Redress for nonpayment of subcontractors
Started by MICHIGANKO · Mar 28, 2014 · 9 replies
- MOriginal post
MICHIGANKO
Mar 28, 2014 · 12y ago
I recently inherited administration of a contract in which the prior KO suspended payment to the prime after learning that the prime had been receiving disbursements, but not paying their subcontractor. The subcontractor performs a large percentage of the actual services.
As I begin my research, I thought I would reach out to this community. What (if any) authority exists for such an action?
- j
joel hoffman
Mar 28, 2014 · 12y ago
Is this a FFP service contract?
- G
Guest Vern Edwards
Mar 28, 2014 · 12y ago
We need to know the contract type (FFP, CPFF, etc.) and the payment clause(s) in the contract.
- G
Guest jrt132
Mar 28, 2014 · 12y ago
Also subcontractor business size would be beneficial.
- G
Guest Vern Edwards
Mar 28, 2014 · 12y ago
As a general rule, the authority to reduce, refuse, suspend, or withhold payments comes either from (1) a contract clause or (2) the doctrine of breach of contract.
For an example of a contract clause, see, e.g., FAR 52.222-41, Service Contract Act of 1965 (NOV 2007), paragraph (k), and FAR 52.232-16, Progress Payments (APR 2012), paragraph ( c ). See also FAR 52.216-7, Allowable Costs and Payment (JUN 2013), paragraph ( b )(1)(ii) (authority implicit) and (g)(1) (authority explicit).
To reduce, refuse, suspend, or withhold payments improperly is a serious breach of contract.
- M
MICHIGANKO
Mar 28, 2014 · 12y ago
The Contract Type is T&M. Payment Clause 52.232-7 - Payments under Time-and-materials and labor-hour contracts FEB/2007 is included. Prime is a SB, as is its subcontractor.
- G
Guest Vern Edwards
Mar 28, 2014 · 12y ago
Does the prime bill for the subs at hourly rates pursuant to para. (a), or does it invoice pursuant to para. ( b )? If the latter, then the Allowable Cost and Payment clause applies and the authority is probably para. ( b )(1)(ii)(A) of that clause, whether or not the subs are small businesses. Under that provision you would not be "suspending" payments, you would be disallowing the invoiced cost.
- R
Retreadfed
Mar 28, 2014 · 12y ago
MichiganKO, look at 52.232-7(a)(5). The requirement for the prime to substantiate payment may be of benefit to you in this case.
- M
MICHIGANKO
Mar 28, 2014 · 12y ago
Gentlemen -
Thank you for the feedback. This has been most helpful. In addition to the suggestions above, the payment clause includes the following:
(5) Vouchers may be submitted once each month (or at more frequent intervals, if approved by the Contracting Officer), to the
Contracting Officer or authorized representative. The Contractor shall substantiate vouchers (including any subcontractor hours
reimbursed at the hourly rate in the schedule) by evidence of actual payment and by
(i) Individual daily job timekeeping records;
(ii) Records that verify the employees meet the qualifications for the labor categories specified in the contract; or
(iii) Other substantiation approved by the Contracting Officer.
(6) Promptly after receipt of each substantiated voucher, the Government shall, except as otherwise provided in this contract, and
subject to the terms of paragraph (e) of this clause, pay the voucher as approved by the Contracting Officer or authorized
representative.
It appears from the billing, that the Prime was submitting time sheets from the Sub directly to the COR along with its billing. There is no documentation from the prime demonstrating that it actually paid the Sub.
- G
Guest Vern Edwards
Mar 28, 2014 · 12y ago
There you go.