Consent and Advance Notification
Started by rdtmk5 · Oct 31, 2011 · 3 replies
- rOriginal post
rdtmk5
Oct 31, 2011 · 14y ago
If a contractor has a CPSR-approved purchasing system, is that contractor then never required to obtain consent or provide advance notification (except in accordance with 52.244-2 (
and (d))? We are currently debating the requirements of FAR 52.244-2 (which, in my opinion, contains a far amount of ambiguity), and are faced with several competing interpretations. Your guidance would be greatly appreciated. Thank you. - D
Don Mansfield
Oct 31, 2011 · 14y ago
That's how I read the clause. Seems pretty straightforward to me.
- C
Cajuncharlie
Nov 1, 2011 · 14y ago
Agree with Don. Also please note the requirement for "short form" Advance Notification, in (e)(2) of Alternate I, when consent is not required. The prescription in 44.204(a)(2) says to use Alternate I for civilian agencies other than Coast Guard and NASA.
- r
rdtmk5
Nov 1, 2011 · 14y ago
Thanks, everyone. This helped to clarify the requirement.