T for D procedure

Started by lbrob1 · Jun 8, 2015 · 29 replies

  1. l

    lbrob1

    Jun 8, 2015 · 11y ago

    Original post

    If you terminate a contract for Default and fail to notify the SBA offices in accordance with FAR 48 CFR 49.402-3 (e)(4), is this a big deal or not? Is it worse if this occurred 10 times over the course of two years? What are they supposed to do with this info, anyway?

  2. j

    ji20874

    Jun 8, 2015 · 11y ago

    Apparently, it isn't a big deal.

  3. G

    Guest Vern Edwards

    Jun 8, 2015 · 11y ago

    lbrob1:

    You're new, so I'm not going to fuss too much, but your question was ambiguous. What does "big deal" mean? Are you asking if failure to notify SBA would invalidate or otherwise impair the termination? Are you asking if it could get the CO in trouble with an inspector general? Or are you asking something else? Try to be specific.

    Such failure might be a 'big deal." Failure to notify SBA has been asserted as a challenge to the propriety of a termination for default a few times at the boards of contract appeals and once at the Court of Federal Claims. As far as I can tell, such assertions have been to no avail. However, the boards and the court have suggested that such a failure could impair a termination if the failure was prejudicial to the contractor's interests. See, for example, Rowe Inc. v. General Services Administration, 01-2 BCA ¶ 31630, GSBCA 14211, Sept. 28, 2001:

    The main deficiencies cited by appellant essentially involve FAR provisions encouraging consultation with SBA and with the agency small business specialist prior to implementing a default termination of a contract with a small business. 48 CFR 49.402-3(e)(4). First, GSA had previously put SBA on notice that it was considering a partial default termination of the contract. Nothing in the record indicates that SBA objected to GSA's taking this action. Second, the requirement to notify SBA and the agency small business specialist of a pending default termination does not provide a basis for relief. The requirement is imposed for informational purposes. The contracting officer is not constrained to obtain a response from SBA or from the small business specialist before terminating a contract for default. S & W Associates, DOT CAB 2633, 96-2 BCA ¶ 28,326, at 141,454; McOuiston Associates, ASBCA 24676, 83-1 BCA ¶ 16,187, at 80,441. Appellant has not shown how the subsequent omission harmed it.

    In this same vein, Rowe also contends that the failure of the contracting officer to consult with the small business specialist in accordance with FAR 49.402-3 (e)(4) renders the termination procedurally defective. However, consultation with the small business specialist is not a mandatory requirement. The contracting officer need do so only if it is “practicable.” While there is no evidence that it was not practicable to consult with the small business specialist, appellant has not shown that this omission prejudiced it. Consequently, we conclude that the failure to consult with the small business specialist did not affect the propriety of the termination for default. S & W Associates, 96-2 BCA at 141,455; AlW-Alton, Inc., ASBCA 45032, 96-1 BCA ¶ 28,232, at 140,980.

    See also Hanno ElectricCo. v. U.S.,31 Fed. Cl. 135, April 29, 1994:

    Hannon also contends that the CO acted arbitrary and capriciously by failing to forward a copy of the cure notice to the Small Business Administration (“SBA”) as required by 48 C.F.R. § 49.402–3(e)(4). Such a failure is not grounds for overturning a default where, as here, notice is provided to SBA only “as a matter of information,” and plaintiff has not demonstrated that the lack of notice prejudiced it. Acquisition Assocs., ASBCA No. 24676, 83–1 BCA ¶ 16,187, Apr. 29, 1994.

    Off hand, I don't know how the failure might prejudice a contractor, but contractors hire lawyers to figure that out. In theory, SBA might advise the contractor or try to intercede on the contractor's behalf, although I think that's unlikely. In any case, the rule is there for some reason, so it's a good idea to comply with it, if only to deny the contractor a potential legal issue.

    The requirements of FAR 49.402-3(e)(4) do not apply to contracts for commercial items. See FAR 12.403(a).

  4. l

    lbrob1

    Jun 17, 2015 · 10y ago

    I have a new question...is a T for D defective if the following are present on a FFP, unilateral PO for non-commercial supplies, if:

    1. FAR 52.249-8 (T4D)is missing from the PO (contract??),

    2. A first article is required prior to production, it is supplied, but it is (likely wrongfully) rejected for a minor/easily correctable defect,

    3. A T4D is issued referencing 52.249-8 based on a failure to supply acceptable first article and failure to make delivery.

    4. The Contractor fails to take action for 16 months, then wants to file a claim

    I have my own interpretation, but want to see what superior minds might think....

  5. D

    Don Mansfield

    Jun 17, 2015 · 10y ago

    Did the PO contain a termination for default clause?

  6. l

    lbrob1

    Jun 17, 2015 · 10y ago

    No, T4D clause was missing...T4C was included, though

  7. D

    Don Mansfield

    Jun 17, 2015 · 10y ago

    I'll offer an opinion while we're waiting for the superior minds to show up.

    If you issued a unilateral purchase order and the vendor did not deliver an acceptable product by the date stated in the order, then I don't think you had a contract. There was an offer, but no acceptance. If that's the case, there's nothing to terminate and the vendor is not in default.

    That's what I think based on the facts provided.

  8. B

    Boof

    Jun 17, 2015 · 10y ago

    Don,

    They said the contractor provided a first item for testing. So, isn't that legally an acceptance of the order.

    However,if the order depended on first order acceptance and there was none, that really complicates the issue.

  9. D

    Don Mansfield

    Jun 17, 2015 · 10y ago

    If the order just required them to provide an item for testing and they did that, then you probably would have acceptance. I assumed that the vendor was required to deliver an acceptable first item by a specified date.

  10. R

    Retreadfed

    Jun 17, 2015 · 10y ago

    I don't know what lbrob is asking for an opinion on. If he is asking can the contractor file a claim, I do not see any reason why it can't. Of course we do not know what the theory of the claim would be because that is up to the contractor. However, if it wants to challenge the T4D, from what is written, I see no reason why it cannot. In this regard, remember that a T4D is a government claim and the government would have to establish that a termination for default clause was required to be included in the contract as a matter of law and that the predicate for a T4D under that clause was met.

  11. l

    lbrob1

    Jun 18, 2015 · 10y ago

    Here is some more on the subject...

    1. There is a thing called the Christian Doctrine, apparently including T4D in all contracts,even if not cited explicitly, to my understanding.

    2. It may or may not apply to this case, because it may only permit T4D for a failure to make progress and not a failure to supply an acceptable first article....need a big brain to advise more on this one.

    3. The Branch Chief stepped in and issued a statement that claims submitted by the contractor more than 12 months after the Government's T4D are untimely and will not be evaluated for a final decision.

    Some questions are: is the Branch Chief correct? Did she set up the agency for trouble by stepping in? Can a contractor still file am actionable claim despite the T4D against them or is the issue technically already adjudicated?

  12. j

    ji20874

    Jun 18, 2015 · 10y ago

    lbrob1,

    May I re-state the facts? I want to make sure I'm understanding...

    1. YES NO A Government agency issued a unilateral purchase order under FAR Part 13.

    2. YES NO The purchase order was for supplies -- non-commercial, so no FAR Part 12 clauses were used.

    3. YES NO The purchase order did not include the clause at FAR 52.249-8, Default (Fixed-price Supply and Service), because the prescribing language makes the clause optional under the simplified acquisition threshold.

    4. YES NO The purchase order required a first article submission for the Government's testing and approval. The purchase order included the clause at FAR 52.209-4, First Article Approval--Government Testing.

    5. YES NO The contractor delivered a first article item on time.

    6. YES NO The Government disapproved the first article for an easily correctable defect and provided timely notice to the contractor under paragraphs ( b ) or ( c ) of the clause at FAR 52.209-4.

    7. YES NO The Government did not request that the contractor submit an additional first article for testing.

    8. YES NO Because of the first article disapproval, the Government deemed the contractor to have failed to make delivery under paragraph ( d ) of the clause at FAR 52.209-4.

    9. YES NO The Government terminated the purchase order because of the contractor's default, and cited the clause at FAR 52.249-8, and paragraph ( a )( 1 )( i ) within that clause, as the basis for the termination.

    10. YES NO The Government provided notice of the termination to the contractor, and has evidence of delivery and receipt of the notice.

    11. YES NO The Government heard nothing more from the contractor for the following sixteen months.

    12. YES NO The contractor then indicated that it wanted to file a claim, but did not actually do so.

    13. YES NO The contracting officer's branch chief issued a written statement to the contractor that claims submitted by the contractor more than 12 months after the Government's notice of termination for default are untimely and will not be evaluated for a final decision.

    If any of these are NO, please provide the correct information.

  13. R

    Retreadfed

    Jun 18, 2015 · 10y ago

    One more question. Was the termination notice in the form of a final decision under the Disputes clause in which the contractor was informed of its appeal rights?

  14. l

    lbrob1

    Jun 18, 2015 · 10y ago

    #5 No, the contractor was 18 months late to submit a first article, but the Government still evaluated it in full.

    #6 No: The Government's notice of disapproval was slightly untimely (56 days late). Other than this, yes to the question.

    #7 No: The Govt requested a new first article, but the Contractor refused, asking Engineers from the local COR (DCMA) to see the minor defects and report back to the KO. DCMA refused and the original KO took no action for a year+.

    #8 No: Govt found failing to provide a first article that meets contract requirements AND BY NOT MAKING DELIVERY UNDER THE CONTRACT

    #9 No: FAR 52.249-8 was used, but (a)(1)(i) was omitted. FYI, the Govt took one year to decide to T4D after receiving Contractor's request for reevaluation.

    #11 No: Govt heard nothing back regarding this contract, but had extensive contact with the KO 30+ times in that time frame regarding improper Govt first article testing results, often verified as improper by results sent over from independent laboratories.

    #12 No: Contractor did file a claim 18+ months later.

    and to Retreadfed: Yes, the proper method of termination was performed in a contract mod (good one!).

  15. D

    Don Mansfield

    Jun 18, 2015 · 10y ago

    So is the basis of the claim that the vendor delivered an acceptable item that was improperly rejected?

  16. l

    lbrob1

    Jun 18, 2015 · 10y ago

    The bases are Improper and delayed Government inspection of the first article, Government failure to use a proper, contractually binding authority to terminate the contract., Government failure to enter into discussion or negotiate a termination settlement in good faith. and a long standing failure to cooperate to correct known problems with the first article process....

    Are any of these defensible?? What would you do?

  17. R

    Retreadfed

    Jun 18, 2015 · 10y ago

    lbrob, since you did not answer my question directly, I want to make sure of one thing, the termination notice was in the form of a decision under the Disputes clause that complied with the requirements of FAR 33.211.

  18. l

    lbrob1

    Jun 19, 2015 · 10y ago

    Retreadfed: Correct, FAR 33.211 was followed, however the statement of facts in agreement and disagreement 33.211 (a)(4)(iii) is poorly supported and vague...effectively saying the first article failed and the KO agrees it failed, without going into detail.

  19. R

    Retreadfed

    Jun 19, 2015 · 10y ago

    From what you have written, I would say that the contractor cannot file a valid claim in regard to any matter that is within the scope of the final decision. Under the CDA, a contractor can challenge a decision under the Disputes clause by filing an appeal with the appropriate appeals board within 90 days of receipt of the decision or by filing a lawsuit in the COFC within 1 year of receipt of the decision. If the contractor does neither, the decision becomes final and binding even if it is erroneous. Because the decision was delivered to the contractor 16 months ago, any challenge to that decision would not be timely.

    However, because a contractor has six years within which to file a claim after the claim accrues, the contractor can file a claim unrelated to the subject of the final decision so long as the six year period has not elapsed.

  20. h

    here_2_help

    Jun 19, 2015 · 10y ago

    I'm no attorney and it would be interesting (read: *vital*) to get an attorney's view of this issue. That said, I had thought there was a 2010 Federal Circuit decision (Maropakis Carpentry) that required defenses against government actions to be submitted to a KO and to receive a COFD before being adjudicated. My understanding of that dispute is that the government assessed liquidated damages and the contractor raised a defense of excusable delay, but because the contractor failed to submit that defense to the CO within 6 years, the defense was found to be outside the statute of limitations and would not be heard. Thus, the contractor had 6 years to raise all claims, including defenses to the government's actions.

    If my understanding of that decision is correct -- and let me emphasize I may not have it right -- then the Branch Chief's edict that contractor claims submitted more than 12 months after the T4D are untimely and would not be considered may be construed as denying a contractor the right to raise defenses and to have them heard on appeal, in certain circumstances. I don't know. But I would be worried that, if the contractor is raising a defense against the T4D, then its claim may not be untimely and would require a separate COFD, even if more than a year has passed since the T4D.

    At least, that's how I think the Federal Circuit decision reads.

    Did I mention I'm not an attorney?

    H2H

  21. m

    metteec

    Jun 19, 2015 · 10y ago

    From a legal perspective, I am in agreement with Retreadfed's assessment that the ship has sailed to dispute the T4D. However, from an ethical perspective, I am having a difficult time with that action. Originally, lbrob1 stated:

    "2. A first article is required prior to production, it is supplied, but it is (likely wrongfully) rejected for a minor/easily correctable defect"

    From this statement, I inferred that the agency possibly erred in rejecting the Contractor's first article. This improper rejection might have influenced the Contractor's capability to perform on the remainder of the contract. While many of the details in this case are obfuscated, the Government might have set the Contractor up for failure, and ultimately the T4D.

    lbrob1's agency is within its rights to do absolutely nothing with the T4D. However, if I was in the situation, and knowing that the agency might have contributed to the Contractor's failure, I would offer the Contractor the option to convert the T4D to a termination for convenience with a no cost settlement agreement. TheT4C with a no cost settlement agreement would allow the Contractor to improve its business process while also eliminating any further hassle and cost of involving agency staff to defend against the Contractor's claims.

    A T4D has a devastating effect on a business. A T4D stays on the Contractor's record for up to six years and could prevent it from seeking future business. The Contractor has employees which rely on the Government's business for their livelihoods. Those employees are taxpayers. Even if I knew I could get away with it, I would prefer not to have the weight of those employees' future on my conscience if I knew that the Government was contributory to the Contractor's failure.

  22. R

    Retreadfed

    Jun 19, 2015 · 10y ago

    H2H, your memory is partially correct. In Maropakis, the government did assert a claim for liquidated damages and issued a final decision establishing the amount and demanding payment by the contractor. Three days before the time for filing in the COFC expired, Maropakis filed suit. Maropakis submitted a complaint in which it asserted a right to a schedule adjustment. The COFC held that the request for a schedule adjustment was a claim by Maropakis. Because that claim had never been submitted to the contracting officer, the court had no jurisdiction to rule on that part of the complaint and dismissed it. The CAFC affirmed the COFC's decision. Thus, the Maropakis decision only dealt with whether a part of Maropakis complaint constituted a separate claim that needed to be submitted to the contracting officer before the court had jurisdiction to rule on the substance of the complaint, not whether the claim was barred by the 1 year period in which to appeal a contracting officer's decision or the six year period within which to assert a claim after the claim accrued.

  23. h

    here_2_help

    Jun 19, 2015 · 10y ago

    Retreadfed,

    Thank you for clarifying.

    H2H

  24. G

    Guest Vern Edwards

    Jun 20, 2015 · 10y ago

    From what you have written, I would say that the contractor cannot file a valid claim in regard to any matter that is within the scope of the final decision. Under the CDA, a contractor can challenge a decision under the Disputes clause by filing an appeal with the appropriate appeals board within 90 days of receipt of the decision or by filing a lawsuit in the COFC within 1 year of receipt of the decision. If the contractor does neither, the decision becomes final and binding even if it is erroneous. Because the decision was delivered to the contractor 16 months ago, any challenge to that decision would not be timely.

    However, because a contractor has six years within which to file a claim after the claim accrues, the contractor can file a claim unrelated to the subject of the final decision so long as the six year period has not elapsed.

    Did the contractor ever submit a claim as defined in FAR 2.101 about the T4D?

    If not, how could there have been a CO final decision on such a claim?

    Did the T4D communication include the CO final decision language from FAR 32.211?

    If not, was the T4D communication a final decision?

    Could the T4D communication have validly included that language if the contractor had not yet submitted a claim as defined in FAR 2.101?

    Would/could the contractor have submitted a claim as defined in FAR 2.101 about a prospective T4D?

    If there was a claim as defined by FAR 2.101, I wonder if a "statement" by a "branch chief" would constitute a final decision of the CO.

    If the branch chief were a CO and could have issued a final decision, would he have done so if he had stated that it was too late to submit a claim?

    If he did, wouldn't he have contradicted himself?

    If the contractor had submitted a claim about the branch chief's statement that it was too late to file a claim, and if the branch chief had properly issued a final decision denying that claim, and if the contractor had failed to timely appeal that decision, couldn't the contractor still submit a claim about the T4D?

  25. h

    here_2_help

    Jun 21, 2015 · 10y ago

    Vern,

    Outstanding points. You articulated what I could only hint at.

    H2H

  26. l

    lbrob1

    Jun 21, 2015 · 10y ago

    Regarding Vern's questions,

    1. Yes, the contractor filed a claim for many things including T4D, breach of contract and failure to use discretion in the termination and first article rejection.

    2. To my knowledge a T4D is automatically a COFD on a Government claim.

    3. The terminating mod did include the FAR 2.101 language.

    4. The terminating mod explicitly stated it contained the CO's final decision.

    5. I suppose the contractor could have submitted a claim for the value of its first article, had it made one, prior to T4D (if I understand your question correctly).

    6. I suspect the Branch Chief statement could signal an impasse, constituting a final decision. More importantly the case of John A. Johnson v. US, 132 Ct. Cl. 645 (1955) suggests that when a branch chief steps in, they are doing so improperly, perhaps in bad faith.

    7. In this case the Branch Chief is a supervising CO and has stepped in to issue final decisions in prior cases in the past.

    8. In this case the claim is a deemed denial for Government non responsiveness

    9. Th last question is similar to my original question...which I'm still unsure about...my guess is the 6 year statute of limitations allows the claim to proceed and not the 12 month appeal limit on T4D.

    thx

  27. G

    Guest Vern Edwards

    Jun 22, 2015 · 10y ago

    lbrob1:

    In response:

    2. A T4D is not "automatically" a CO's final decision. It is a government claim.

    That being the case, there is no need for the contractor to submit a claim to the CO about the T4D. Instead, it can appeal directly to a board of contract appeals within 90 days after the T4D or to the Court of Federal Claims within a year. See Malone v. U.S., 849 F.2d 1441, June 16, 1988; U.S. Coating Specialties & Supplies, LLC, ASBCA 58245, April 9, 2015; and Connectec Co., ASBCA 57546, 11-2 BCA ¶ 37,797. You might want to read Connectec, because you said in Post #6 that the purchase order did not contain a default clause. That might be significant in your case.

    If, on the other hand, the contractor does not want to contest the T4D, but only wants some relief with respect to the first article, then it must submit a claim to the CO and it has six years to do so from the date of accrual.

    3. There is no language in FAR 2.101 for a terminating mod to include with respect to a final decision.

    8. "The claim" (meaning the contractor's claim?) is a deemed denial? That doesn't make sense. Government inaction would be a deemed denial.

    Your story in this thread has unfolded somewhat disjointedly. Even in your last post we seem to have learned some things that I don't think you mentioned before. Wifconers should be careful about responding to you.

  28. W

    Weno2

    Jun 22, 2015 · 10y ago

    Since the acquisition was a non-commercial purchase order (PO), FAR clause 52.213-4 -- "Terms and Conditions -- Simplified Acquisitions Other Than Commercial Items" should be in the PO.

    And if it is, why would FAR 52.249-8, TFD clause be in the PO, when FAR clause 52.213-4 (g), "Termination for Cause" would be applicable?

  29. l

    lbrob1

    Jun 23, 2015 · 10y ago

    Mr. Edwards,

    I was under the impression this was a forum to openly discuss relevant federal contracting issues and the nature of these issues is often confusing, debatable and unclear. While I certainly respect your lengthy experience and work history, please note the following:

    1. I still believe a T4D may be ALSO be a contracting officer's final decision. See the suggested terminating language in Air Force Exhibit #3 https://www.google.com/url?sa=t&rct=j&q=&esrc=s&source=web&cd=1&cad=rja&uact=8&ved=0CB8QFjAA&url=http%3A%2F%2Fwww.acq.osd.mil%2Fdpap%2Fccap%2Fcc%2Fjcchb%2FFiles%2FTopical%2FTerminations%2Fguides%2Fafmc%2520t4d%2520guide.docx&ei=ccSIVdCJDsjboAS656LoDg&usg=AFQjCNGdi7rHdSLQESXqq_LSCBKRKMwzvg&sig2=J8_uu9D9ac4E0Yu5GN9mdw

    The 2014 JAG Contracting Officer's Handbook, page 22-19 Sect V (A) also seems to support this...however I'm somewhat unclear and am looking for discussion. The Connectee case you listed is interesting, but differs somewhat because it has an order withdrawal. In the case I mentioned this was a formal T4D action...probably undertaken mistakenly.

    2. You mistakenly listed FAR 32.211 in post #25; it should be 33.211; I started to look into this problem, came back to it later and mistakenly put in a FAR from question 1.

    3. I'm not sure what doesn't make sense. The Government terminated for default and the contractor filed a contractor claim mote than a year later. The Govt never made a final decision, creating a deemed denial of the claim.

    4. Regarding Weno2's question, I'm not sure why the preaward folks didn't use your 52.213-4 method, but also note that FAR 52.249-8 was not in the contract, but was (mistakenly??) used as the terminating basis.

    This is a complex case with a lot of interesting twists and turns, perhaps even a case of first review. I probably should have made several different new posts instead of a single one, for clarity.

    Thanks for your interest.

  30. G

    Guest Vern Edwards

    Jun 23, 2015 · 10y ago

    lbrob1:

    1. I agree that a T4D can be a CO's final decision. What I said was that it is not "automatically" a final decision. I was disagreeing with your use of "automatically" in Post #26. I was also pointing out that a T4D is a government claim, in response to which the contractor can go to the board or the Court of Federal Claims without first submitting a claim and getting a CO's final decision.

    You started out by asking if the T4D was defective. Maybe that doesn't matter if the T4D, defective or not, final decision or not, was a government claim. Maybe the T4D started the countdown to the appeal deadline. Maybe you should ask whether failing to appeal the T4D to the board or the COFC within the appeal time limits (90 days to a board; one year to the COFC) would deny the board or the court jurisdiction over the issue. If so, maybe the claim submitted 18 months later does not require a CO response. Maybe that's what the branch chief was talking about when he said the contractor couldn't file a claim after more than a year.

    2. Sorry about the typo.

    3. What doesn't make sense is your statement "the claim is a deemed denial for Government non responsiveness[.]" You said: "the claim" [subject] "is a deemed denial" [predicate]. "Deemed denial" refers to a CO's failure to provide a final decision within the specified time limits would be a deemed denial. A claim is not a deemed denial. A CO's failure to respond to a claim with a final decision is a deemed denial. Maybe what you meant to say was the claim is deemed to have been denied because the CO didn't respond.

    I apologize if I have missed something you already said. This thread has strung out over a long series of posts, most of which sought to understand your facts, and I don't care to go over all of them carefully in order to get a coherent narrative. Sometimes confusion and lack of clarity are not inherent in the situation.

    This case is not inherently or especially confusing. The key facts are:

    There was a contract.

    The government notified the contractor that it had terminated the contract for default.

    The contractor submitted a "claim" 18 months later, challenging the termination.

    The Government did not respond to the "claim."

    Are those true statements? If so, then I think the question is: Can the contractor appeal the Government's deemed denial of its claim? Corollary questions might be: If not, did the Government have to respond to the contractor's "claim" filed 18 months after the T4D? Can the contractor still submit claims about other issues?

    See Guardian Angels Medical Service Dogs v. U.S., 118 Fed. Cl. 87, August 29, 2014. (That decision has been appealed to the Federal Circuit.) See also Educators Associates, Inc. v. U.S., 41 Fed.Cl. 811, September 23, 1998.

Sign in or sign up to post a reply.