Extended field overhead

Started by It_Dependsss · Jan 8, 2025 · 1 replies

  1. I

    It_Dependsss

    Jan 8, 2025 · 1y ago

    Original post

    Can a GC claim extended field overhead for an agreed upon delay where operations on the critical path were disrupted due to differing site conditions, but they continued to work on non-critical path activities? A suspension of work was not issued.

  2. j

    joel hoffman

    Feb 26, 2025 · 1y ago

    On 1/8/2025 at 4:57 PM, It_Dependsss said:

    Can a GC claim extended field overhead for an agreed upon delay where operations on the critical path were disrupted due to differing site conditions, but they continued to work on non-critical path activities? A suspension of work was not issued.

    Just saw a notice of this new topic this morning in my Denali.

    In response, based upon the limited information in the original post:

    If the contract completion date has been extended due to delays to the critical path to completion due to a DSC, it would appear that some form of extended field office overhead would be allowable.