PoP Violations
Started by Corduroy Frog · May 29, 2019 · 2 replies
- COriginal post
Corduroy Frog
May 29, 2019 · 7y ago
When (if ever) is it possible to charge a contract outside of the Period of Performance?
What if the government simply wants performance in advance of their stated PoP?
- R
Retreadfed
May 29, 2019 · 7y ago
When the contract contains a pre-award contract costs provision. See FAR 31.205-32.
- h
here_2_help
May 29, 2019 · 7y ago
You can charge after the end of the PoP in the following circumstances:
1. Any completion-type contract where funding is not limited by year. For example -- FFP contracts with required deliveries.
You can charge before the beginning of the PoP in the following circumstances:
1. In accordance with FAR 31.205-32.