Are you able to create new options on an existing task order that has no options? Existing Task Order will expire six months from now.
- G
Guest Vern Edwards
Apr 3, 2018 · 8y ago
I presume that the underlying contract is multiple award.
The answer to your question is yes. However, a new option would be out-of-scope and tantamount to a new order, subject to all of the rules that apply to all new orders.
- c
creyes814
Apr 3, 2018 · 8y ago
Yes, the underlying contract is a multiple award. Is there specific guidance/policy that says you can/can't add options to an existing task order? Thank you.
- G
Guest Vern Edwards
Apr 3, 2018 · 8y ago
creyes814 said:
Is there specific guidance/policy that says you can/can't add options to an existing task order?
In order for you to add work to an existing task order by adding a new extension new option without giving the other contractors a fair opportunity to be considered for that work, you must comply with FAR 16.505(b)(2) and any applicable contract terms..