    I have a contractor that submitted a request for modification for an additional $13k. The contractor did not get all required permits before starting, which was outlined in the SOW and contract and is now claiming delay costs associated with having to stop work until one additional permit was received. I am making the decision to deny it, but am wondering if I needed to provide appeal rights? The letter was not addressed as a formal claim and am thinking that I would deny it and then if they re-submit it as an actual claim, requesting a decision, I would give it at that time. Appreciate thoughts.

  2. C

    C Culham

    Oct 20, 2014 · 11y ago

    JL - Your post could very well lead to a long thread and before it does I thought I would reference this blog by Mr. Vern Edwards as it might help you answer your own question.

    wifcon.com/discussion/index.php?/blog/2/entry-2868-reas-and-claims-is-there-a-difference/

  3. J

    JLchief55

    Oct 20, 2014 · 11y ago

    Great, that you C Culham, very informative and it does answer my question.