Cost Plus Fixed Fee NTE Labor Rates?

Started by Mayonayze · Sep 30, 2014 · 8 replies

  1. M

    Mayonayze

    Sep 30, 2014 · 11y ago

    Original post

    Trying to find the section of the FAR that deals with these kinds of contract arrangements. under what circumstances are relief from the NTE labor rate granted? if the basis of pricing provides for a $50k salary based on statistical compensation analysis and salary surveys, but the market for this particular LCAT is highly volatile and by the time a task-order for this labor is released, the mid-point of the compa-ratio range has moved up and we can't find these guys for less than $55k, then are we stuck holding $5k of that salary in unallowable? doesn't seem to be in the true nature of a CPFF contract...

  2. j

    ji20874

    Sep 30, 2014 · 11y ago

    There is a basic principle of cost-reimbursement contracts you are not considering -- in a cost-reimbursement contract, the parties can agree on the treatment of certain costs before incurrence of the costs.

    If an offeror submits a proposal promising a cap or NTE on certain costs, and wins a contract based in part on that NTE, then that NTE is enforceable for the life of the contract. It must be this way; otherwise, the original promise was not a promise.

    If you promised a NTE labor rate, and that promise is captured in your contract, then yes, you are "stuck holding $5k of that salary."

  3. B

    BZMANINTEXAS

    Sep 30, 2014 · 11y ago

    Have you presented your case to the CO for consideration of raising that specific labor rate? If not, why not?

  4. M

    Mayonayze

    Sep 30, 2014 · 11y ago

    not yet, i just didn't know if there were provisions set forth in the FAR that outlined the criteria for a waiver.

  5. G

    Guest Vern Edwards

    Sep 30, 2014 · 11y ago

    There is nothing in FAR that will help you.

  6. M

    Mayonayze

    Sep 30, 2014 · 11y ago

    if not the FAR, then perhaps the WIFCON bag of wisdom can shake forth a nugget of advice or experience?

  7. j

    ji20874

    Sep 30, 2014 · 11y ago

    Well, my advice is to honor the promise and agreement memorialized in the contract.

    When I award a cost-reimbursement contract and the contractor promises to cap certain rates, I expect the contractor to honor its promise.

  8. G

    Guest Vern Edwards

    Sep 30, 2014 · 11y ago

    Aren't you a businessperson? You made a deal and now you want out of it. If you can't figure out how to do that on your own, then nothing any of us could say is going to help you.

    This isn't the HBA. You are on your own. Figure something out. Or don't.

  9. M

    Mayonayze

    Sep 30, 2014 · 11y ago

    *sips tea* very well then. good day to you.