103( b ), says:
( b ) Certification of Claims.—
(1) Requirement generally.— For claims of more than $100,000 made by a contractor, the contractor shall certify that—
(A) the claim is made in good faith;
( B ) the supporting data are accurate and complete to the best of the contractor’s knowledge and belief;
( C ) the amount requested accurately reflects the contract adjustment for which the contractor believes the Federal Government is liable; and
(D) the certifier is authorized to certify the claim on behalf of the contractor.
(2) Who may execute certification.— The certification required by paragraph (1) may be executed by an individual authorized to bind the contractor with respect to the claim.
(3) Failure to certify or defective certification.— A contracting officer is not obligated to render a final decision on a claim of more than $100,000 that is not certified in accordance with paragraph (1) if, within 60 days after receipt of the claim, the contracting officer notifies the contractor in writing of the reasons why any attempted certification was found to be defective. A defect in the certification of a claim does not deprive a court or an agency board of jurisdiction over the claim. Prior to the entry of a final judgment by a court or a decision by an agency board, the court or agency board shall require a defective certification to be corrected.
See also FAR 33.207(a) which requires certification of "any claim" exceeding $100,000, and the Disputes clause, FAR 52.233-1(d)(2)(i), which requires certification of "any claim" exceeding $100,000.
So, according to the statute and other sections in FAR, any written demand or request stated in monetary terms in excess of $100,000, whether for payment or price adjustment, must be certified before the CO is obligated to render a final decision.
The definition of claim in FAR is inexplicable. The courts have added to the confusion by issuing carelessly written decisions. For a superb discussion of the problem of defining "claim", see "A Retrospective on the Contract Disputes Act," by W. Stanfield Johnson, Public Contract Law Journal (Summer 1999), 28 Pub. Cont. L.J. 567. In that article, Stan pointed out that 20 years after the enactment of the CDA, "Affter repeatedly revisiting the subject in litigation, regulation, and statutory amendment, we are still not completely certain what 'claim' means."
I'm pretty certain that I know what it means, because I have steeped myself in the case law and can read plain English. But I can tell you that most COs and contractors don't have a clue, which is why the issue keeps coming up in court and why Don started this thread. But I'm going to let him answer his own question and wrap things up.
- T
TAP
Mar 24, 2014 · 12y ago
No, it appears to be a REA rather than a claim.
- C
C Culham
Mar 24, 2014 · 12y ago
A claim only if submitted by the prime contractor or the Government to the other party.
Written demand or assertion – Yes
By prime or Government – Unknown
Sum Certain - Yes
Relief pursuant to terms of the contract - Yes
Certification - Not required per the “claim” definition clause
- G
Guest Vern Edwards
Mar 24, 2014 · 12y ago
No, it appears to be a REA rather than a claim.
The REA/claim distinction is false. There is no categorical difference between an REA and a claim. An REA that meets all of the criteria for a claim is an REA that's a claim. An REA that does not meet any of the criteria is an REA that is not a claim. That has been long and well-established in the case law.
There are some who think that an REA that meets the criteria for a claim should not be called an REA. That is perhaps sound advice, but that's all it is -- advice.
- T
TAP
Mar 24, 2014 · 12y ago
Our command's process for REAs states; "Verify that Contractor's letter clearly states that the request is an REA (versus a contract claim)." And, "Immediately obtain written clarification from the Contractor if the Contractor’s letter does not clearly identify whether the request is an REA or a claim." Also, DFARS 243.204-70 talks about converting the request (REA) to a claim under the contract disputes act.
Maybe it's a distinction without a difference? But unless I knew the contractor's intent was to file a claim and that there was an actual dispute, I would have assumed it was a REA. You learn something new every day.
Thanks Vern!
- D
Don Mansfield
Mar 24, 2014 · 12y ago
The Court of Federal Claims said that it was a claim. See K-CON Building Systems, Inc., v. U.S. In relevant part:
In granting plaintiff’s motion, the court rejects defendant’s contention that the court lacks jurisdiction over plaintiff’s proposed claim. Specifically, defendant argues that plaintiff’s February 25, 2005 request for a price adjustment cannot constitute a valid claim under the CDA because plaintiff did not, in its letter, make a demand or indicate that it was seeking a final decision from the contracting officer. Defendant’s interpretation of the CDA’s requirements is too narrow. According to binding Federal Circuit precedent, there is “no requirement in the [CDA] that a ‘claim’ must be submitted in any particular form or use any particular wording.” Contract Cleaning Maint., Inc., 811 F.2d at 592; see also Transam. Ins. Corp. v. United States, 973 F.2d 1572, 1578 (Fed. Cir. 1992) (noting that “certain ‘magic words’ need not be used and that the intent of the ‘claim’ governs”). “All that is required is that the contractor submit in writing to the contracting officer a clear and unequivocal statement that gives the contracting officer adequate notice of the basis and amount of the claim.” Contract Cleaning Maint., Inc., 811 F.2d at 592. Thus, the contractor’s request for a decision from the contracting officer need not be explicit; it may be implied. James M. Ellett Constr. Co. v. United States, 93 F.3d 1537, 1543 (Fed. Cir. 1996); see also Transam. Ins. Corp., 973 F.2d at 1576 (“The statute’s broad language demonstrates that as long as what the contractor desires by its submissions is a final decision, that prong of the CDA claim test is met.”). Although plaintiff’s February 25, 2005 letter is terse, plaintiff clearly indicates that it is a “request” for extended overhead based on the delays it alleged in its other three February 25, 2005 letters. Not only is plaintiff’s “request” tantamount to a demand, but any reasonable contracting officer receiving plaintiff’s letter would have interpreted it as a request for a decision regarding plaintiff’s entitlement to extended overhead. In fact, it bears noting that Ms. Hundley rendered decisions in response to plaintiff’s other three February 25, 2005 letters, all of which contained language similar to the letter at issue (each of the three letters began, “[t]his letter serves as our request for time extension,” and each concluded, “[t]herefore [plaintiff is] requesting a non-compensable time extension” ).
- G
Guest Vern Edwards
Mar 24, 2014 · 12y ago
Our command's process for REAs states; "Verify that Contractor's letter clearly states that the request is an REA (versus a contract claim)." And, "Immediately obtain written clarification from the Contractor if the Contractor’s letter does not clearly identify whether the request is an REA or a claim." Also, DFARS 243.204-70 talks about converting the request (REA) to a claim under the contract disputes act.
Maybe it's a distinction without a difference? But unless I knew the contractor's intent was to file a claim and that there was an actual dispute, I would have assumed it was a REA. You learn something new every day.
Thanks Vern!
Actually, your command has issued an excellent instruction, and here's why it's excellent: Most contractors don't know the difference between an REA that is a claim and an REA that is not a claim. Many mistakenly think that there is a categorical difference. It's important that they know, because if they submit an REA that is a claim they cannot charge claim preparation and legal costs to the Government, see FAR 31.205-47(f)(1). But if they submit an REA that is not a claim, then they can charge those costs to the Government.
If a contractor writes a letter to a CO asking for a monetary equitable adjustment in an amount of $100,000 or less, the letter might meet all of the criteria for a claim, but the contractor might not have intended to submit a claim. (A claim does not have to say that it is a claim.) If the letter seeks more than $100,000, then the CO does not have to treat it as a claim, even if the letter says it is a claim, unless the contractor certifies it as a claim. If the contractor certifies it as a claim, then the contractor's intent should be pretty clear.
What I tell COs is that when they get a letter seeking an equitable adjustment that meets all the criteria of a claim, including certification, and if they are not sure that the contractor understands what a claim is and what the cost consequences are of submitting a claim, then the CO should contact the contractor to verify that they intended to submit a Contract Disputes Act claim. The CO should explain why he's asking, pointing out that if submitting a claim they cannot charge claim preparation costs and associated legal costs to the Government. (At today's interest rates, those costs might easily exceed any interest earned on the claim.) The CO should handle it as a claim until told that the contractor had not intended to submit one. If the contractor says that they had not intended to submit one, then the CO should ask for immediate confirmation in writing and continue treating it as a claim until he receives the confirmation. You probably don't have to do that with Lockheed or Boeing, but you ought to do it with smaller companies who might not know the ropes.
A dispute is not a prerequisite to a claim, unless the contractor has submitted an invoice, voucher, or other routine request for payment. REAs are not routine requests for payment. See Reflectone v. Dalton, 60 F.3d 1572 (Fed. Cir. 1995). Claim and dispute are not synonymous.
- D
DingoesAteMyBaby
Mar 25, 2014 · 12y ago
So does the statement in question provided by Don demand or indicate that the entity is seeking a final decision from the contracting officer?
It does not, therefore it is not a claim. It is a request for equitable adjustment, based on what authority for such an adjustment, I have no idea because that is not stated.
I would be cautious calling the Contractor to ask them what they intend, especiall because of the direction that the conversation could take. I'm not in the business of advising the Contractor of the finer points of writing their claims or REAs. Perhaps at some point in private employment I will have that opportunity.
I had a similar incident occur, except that the letter I received was for a sum certain amount over $100K, it included the certification language, and it cited the contract's "Notification of Changes" clause as the authority for what it was seeking. Their initial submission did not state either way that it was an REA or a claim, although it had all but one component. What it was lacking was a request for a written decision by the Contracting Officer, however, it was implied. By default I sent a letter to the Contractor informing them that I was in receipt of their claim and that they would receive a written decision from the Contracting Officer no later than a date certain; they replied with 'wait, wait, wait, this is an REA, not a claim'. I amended the letter to the Contractor, and the Government processed it as an REA. The reason that the Contractor wanted an REA rather than a claim was so that the Contractorould negotiate the adjustment with the Government rather than just receive a decision. Fair enough. The understanding was that at any time they could request a written Contracting Officer's decision within 60 days, which would trigger me to set a date certain for a later date, and that by that date the Contracting Officer's written decision would be issued.
Quite the dicey process.
The Court of Federal Claims said that it was a claim. See K-CON Building Systems, Inc., v. U.S. In relevant part:
Quote
In granting plaintiff’s motion, the court rejects defendant’s contention that the court lacks jurisdiction over plaintiff’s proposed claim. Specifically, defendant argues that plaintiff’s February 25, 2005 request for a price adjustment cannot constitute a valid claim under the CDA because plaintiff did not, in its letter, make a demand or indicate that it was seeking a final decision from the contracting officer. Defendant’s interpretation of the CDA’s requirements is too narrow. According to binding Federal Circuit precedent, there is “no requirement in the [CDA] that a ‘claim’ must be submitted in any particular form or use any particular wording.” Contract Cleaning Maint., Inc., 811 F.2d at 592; see also Transam. Ins. Corp. v. United States, 973 F.2d 1572, 1578 (Fed. Cir. 1992) (noting that “certain ‘magic words’ need not be used and that the intent of the ‘claim’ governs”). “All that is required is that the contractor submit in writing to the contracting officer a clear and unequivocal statement that gives the contracting officer adequate notice of the basis and amount of the claim.” Contract Cleaning Maint., Inc., 811 F.2d at 592. Thus, the contractor’s request for a decision from the contracting officer need not be explicit; it may be implied. James M. Ellett Constr. Co. v. United States, 93 F.3d 1537, 1543 (Fed. Cir. 1996); see also Transam. Ins. Corp., 973 F.2d at 1576 (“The statute’s broad language demonstrates that as long as what the contractor desires by its submissions is a final decision, that prong of the CDA claim test is met.”). Although plaintiff’s February 25, 2005 letter is terse, plaintiff clearly indicates that it is a “request” for extended overhead based on the delays it alleged in its other three February 25, 2005 letters. Not only is plaintiff’s “request” tantamount to a demand, but any reasonable contracting officer receiving plaintiff’s letter would have interpreted it as a request for a decision regarding plaintiff’s entitlement to extended overhead. In fact, it bears noting that Ms. Hundley rendered decisions in response to plaintiff’s other three February 25, 2005 letters, all of which contained language similar to the letter at issue (each of the three letters began, “[t]his letter serves as our request for time extension,” and each concluded, “[t]herefore [plaintiff is] requesting a non-compensable time extension” ).
- G
Guest Vern Edwards
Mar 25, 2014 · 12y ago
So does the statement in question provided by Don demand or indicate that the entity is seeking a final decision from the contracting officer?
It does not, therefore it is not a claim.
Gee, Dingoes, did you miss the part in the quote Don provided from the court decision in which the court said:
Thus, the contractor’s request for a decision from the contracting officer need not be explicit; it may be implied.
and then found that the request was implicit and that a reasonable CO would find it so? Or are you just ignoring it? Or do you not know the meaning of implicit?
In case that quote isn't clear enough for you, here is one from the Federal Circuit Court of Appeals:
To be a claim under the CDA, the submission must request a “final decision.” See Ellett, 93 F.3d at 1543. A request for a “final decision,” however, need not be “explicit.” Id. That the contractor intended to make such a request could be “ ‘implied from the context of the submission.’ ” Id. (quoting Heyl & Patterson v. O;Keefe, 986 F.2d 480, 483 (Fed.Cir.1993)).
Rex Systems, Inc. v. Cohen, 224 F.3d 1367 (Fed. Cir. 2000). See, too, Cibinic, Nash and Nagle, Administration of Government Contracts 4th, pp. 1267 - 68:
The requirement that the contractor request a contracting officer decision is in neither the CDA nor the FAR but rather derives from case law… The request for a decision may be either explicit or implied.
Now, do you disagree with the Court of Federal Claims or the Federal Circuit Court of Appeals or both, or do you think that the letter did not even request a decision implicitly?
The only thing that makes the process dicey is that so many people involved in it don't know the law and refuse to learn. Actually, the process could not be simpler.
- D
Don Mansfield
Mar 25, 2014 · 12y ago
(legacy post)
- R
Retreadfed
Mar 25, 2014 · 12y ago
Going back to Tap's posts, another point to keep in mind for DoD contracts is the requirement that REAs above the SAT require certification in accordance with DFARS 252.243-7002. This is a different certification than the one required for a claim. If a contractor submits an REA with the REA certification, then wishes to convert the REA to a proper Disputes clause claim, it must recertify using the Disputes clause certificate.
- G
Guest Vern Edwards
Mar 25, 2014 · 12y ago
If the contractor submits an REA that's a claim, it must make both certifications, because they are different. I know of no regulation, policy, or ruling to the contrary.
If he submits an REA that is not a claim he must make the REA certification. If he decides to convert the non-claim REA to a claim, then he must make the claim certification. He doesn't "recertify".
- D
DingoesAteMyBaby
Mar 25, 2014 · 12y ago
You're right Vern, I mis-spoke when I stated "It does not, therefore it is not a claim. It is a request for equitable adjustment, based on what authority for such an adjustment, I have no idea because that is not stated." I will now back-pedal, but not much.
This is a very interesting case. I'm actually glad to have it.
When it comes down to it I acted as I did previously, in part, because of "The Claim Problem Decision Table" that's a part of The FAR Bootcamp curriculum. Step 19 states that if the Contractor has not requested a decision by the Contracting Officer then the submission is not a claim. The basis stated for this discriminator is that "Case law requires that in order for a demand or assertion to be a claim the contractor must request a decision by the contracting officer. See Cibinic, et al., Administration of Government Contracts, 4th ed., pp. 1267-1269. The request may be explicit or implied." While I had conducted a great deal of research which led to treating the submission as a claim, this decision table really caused me issue because it led me to believe that the implied request was not patently obvious and you really had to reach to determine that the letter implied a decision when in fact I knew that the Contractor did not want a written decision based upon previous discussions with the Contractor. Probably a stronger caviat in the decision table should be placed on that decisional discriminator. My interpretation at that time was that the definition of "implied" is different than is stated in this recent case:
“All that is required is that the contractor submit in writing to the contracting officer a clear and unequivocal statement that gives the contracting officer adequate notice of the basis and amount of the claim.” Contract Cleaning Maint., Inc., 811 F.2d at 592. Thus, the contractor’s request for a decision from the contracting officer need not be explicit; it may be implied. James M. Ellett Constr. Co. v. United States, 93 F.3d 1537, 1543 (Fed. Cir. 1996); see also Transam. Ins. Corp., 973 F.2d at 1576 (“The statute’s broad language demonstrates that as long as what the contractor desires by its submissions is a final decision, that prong of the CDA claim test is met.”).
Knowing now what I did not know then, I would have still sided with caution and considered the submission to be a claim and allow the Contractor to come back and tell me in writing that he is not seeking a written decision, instead, he is seeking to negotiate.
- G
Guest Vern Edwards
Mar 25, 2014 · 12y ago
Dingoes:
Here is the letter that Don quoted:
This letter serves as our request for cost modification in the amount of $50,325.00 for extended overhead due to delays outlined in our request for time extension letters dated 25 February 2005.
The writer says he's requesting something and says what he wants. In order for him to get what he wants, the CO will have to make a decision. Right? Doesn't that imply (indicate by suggestion rather than explicit reference) that he wants the CO to make a decision? Wouldn't it be reasonable to think so?
Now, a CO who is familiar with the case law should know that implication is enough to satisfy the requirement for a request for a decision. Since the request is for less than $100,000, it need not be certified, so there is room for doubt about the contractor's intentions. It seems to me that a knowledgeable CO would think: I wonder if this guy really wants a final decision. I suspect that he does not understand my problem, which is that while I'm legally compelled to treat it as a claim, I'd rather not be up against a deadline and have to pay interest. I mean, how much can claim prep costs be for a $50,000 claim. I think I'll call the guy and ask him what his intentions are. I may have to explain the consequences of making a claim instead of an REA that's not a claim.
I think you did the right thing in making the inquiry. That's what I think any good CO would have done.
P.S. The Bootcamp decision table does not tell you everything, because we want you to read the references that we provide.
- j
joel hoffman
Mar 25, 2014 · 12y ago
From the limited information that Don initially provided, I'm not sure that "any reasonable contracting officer" would have recognized it in this instance as a request for a CO Decision regarding entitlement to extended overhead. The context of that statement in the quoted Court Decision suggested to me that it meant "all reasonable CO's" should have recognized the "request for a cost modification" as a request for a CO decision.
The Court said, in part: "Thus, the contractor’s request for a decision from the contracting officer need not be explicit; it may be implied. James M. Ellett Constr. Co. v. United States, 93 F.3d 1537, 1543 (Fed. Cir. 1996); see also Transam. Ins. Corp., 973 F.2d at 1576 (“The statute’s broad language demonstrates that as long as what the contractor desires by its submissions is a final decision, that prong of the CDA claim test is met.”). Although plaintiff’s February 25, 2005 letter is terse, plaintiff clearly indicates that it is a “request” for extended overhead based on the delays it alleged in its other three February 25, 2005 letters. Not only is plaintiff’s “request” tantamount to a demand, but any reasonable contracting officer receiving plaintiff’s letter would have interpreted it as a request for a decision regarding plaintiff’s entitlement to extended overhead. In fact, it bears noting that Ms. Hundley rendered decisions in response to plaintiff’s other three February 25, 2005 letters, all of which contained language similar to the letter at issue (each of the three letters began, “[t]his letter serves as our request for time extension,” and each concluded, “[t]herefore [plaintiff is] requesting a non-compensable time extension” )."
1. There was no indication that the letter that Don originally referred to directly tied to THREE other letters dated the same as the request for a cost modification.
2. Please note that each of the thee other letters, per the Court Decision, "requested a non-compensable time extension". Is there some mistake in that quote? A non-compensable time extension does not usually entitle a contractor to recover extended overhead, as compensation.
3. I don't think, in reading the letter by itself, that it is clearly a "terse" letter. The Merriam-Webster on-line Dictionary uses the definition of terse as "brief and direct in a way that may seem rude or unfriendly".
4. The Court stated that the CO rendered decisiions on each of the other letters of the same date. That wasn't evident in the original question posed here.
5. Those are all facts that were revealed in the Court's Decision.
From my personal perspective, since the mid-1990's, I am used to dealing with many more construction contractors that deliberately avoid submitting claims for various reasons. One is the reason that Vern described in post #21 of not being able to recover claim preparation and legal costs.
Another reason is that since the mid-1990's, most of our contractors participate in formal "Partnering" with the government, wherein both sides make concerted efforts to resolve issues before they become claims or disputes.
Many of our contracts also began including Alternatative Dispute Resolution clauses, which provided for arbitration or other collaberative processes as alternatives to resorting to final decisions under the CDA.
Many of our contractors only elevate an issue to the status of a "claim" as a last effort or when the government refuses to timely resolve or respond to the issue because they want to avoid any impression of being considered a claim's artist, difficult to deal with. etc. Reputations and client relations are often extremely important with our construction contractors.
When the USACE transitioned from primarily using IFB's to best value RFP's, Partnering and Alternate Disputes, there was a large reduction in the numbers of "claims", each of which are tracked as recordable metrics by USACE.
I tend to agree that a CO should attempt to deterrmine the intent of the contractor. However, I do not think that any US Government employee should coach or otherwise advise a contractor on how they can maximize their monetary recovery by either making an issue a claim and requesting a CO decision or by just calling it a (non-claim) REA. I think that we were taught in our government ethics training that this is not legal.
Don has tried to provide good teaching points here. However, did the information initially presented in that post - on its own - demonstrate to a reasonable CO that the contractor implicitly desired or requested, by its submission of that letter, a final CO decision? We have more information to draw upon at this point. It might reasonably depend upon facts that were not evident until we read the quote from the Court Decision or it may also depend upon the CO's or the organization's experience and perspective. All we knew for sure was that the request for a monetary adjustment was not a routine request for payment. A routine request for payment would not be considered a claim on its own but could be converted to one.
EDIT: I posted this prior to seeing post number 28 above, so it is not in response to that post.
- G
Guest Vern Edwards
Mar 25, 2014 · 12y ago
Joel:
Don's teaching point was: read the definition.
The definition of claim has not changed in 20 years. The case law about what is and what is not a claim has been known for quite a while now. It is inexcusable that people who are empowered to make final decisions on claims don't know that case law and can't recognize a claim.
One of the earliest responses to the question said it's not a claim because it's a request, not a demand or assertion. Demand or assertion are legal terms of art and a visit to Black's Law Dictionary would have shown that a demand is simply a request made as a matter of right. In any case, the ASBCA said BACK IN 1993:
[T]he threshold question is whether that submission constituted a “claim” under the CDA. To that end, it does not matter if the submission is styled as a “claim,” a “proposal,” a “request for equitable adjustment,” or something else. What matters is that the submission satisfies the definition of “claim” prescribed in applicable implementing regulations and contract clauses, as interpreted by the Federal Circuit.
Nor does the word “request” preclude a document's status as a claim. See Zafer, stating:
The government objects [the contractor's] 1 August 2007 REA as the basis for our jurisdiction, alleging that the document is a preliminary request for equitable adjustment, and does not adhere to CDA certification requirements because “request” is twice substituted for “claim” and the authority of the certifier is not stated. We find that the REA is a cognizable claim, as it adequately informs the government of the basis and precise amount of the claim and that the use of the word “request” in lieu of “claim” is inconsequential.
See Saco Defense, Inc., ASBCA 44792, 93-3 BCA ¶ 26029. That decision is still "good law".
The rest of the "no" responses were wrong either because they applied criteria that were not in the definition or because the author did not know the case law.
There is no excuse for a CO or contract specialist who cannot recognize a claim when he or she sees it. Study, dammit. Read books. Read cases. Or give back the certificate of appointment.
- j
joel hoffman
Mar 25, 2014 · 12y ago
I read the Case. The significance of the fourth letter as a claim was primarily related in this Decision to whether or not the Coast Guard had the authority to terminate an order under a FSS contract of the GSA. The Court was not determining the merits of the claim itself. The Court didn't dwell on the apparent discrepancy between three letters seeking non-compensable time extensions and a fourth letter seeking monetary adjustment for the reasons set forth in the other letters.
EDIT: This post is a followup to my post #29. The Court Decision, when put in context of what all happened - the contractor had been terminated for cause for gosh sakes - would certainly indicate that the CO should have considered it a claim.
- j
joel hoffman
Mar 25, 2014 · 12y ago
In response to post 30, I still feel that my points raised in my post 29 are also valid. Inasmuch as only 15 minutes transpired between my post and the lengthy, rather passionate response, I wonder if you really read my post from my perspective.
- G
Guest Vern Edwards
Mar 25, 2014 · 12y ago
I read it. It doesn't take me long to read stuff like that and to write a response.
My only interest is the responses to Don's question. I have no interest in revisiting the case in question. It was a simple decision, based on well-established legal principles, and we did not need it in order to answer correctly that the letter was a claim. It did not make new law. I knew my answer before I knew there had been a decision. I guessed that there had been one and found it within about 30 minutes.
We only needed the decision in order to be able to convince those who thought it was not a claim because REAs and claims are different things, or because it was a request, not a demand or assertion, or because it was not submitted within six years of its accrual, or because it did not request a CO decision. The only person who raised a legitimate issue was Carl Culham, who questioned whether it had been submitted by a party to the contract. Don had neglected to make it clear in his opening post that the letter was from the prime contractor. None of the facts you cited had any bearing on the answer to Don's question.
I am bothered by one part of your long post:
I do not think that any US Government employee should coach or otherwise advise a contractor on how they can maximize their monetary recovery by either making an issue a claim and requesting a CO decision or by just calling it a (non-claim) REA. I think that we were taught in our government ethics training that this is not legal.
I don't think it is wrong for a CO to explain to a contractor the alternative consequences of two possible courses of action, which is what I suggested. The clauses in government contracts and the procurement regulations are written by the government. As the only government representative empowered to interpret the contract, the contracting officer owes a contractor that kind of explanation. I don't think the CO should urge one course or the other, which I did not suggest, but there is nothing illegal about explaining the consequences of a choice. If there were more COs like that, there would be less litigation and less litigation cost.
- j
ji20874
Mar 25, 2014 · 12y ago
I don't think there is a clear teaching point.
If I read the damned definition, to use Vern's words, and a letter meets the definition of a claim, then I must process it as a claim...
But wait, wait, maybe I should ask the contractor first to make sure the letter was intended as a claim? If the above sentence is true, why should I bother asking the contractor? Well, for the good reasons Vern provides.
We ask the question because we know from experience that every request of the sort we're talking about is not intended to be a claim. Some are, some aren't. In cases like this, the proof seems to be in the contractor's intent rather than the form of the request letter.
- G
Guest Vern Edwards
Mar 25, 2014 · 12y ago
Actually, if you read the cases, the contractor's intent is very important.
The only time you really have to ask is with respect to requests of $100,000 or less and non-monetary requests, which don't have to be certified. The criteria for a claim are not very demanding -- a short email might be a claim. The contractor might intend it to be a claim and he might not. It's reasonable to ask the contractor its intentions, because it (like so many COs) it might not know a claim when it sees one, and might not know the consequences of the difference. If you're the CO, you might be happy to learn that you don't have to issue a decision within a deadline -- 60 days or a reasonable time.
If a request exceeds $100,000, then it must be certified, and if it isn't it need not be treated as a claim. That should be clear even to ignorant and inexperienced contractors and COs.
- j
joel hoffman
Mar 26, 2014 · 12y ago
If Don's teaching point is only to read the definition, then determine if a one line letter requesting a cost modification is a claim, I don't agree with the teaching point. It isn't enough. The Decision itself required more than simply reading the definition and applying it to the one line letter that had little or no context. The Court stated that the "claim test" also included this: “The statute’s broad language demonstrates that as long as what the contractor desires by its submissions is a final decision, that prong of the CDA claim test is met.” Then the Court explained the clear relationship of the letter to the other contemporaneous letters that did request entitlement, which were treated as claims and which did result in CO decisions. Thus, the letter was directly related to other claims and now requested money in addition to no cost time extensions separately requested.
It was not clear to me from the letter that Don quoted in post #1 that the contractor was requesting a CO decision concerning entitlement to a time extension. We did not know wheher or not the Government had already agreed to entitlement to time extension(s) from the "request for time extension letters dated 25 February 2005", nor did we have any knowledge of the time between the requests for time extension(s) and the letter which contained the quantification. We didn't know if the contractor was just providing the amount in response to a request by the government after deciding entitlement. The other letters may have been in response to a government request to resolve schedule issues. Thus, we had no way of knowing if those other letters constituted a claim(s).
The only thing that I was pretty sure of. without further information, was that this was not "a voucher, invoice, or other routine request for payment that is not in dispute when submitted. Thus, it could have been a claim per the definition.
I suggested asking the contractor to clarify if it was a claim or not, in part for the same reason Vern used in post #28 when he said "Since the request is for less than $100,000, it need not be certified, so there is room for doubt about the contractor's intentions." Vern also said "I think (Dingoes) did the right thing in making the inquiry. That's what I think any good CO would have done."
I described some additional considerations for obtaining clarification from a contractor, assuming that the parties are on speaking terms. Asking a contractor to clarify its intent is simply a matter of proper communications and good judgement. Once a CO determines that the matter is a claim that implicitly or explicitly constitutes a request for a CO Decision, he/she proceeds to initiate a CO decision. I believe that he/she may alternatively simply agree with the contractor, document that agreement and proceed to settle the claim.
Don asked if the matter is a claim. From various posts here, apparently the teaching point described here is 1 ) read the definition of a claim, 2 ) compare it to the letter, then 3 ) determine that it is a claim. If you don't agree, then you are wrong.
To jump off into the CO decision process based upon that one line letter without any other understanding or knowledge of the circumstanmces or to discern the clear intent of the contractor would not generally be something that any "good contracting officer" should do, in my opinion. There could be tens or more "claims" on any individual construction contract if the CO treated every letter that included a request for a modification as a claim.
- j
joel hoffman
Mar 26, 2014 · 12y ago
The teaching point point is very good that just because a Contractor doesn't explicitly request a CO decision doesnt mean that the issue is not a "claim" However, I think that teaching contracting officers about claims should also extend beyond knowing the simple legal definition iof a claim. The lesson should include the practical aspects of being a good CO. One must determine the contractor's intent - especially when the Contract Disputes Act is involved. It is more than the mechanics of reading definitions. The time and efforts of a CO and its contract admin and legal staffs would soon be totally consumed by the contract claims process if it simply considered virtually every request for monetary adjustment, time extension, change in the specifications, etc. as an implicit request for a contracting officer's decision without asking the contractor to clarify its intent. Can you imagine what a CO with a hundred or more active construction type or similar contracts would do under such circumstances?
To be fair to Don, he was aware of the facts that would lead one to conclude that the contractor was implicitly requesting a CO decision because he read the Decision. I think that he was able to interpret the simple letter from the context of the situation I teach my students in the Design-Build class that when we and our fellow project delivery teammates know the intent, context and facts concerning what we are trying to say in an RFP, we should have someone not familar with all the intent and facts review the draft document. Sometimes what we write doesn't fully express what the full intent is or all of the facts necessary for another, reasonable reader to discern the full intention.
- S
Smallbusiness
Mar 26, 2014 · 12y ago
This teaching point was valuable and timely. I have a case before a Board where the Government attorney questioned jurisdiction under exactly the conditions of this thread. Though I argued exactly the logic in the decision of K-Con Building Systems vs Government, it is helpful to have case reference.
- G
Guest Vern Edwards
Mar 26, 2014 · 12y ago
To be fair to Don, he was aware of the facts that would lead one to conclude that the contractor was implicitly requesting a CO decision because he read the Decision.
The request was implicit based on the plain language of the request itself, not because of facts that went before it. That is a crucially important point. The judge pointed out the earlier transactions to show why it should have been even more obvious to the CO.