Subcontract cost/price analysis as part of CO consent decision?
Started by VipinOwl · May 13, 2019 · 41 replies
- VOriginal post
VipinOwl
May 13, 2019 · 7y ago
During performance of an R&D contract (roughly 2 years after award), does the CO need to perform price/cost analysis for a proposed subcontract award when providing consent?
Scenario:
- CPFF prime contract for R&D Services (non-commercial, competitive acquisition)
- Subcontract award also CPFF from a competitive RFP (above the SAT). 3 proposals were received and prime made its selection
- Prime provides advance notification to CO for the anticipated subcontract award, including prospective subcontractor cost/price information such as budget and the non-winning proposal cost information
- Prime provides a negotiation memo and states the technical reasons for the selection, the fact that the prices have been determined to be fair and reasonable and the offeror's past performance.
Does the CO need to independently review the cost/price information and perform a price analysis and cost realism analysis? Intuitively, this seems imperative to ensure that services are acquired at a fair and reasonable price. However, FAR part 44.202, does not state that at a minimum the CO shall determine that prices are fair and reasonable, under its considerations. Instead item 8. states, "(8) Has the contractor performed adequate cost or price analysis or price comparisons and obtained certified cost or pricing data and data other than certified cost or pricing data?" To make matters more convoluted (at least to me) FAR 44.203 states, "(a) The contracting officer’s consent to a subcontract or approval of the contractor’s purchasing system does not constitute a determination of the acceptability of the subcontract terms or price..."
Is the subcontractor's determination sufficient for this analysis? FAR part 15 states that "The contracting officer is responsible for the determination of a fair and reasonable price for the prime contract, including subcontracting costs." Then again a paragraph further down it states, that "The prime contractor or subcontractor shall -- (1) Conduct appropriate cost or price analyses to establish the reasonableness of proposed subcontract prices".
Is the onus on the prime contractor to determine fair and reasonable prices for its intended subcontract, if at a minimum the CO's determination is not required, under considerations, and further that a CO's consent is not an indication of acceptable subcontract prices? Can a CO's evaluation of the prices submitted in response to a competitive requirement be sufficient, for a CPFF subcontract?
- j
ji20874
May 13, 2019 · 7y ago
Owl,
Have you read the clause at FAR 52.244-2, Subcontracts?
Is consent to subcontract (under the clause at FAR 52.244-2) required for the subcontract you are asking about?
- N
Neil Roberts
May 13, 2019 · 7y ago
44.203 consent does not support a contractor relying on it as the government seal of approval or agreement to any other matter, such as allowable costs, approval of special test equipment, whether the transaction was now considered audited, etc. It is merely permission to enter into a contract.
Yes, when consent is required, the contractor is required to furnish information about the transaction per FAR 52.244-2.
Not sure what you mean by your last sentence, VipinOwl. Is it about consent?
- P
Patrick Mathern
May 13, 2019 · 7y ago
You’ve mentioned cost analysis here - if you’ve documented adequate competition, per FAR 15.403-1, you alleviate the certification requirements. The contracting officer wouldn’t be required to do a cost analysis unless the competition is somehow determined inadequate.
Your cost reimbursable contract type will subject you and your sub to accounting system adequacy questions. That’s potentially a much bigger issue than price reasonableness, although the two go hand in hand.
- D
Don Mansfield
May 13, 2019 · 7y ago
Are you pricing a contract modification?
- V
VipinOwl
May 14, 2019 · 7y ago
ji20874 said:
Owl,
Have you read the clause at FAR 52.244-2, Subcontracts?
Is consent to subcontract (under the clause at FAR 52.244-2) required for the subcontract you are asking about?
Yes, the subcontract is subject to consent requirements.
Neil Roberts said:
44.203 consent does not support a contractor relying on it as the government seal of approval or agreement to any other matter, such as allowable costs, approval of special test equipment, whether the transaction was now considered audited, etc. It is merely permission to enter into a contract.
Yes, when consent is required, the contractor is required to furnish information about the transaction per FAR 52.244-2.
Not sure what you mean by your last sentence, VipinOwl. Is it about consent?
Yes, its about consent. Does the CO's consent involve a CO's independent determination of a fair and reasonable price for the subcontract or can he/she rely on the prime's certification?
Patrick Mathern said:
The contracting officer wouldn’t be required to do a cost analysis unless the competition is somehow determined inadequate.
I was wondering if a cost realism analysis, in line with FAR part 15 was required of a CPFF subcontract, even if there is adequate competition and price analysis indicates that prices are fair and reasonable.
Don Mansfield said:
Are you pricing a contract modification?
Don, this is not part of a contract modification. It is for a subcontract consent decision, within the ceiling of the contract. From my reading of FAR part 15, subcontract pricing, the review and analysis of subcontracts is specifically required when pricing a prime contract award or modification. I'm trying to ascertain if a subcontract needs to be subjected to price/cost analysis after contract award and not for a contract modification. It appears from both FAR part 15 and FAR part 44 that the onus is on the prime contractor to make a determination of fair and reasonable prices for a subcontractor.
- D
Don Mansfield
May 14, 2019 · 7y ago
VipinOwl said:
Yes, its about consent. Does the CO's consent involve a CO's independent determination of a fair and reasonable price for the subcontract or can he/she rely on the prime's certification?
No, consent does not require the CO's independent determination of a fair and reasonable subcontract price. FAR 44.203(a):
Quote
The contracting officer’s consent to a subcontract or approval of the contractor’s purchasing system does not constitute a determination of the acceptability of the subcontract terms or price, or of the allowability of costs, unless the consent or approval specifies otherwise.
- g
general_correspondence
May 14, 2019 · 7y ago
If the question is "does the CO need to perform price/cost analysis" ...the CO is to determine the contract price is fair and reasonable, not necessarily the subcontracted prices. By design, the onus is on the contractor to determine fair and reasonable prices from their subcontractors in their proposals to the government, if that is adequately done to the satisfaction of the CO, he/she may need not go any further.
- V
VipinOwl
May 14, 2019 · 7y ago
Don Mansfield said:
No, consent does not require the CO's independent determination of a fair and reasonable subcontract price. FAR 44.203(a):
Thank you kindly for your help Don. Just so I'm clear, does the CO ever need to independently analyze a subcontractor's proposal (cost/cost realism/price analysis)? FAR part 15.404-3 states, "The contracting officer is responsible for the determination of a fair and reasonable price for the prime contract, including subcontracting costs." Should this be read as the CO shall determine if only the prime contract's price (to include subcontract costs) is fair and reasonable or that the CO shall determine that both the prime contract's and subcontract's prices are fair and reasonable? FAR 15.404-3(b)1 goes on to say that the "prime or subcontractor shall conduct appropriate cost or price analyses to establish the reasonableness of proposed subcontract prices", seeming to put the burden of the subcontract price reasonableness determination on prime contractors.
If that is the case, pre-award cost realism and or cost analysis of prime contract offerors need not include a CO's cost/price analysis of contemplated subcontract awards, is that correct? Instead a CO may rely on the prime contractor's certification that it has performed cost/price analysis of subcontracts or has negotiated subcontract prices per FAR 15.404-3.
- j
ji20874
May 14, 2019 · 7y ago
Not only does consent to subcontract not require the contracting officer to determine the subcontract price to be reasonable, but also the fact of consent does not mean that the subcontract price is reasonable (even though the prime contractor shared the proposed subcontract price and its PNM with the consent package).
- V
VipinOwl
May 15, 2019 · 7y ago
Thank you all for your input and guidance.
- D
Don Mansfield
May 15, 2019 · 7y ago
VipinOwl said:
Just so I'm clear, does the CO ever need to independently analyze a subcontractor's proposal (cost/cost realism/price analysis)?
Yes. For example, if the CO is pricing a contract or contract modification and the subcontractor does not share cost information with the prime. In that case, the CO would have to perform any required cost analysis.
- g
general_correspondence
May 17, 2019 · 7y ago
Don,
you provided an example for a Contracting Officer duties. Would an assist audit be requested or required, if the prime Contractors subcontractor did not share cost information with the prime?
- R
Retreadfed
May 17, 2019 · 7y ago
general_correspondence said:
Would an assist audit be requested or required, if the prime Contractors subcontractor did not share cost information with the prime?
That depends on the value of the prime contract and subcontract, how each is priced and what agency is awarding the contract.
- g
general_correspondence
May 17, 2019 · 7y ago
it is an IDIQ already awarded to a prime. The IDIQ was competitively awarded to multiple Primes. Now, this task order pursuit, the Primes' proposal is valued over 2M, and so is the subcontracors proposal to the prime. The Prime solicited several suppliers in RFP, however only one priced proposal came back. The Subcontractors proposal is a CPFF, same as Prime, however the Subcontractor did not share rates, and indirect costs. Therefore, adequate competition was attempted, only one source responded. We, as the prime, want to know what is the policy/guidance on when an assist audit is required for subcontractors under a competitive process?
- R
Retreadfed
May 17, 2019 · 7y ago
general_correspondence said:
We, as the prime, want to know what is the policy/guidance on when an assist audit is required for subcontractors under a competitive process?
Generally, no audit of the prime or subcontractors would be required if the prime contract (task order) is being awarded competitively. To the best of my knowledge, the only pre-award audit rights that the government has is in regard to non-competitive awards when certified cost or pricing data are required. See, table 15-2 in FAR 15.408.
- N
Neil Roberts
May 18, 2019 · 7y ago · edited 7y ago
I have never believed there is adequate price competition or even attempted adequate price competition when all the bidders (or one bidder) are proposing CPFF contracts because there is no price. Certified cost or pricing data is required from the one bidder if the threshold is exceeded. The prime should verify the data (factfind and prepare a negotiation plan) /and or request an audit assist from DCAA or information from it or the subcontractor regarding any approved rates.
- R
Retreadfed
May 19, 2019 · 7y ago
Neil, look at the definition of "price" in FAR 15.401.
- N
Neil Roberts
May 19, 2019 · 7y ago
Retreadfed said:
Neil, look at the definition of "price" in FAR 15.401.
My view/interpretation is from a prime contractor standpoint. I do not know how the government sees this. Prime contractors would be taking unreasonable risks for itself and the government to simply compare proposed estimated cost and fee by 2 or more subcontractors and awarding it as proposed to the one that has the lowest mathematical total. Regardless of the estimated cost proposed, the government is bound to pay the contractor its actual and allowable costs. FAR §§ 15.305(a)(1); 15.404-1(d); Palmetto GBA, LLC, B-298962, B-298962.2, Jan. 16, 2007, 2007 CPD ¶ 25 at 7. Those costs are unknown and can not be compared to one another. The government and the prime contractor should perform cost realism per 15.404-1. When performed, I think it would be reasonable to say that it would be rare that the analyzing party would not seek some adjustment in the proposed. Hence, as a practical matter, CPFF contracts are negotiated and outside the bounds of adequate price competition defined in 15.403-1.
I looked at the definition of price in 15.401, Retreadfed. I have not done any research. Offhand I would argue that when the cost applicable to the contract type is unknown, there is no price for purposes of 15.403-1 (1)(c)(1) Adequate price competition.
- R
Retreadfed
May 20, 2019 · 7y ago
Neil Roberts said:
I looked at the definition of price in 15.401, Retreadfed. I have not done any research. Offhand I would argue that when the cost applicable to the contract type is unknown, there is no price for purposes of 15.403-1 (1)(c)(1) Adequate price competition.
FAR 15.401 reads
As used in this subpart-“Price” means cost plus any fee or profit applicable to the contract type.
Since 15.403-1 is a part of subpart 15.4, why would the definition of "price" in 15.401 not be the definition of "price" in 15.403-1?
- N
Neil Roberts
May 20, 2019 · 7y ago
Retreadfed said:
FAR 15.401 reads
As used in this subpart-“Price” means cost plus any fee or profit applicable to the contract type.
Since 15.403-1 is a part of subpart 15.4, why would the definition of "price" in 15.401 not be the definition of "price" in 15.403-1?
The definition is unchanged. I am saying that the cost "applicable to the contract type" is unknown and therefore "not applicable to the contract type." If it is "not applicable," the concept of price is essentially voided in 15.403-1 adequate price competition.
I am not saying that competition is absent when two or more propose a CPFF contract type. To me, competition is not the same as adequate price competition.
I would like to read other views especially those that have reference to cases. I am willing to reconsider whether my view is sustainable by cases or FAR rationale. However, I am less willing to change my view if it turns out to be only my business practice.
- R
Retreadfed
May 20, 2019 · 7y ago
Neil Roberts said:
However, I am less willing to change my view if it turns out to be only my business practice.
Neil, do you view FAR 15.403-1 or -2 as imposing any restrictions on your ability to obtain certified cost or pricing data from potential subcontractors? Put another way, do you believe you have the discretion to require subcontractors to submit certified cost or pricing data when it is not required by these FAR subsections?
- N
Neil Roberts
May 20, 2019 · 7y ago
Retreadfed: I believe there is no discretion but to comply with United States Code requirements as may be construed and interpreted by the federal common law of government contracts. In keeping with the posted facts to start with, perhaps there is authority that a CPFF subcontract can be based on adequate price competition when there is one or more bidders?
- R
Retreadfed
May 21, 2019 · 7y ago
Neil Roberts said:
I believe there is no discretion but to comply with United States Code requirements
Neil, the reason I asked my earlier question was your reference to business practices. In regard to complying with the US Code, the relevant statutes (10 U.S.C. 2306a for DoD), do not impose any requirements on contractors or subcontractors. They only impose requirements on the government. One of those requirements is to require potential contractors and subcontractors to submit certified cost or pricing data in specified circumstances. The statutes also impose restrictions on when the government can require the submission of certified cost or pricing data. Some of these statutory restrictions are implemented in FAR 15.403. Note that the statutes and FAR only impose restrictions on the government obtaining certified cost or pricing data. Neither contains a restriction on contractors obtaining cost or pricing data when it is not required by the FAR or statutes. As has been discussed in this forum before, contractors sometimes have policies that require them to obtain certified cost or pricing data from subcontractors when it is not required by the terms of their contract that implement the statutes and FAR. Therefore, you as a prime can attempt to require subcontractors to submit certified cost or pricing data when it is not required by the terms of your contract. Thus, if you have a business practice of requiring a single source subcontractor to submit certified cost or pricing data in regard to a CPFF subcontract when multiple sources were solicited, I see no contractual, statutory or regulatory impediment to doing so, although you may get push back from the subcontractor.
On the other hand, as a prime contractor, I would be surprised if you would try to convince the government that you should submit certified cost or pricing data in regard to a CPFF contract when you are the only offeror although others were solicited.
- j
joel hoffman
May 22, 2019 · 7y ago
Retreadfed said:
Neil, the reason I asked my earlier question was your reference to business practices. In regard to complying with the US Code, the relevant statutes (10 U.S.C. 2306a for DoD), do not impose any requirements on contractors or subcontractors. They only impose requirements on the government.
You might want to review the 10 USC 2306(a) again. The statute states that the Contracting Officer shall require that the contractor or Offeror to submit cost or pricing data and for subs to submit C&P data as applicable.
It also requires that the contractor submit it and to obtain C&P from subs or prospective subs as applicable.
It requires a sub or prospective sub to submit it, where applicable.
I reread my old Briefing papers on TINA and they clearly state that the prospective contractor or contracting shall submit..., shall review..., etc.
- N
Neil Roberts
May 22, 2019 · 7y ago
Retreadfed said:
Neil, the reason I asked my earlier question was your reference to business practices. In regard to complying with the US Code, the relevant statutes (10 U.S.C. 2306a for DoD), do not impose any requirements on contractors or subcontractors. They only impose requirements on the government. One of those requirements is to require potential contractors and subcontractors to submit certified cost or pricing data in specified circumstances. The statutes also impose restrictions on when the government can require the submission of certified cost or pricing data. Some of these statutory restrictions are implemented in FAR 15.403. Note that the statutes and FAR only impose restrictions on the government obtaining certified cost or pricing data. Neither contains a restriction on contractors obtaining cost or pricing data when it is not required by the FAR or statutes. As has been discussed in this forum before, contractors sometimes have policies that require them to obtain certified cost or pricing data from subcontractors when it is not required by the terms of their contract that implement the statutes and FAR. Therefore, you as a prime can attempt to require subcontractors to submit certified cost or pricing data when it is not required by the terms of your contract. Thus, if you have a business practice of requiring a single source subcontractor to submit certified cost or pricing data in regard to a CPFF subcontract when multiple sources were solicited, I see no contractual, statutory or regulatory impediment to doing so, although you may get push back from the subcontractor.
On the other hand, as a prime contractor, I would be surprised if you would try to convince the government that you should submit certified cost or pricing data in regard to a CPFF contract when you are the only offeror although others were solicited.
Retreadfed, and I would be surprised if the Government awarded the only bidder a high dollar value CPFF contract by obtaining certified cost or pricing data only when prompted by the only bidder!
I referenced only the statute in my response to you because I have not done the research to determine whether the implementing FAR is consistent with the statute. I find both to be very complex and confusing. I would surely welcome some authoritative treatise that explains and analyzes both in detail paragraph by paragraph.
As to the business practice, I still believe that all cost reimbursement contracts are essentially negotiated and therefore "adequate price competition" has no place in those awards whether there are one or more bidders. Therefore, certified cost or pricing data should be required when over the threshold. I could perhaps be persuaded with a well reasoned case or interpretation otherwise. I personally abhor beating up two or more bidders with requests for cost or pricing data, or negotiating the best value supplier price lower, where there is already adequate price competition as offered.
- j
joel hoffman
May 22, 2019 · 7y ago
For DoD:
“215.371-3 Fair and reasonable price.
(a) If there was “reasonable expectation… that …two or more offerors, competing independently, would submit priced offers” but only one offer is received, this circumstance does not constitute adequate price competition unless an official at a level above the contracting officer approves the determination that the price is reasonable (see FAR 15.403-1(c)(1)(ii)).”
The above reflects DoD policy not to assume that adequate competition exists where multiple firms were solicited but only one responded or where multiple firms expressed an interest but only one responded.
- R
Retreadfed
May 22, 2019 · 7y ago
joel hoffman said:
It also requires that the contractor submit it and to obtain C&P from subs or prospective subs as applicable.
It requires a sub or prospective sub to submit it, where applicable.
Joel, go back and read the statute again. It clearly states that (sub)contractors "shall be required" to do the things you mention. It does not say that the (sub)contractor is to do these things without first being required to do so. In both cases, the contracting officer is the one who requires these actions. This is done by including FAR 52.215-20 in RFPs and 52.215-12 in RFPs and contracts.
- j
joel hoffman
May 22, 2019 · 7y ago · edited 7y ago
Yes. By Statute, the “head of an agency shall require offerors, contractors,and subcontractors to make cost or pricing data available”, as described in the Statute, where applicable.
Yes, the provision and applicable clauses are required in negotiated acquisitions by the Code of Federal Regulations
However, the Christian Doctrine has been applied to the Truth in Negotiations Act., when the government omitted mandatory TINA clauses that were applicable to the type of acquisition to implement this deeply ingrained procurement policy. Thus, the implementing clauses were read into the contracts.
Reference, for instance: https://www.weitzmorgan.com/2017/06/16/christian-doctrine/
At this point, I’m not sure which scenario or what requirement is under debate in this thread. A CPFF prime received one subcontractor CPFF proposal and one question seemed to be whether or not there was “adequate price competition” to assume that the price is fair and reasonable.
DoD policy is that the scenario doesn’t automatically constitute adequate price competition to establish a presumption of “fair and reasonable pricing”.
- V
VipinOwl
May 23, 2019 · 7y ago
On 5/21/2019 at 10:04 PM, Neil Roberts said:
As to the business practice, I still believe that all cost reimbursement contracts are essentially negotiated and therefore "adequate price competition" has no place in those awards whether there are one or more bidders. Therefore, certified cost or pricing data should be required when over the threshold.
For my own understanding, are we discussing subcontractor awards or prime awards? It is my understanding that when awarding a CPFF prime contract, even given adequate price competition, cost realism must be performed, and as such cost or pricing data must be obtained, so price analysis alone will not suffice. Therefore, in the presence of adequate price competition, other than cost or price data shall be submitted, at a minimum, when awarding a CPFF contract, is that correct?
FAR 15.404-3(b)1, states that "a prime contractor shall conduct appropriate cost or price analysis to establish the reasonableness of proposed subcontractor prices". Question: Is the prime contractor's determination of a fair and reasonable price for its CPFF subcontractor, held to the same cost or price determination standards as the Government for a CPFF? For example, if the prime is contemplating a CPFF subcontract award over the threshold, but where adequate price competition is present, shall the government require the contractor to perform cost realism analysis, given the subcontract type? FAR 15.404-3(c) states, "Any contractor or subcontractor that is required to submit certified cost or pricing data also shall obtain and analyze certified cost or pricing data before awarding any subcontract, purchase order, or modification expected to exceed the certified cost or pricing data threshold, unless an exception in 15.403-1(b) applies to that action." Will adequate price competition suffice in the case of a CPFF subcontract award?
- P
Patrick Mathern
May 23, 2019 · 7y ago
VipinOwl said:
It is my understanding that when awarding a CPFF prime contract, even given adequate price competition, cost realism must be performed, and as such cost or pricing data must be obtained, so price analysis alone will not suffice.
Depends on what you mean by "price analysis." If you consider analysis of other than certified cost or pricing data to fall under cost analysis, then so be it...you're conducting cost analysis instead of price analysis. Just note that you're NOT required to obtain certified cost or pricing data and conduct a full FAR 15 compliant cost analysis.
Cost Realism is very different from Cost Analysis.
- j
joel hoffman
May 23, 2019 · 7y ago
“Adequate competition” is more indicative of price reasonableness than cost realism in the case of a cost reimbursable competition. Cost realism analysis may be necessary due to pressure or tendency to understate costs in a competitive CP environment.
Patrick Mathern said:
Depends on what you mean by "price analysis." If you consider analysis of other than certified cost or pricing data to fall under cost analysis, then so be it...you're conducting cost analysis instead of price analysis. Just note that you're NOT required to obtain certified cost or pricing data and conduct a full FAR 15 compliant cost analysis.
Cost Realism is very different from Cost Analysis.
A cost realism analysis is discussed under 15.404-1 (c) as one form of COST analysis.
- P
Patrick Mathern
May 23, 2019 · 7y ago
Neil, in reference to...
On 5/21/2019 at 7:04 PM, Neil Roberts said:
As to the business practice, I still believe that all cost reimbursement contracts are essentially negotiated and therefore "adequate price competition" has no place in those awards whether there are one or more bidders. Therefore, certified cost or pricing data should be required when over the threshold. I could perhaps be persuaded with a well reasoned case or interpretation otherwise.
...the purpose of competition is to motivate sellers to set forth a proposal based on the stated award criteria. "Adequate competition" simply requires two or more bidders to respond with responsive and viable offers. If that criteria is met, the bidders are relieved of the requirement for certified cost or pricing data.
Hurdles:
- 2 bidders (self explanatory and objectively determined)
- Responsive offers (self explanatory and objectively determined based on comparison of proposal with RFP)
- Viable offers (this is where cost realism comes into play)
If the viable offers hurdle wasn't cleared, I would work with the bidder(s) to come to terms on that point. They will likely be motivated to participate when given a choice between cost realism and submitting certified cost or pricing data.
- P
Patrick Mathern
May 23, 2019 · 7y ago
joel hoffman said:
A cost realism analysis is discussed under 15.404-1 (c) as one form of COST analysis.
Take another look, Joel. While it's discussed in 15.404-1(c), it's actually set forth specifically in 15.404-1(d) and is separate from either cost or price analysis.
Having said that, and to your point Joel, it most closely resembles cost analysis in that you're evaluating separate elements of cost. My original response aimed at avoiding confusing cost realism with cost analysis of certified cost or pricing data.
- N
Neil Roberts
May 23, 2019 · 7y ago
VipinOwl said:
For my own understanding, are we discussing subcontractor awards or prime awards? It is my understanding that when awarding a CPFF prime contract, even given adequate price competition, cost realism must be performed, and as such cost or pricing data must be obtained, so price analysis alone will not suffice. Therefore, in the presence of adequate price competition, other than cost or price data shall be submitted, at a minimum, when awarding a CPFF contract, is that correct?
FAR 15.404-3(b)1, states that "a prime contractor shall conduct appropriate cost or price analysis to establish the reasonableness of proposed subcontractor prices". Question: Is the prime contractor's determination of a fair and reasonable price for its CPFF subcontractor, held to the same cost or price determination standards as the Government for a CPFF? For example, if the prime is contemplating a CPFF subcontract award over the threshold, but where adequate price competition is present, shall the government require the contractor to perform cost realism analysis, given the subcontract type? FAR 15.404-3(c) states, "Any contractor or subcontractor that is required to submit certified cost or pricing data also shall obtain and analyze certified cost or pricing data before awarding any subcontract, purchase order, or modification expected to exceed the certified cost or pricing data threshold, unless an exception in 15.403-1(b) applies to that action." Will adequate price competition suffice in the case of a CPFF subcontract award?
VipinOwl, my view is from the eyes of a prime contractor awarding a CPFF subcontract. Many commentators on this site seem to be from the government side. I am not. I do not know enough about government practices or interpretations of applicable regulations. So, I have nothing to comment on with respect to your first paragraph, which questions award of CPFF primes.
As to your 2nd paragraph, you mention "fair and reasonable price" and "cost or price determination standards." I am unable to compare industry to government because I do not have enough information. However, I can say that it would not be unusual for the government to question the adequacy of a prime contractor's subcontract transaction conclusion that a price was fair and reasonable. You also asked whether "adequate price competition suffice in the case of a CPFF subcontract award." I do no know how the government might view this. I have already expressed my prime contractor side business practice view on this---no.
- j
joel hoffman
May 24, 2019 · 7y ago
Patrick Mathern said:
Take another look, Joel. While it's discussed in 15.404-1(c), it's actually set forth specifically in 15.404-1(d) and is separate from either cost or price analysis.
Having said that, and to your point Joel, it most closely resembles cost analysis in that you're evaluating separate elements of cost. My original response aimed at avoiding confusing cost realism with cost analysis of certified cost or pricing data.
Patrick, I performed price and cost analysis for many years on new construction contracts and mods, changes and claims thereto.
Cost realism is a form of cost analysis but generally for a separate purpose than determining that a price is “fair and reasonable”.
It doesn’t matter that cost realism is also discussed in more detail in a separate paragraph (d). That paragraph merely describes cost realism analysis in more detail.
Note that “technical analysis” is also an element of and an input into the cost analysis process, where applicable. It is especially applicable to construction contracting. Its discussed in detail in a separate paragraph (e). A technical analysis is particularly useful in forward pricing negotiations. It is incorporated into the cost analysis documentation and pre-negotiations objectives.
In fact, the DCAA auditors always mentioned whether or not we had performed a technical analysis for input to the audit.
- V
VipinOwl
May 24, 2019 · 7y ago
joel hoffman said:
Cost realism is a form of cost analysis but generally for a separate purpose than determining that a price is “fair and reasonable”.
Joel,
It's interesting you say that. I never considered cost realism as a tool for other than a fair and reasonable price determination. Per the FAR, "Use techniques such as, but not limited to, price analysis, cost analysis, and/or cost realism analysis to establish a fair and reasonable price". I also consider cost realism, a form of cost analysis.
- j
joel hoffman
May 24, 2019 · 7y ago · edited 7y ago
VipinOwl said:
Joel,
It's interesting you say that. I never considered cost realism as a tool for other than a fair and reasonable price determination. Per the FAR, "Use techniques such as, but not limited to, price analysis, cost analysis, and/or cost realism analysis to establish a fair and reasonable price". I also consider cost realism, a form of cost analysis.
I also consider it a tool to determine whether a price is “fair and reasonable”. However, the Appeals Boards have carved out a distinction by saying, in essence, that “fair and reasonable” tends to look at the upper end while “cost realism” looks to see if it is unrealistically “low” for the scope and probable effort.
For cost reimbursement price or cost evaluations, cost realism analysis is usually important for various reasons, as explained in 15.4. Due to the nature of cost plus, the contractor’s primary risk is a lower fee in order to be price competitive. The government’s risk is that it will have to pay more if the contractor uses the budget without completing the effort. Accidental or deliberate lowballing is possible with an unrealistically low price.
For competitive fixed price evaluations, what one can do with the results of a cost realism analysis is more restrictive. You can ask the Offeror or contractor to verify their price. If there are discussions, you can raise the issue if you think that they can’t do the work for that price, particularly if you think that it would endanger performance or result in poor relations, corner cutting, trying to make up the difference through excess claims, etc. I’ve seen defaults and even bankruptcies by awarding contracts at unrealistically low prices. Accidental lowballing is not good for either the contractor or the government.
I believe that the position of the boards and courts is that a contractor may assume the risk for lowballing on a firm fixed price contract effort. However, if the government determines that a lowball price would endanger performance, it can take that into consideration in a trade off. But to declare a low price disqualifying may be a responsibility matter, with all the restrictions and other ramifications.
For either CP or FP, it is important to ensure that the firm understands the scope and complexity, etc. of the effort, to avoid pricing mistakes.
There is much more to the concept of cost realism but we don’t need to discuss all the details here.
It is part of cost analysis for Part 15 pricing procedures when applicable - yes, normally for CP. Sometimes for FP.
- R
Retreadfed
May 24, 2019 · 7y ago
VipinOwl said:
It is my understanding that when awarding a CPFF prime contract, even given adequate price competition, cost realism must be performed, and as such cost or pricing data must be obtained, so price analysis alone will not suffice. Therefore, in the presence of adequate price competition, other than cost or price data shall be submitted, at a minimum, when awarding a CPFF contract, is that correct?
No. Certified cost or pricing data is required in the circumstances described in FAR 15.403. Note that 15.403-1 explicitly prohibits contracting officers from obtaining certified cost or pricing data when the conditions listed there exist. Note that 15.403-1 does not make any distinctions in regard to how the contract is priced. Thus, if the conditions in 15.403-1 exist, certified cost or pricing data may not be obtained in regard to a cost reimbursement contract.
On the other hand, if the conditions in 15.403-1 exist, data other than certified cost or pricing data may be submitted if that is the only way the contracting officer can determine that the price quoted is fair and reasonable. This data is analyzed using price analysis.
In short, there is no blanket requirement that certified cost or pricing data or even data other than certified cost or pricing data must be submitted when the government contemplates award of a cost reimbursement contract.
- N
Neil Roberts
May 24, 2019 · 7y ago · edited 7y ago
VipinOwl, throughout this posting, I have not been quite sure of your understanding about what party is required to comply with a particular FAR /FAR Supplement. For example, if a regulation states throughout it "contracting officer shall...," that regulation is not worded as applying to contractors. Vice versa is also true. I have met many contractor and government professionals that did not know or understanding the difference. FAR 15.403-1(c)(1) is one of those confusing areas. If your focus is adequate price competition regarding a prime contractor's subcontract, has it been your understanding that FAR 15.403-1(c)(1) applies to the transaction, and also applies to a government awarded contract? Just checking with you.
- R
Retreadfed
May 24, 2019 · 7y ago
Neil Roberts said:
For example, if a regulation states throughout it "contracting officer shall...," that regulation is not worded as applying to contractors. Vice versa is also true.
I have to disagree. As has been stated in this forum several times, the FAR does not apply to contractors. Instead, it applies to government personnel when executing an acquisition. FAR 1.101 reads in part "The Federal Acquisition Regulations System is established for the codification and publication of uniform policies and procedures for acquisition by all executive agencies." Contractors are required to comply with the terms of their contracts. If a contract term incorporates a FAR section, the contractor must comply with that section to the extent it applies to that contract.
- N
Neil Roberts
May 24, 2019 · 7y ago · edited 7y ago
On 5/24/2019 at 12:34 PM, Retreadfed said:
I have to disagree.
Retreadfed, Are you disagreeing with my view about sentence grammar? I don't understand what the disagreement is and its connection to your response. I didn't say anything about whether a contractor is required or not required to comply with the terms of their contract.