Follow-on duration limit for GSA Schedule Task Orders FAR Subpart 8.4
Started by KON05012006 · Jun 13, 2019 · 1 replies
- KOriginal post
KON05012006
Jun 13, 2019 · 6y ago
Is there a time limit for the duration of a follow-on task order under a GSA schedule contract for information technology (IT) services and supplies under FAR Subpart 8.4?
- f
formerfed
Jun 13, 2019 · 6y ago
The exception states “in the interests of economy and efficiency...” so it boils down to discretion and deciding are you wasting government’s and industry’s time with competing knowing which source will likely win? No, there’s no absolute time limit and you have to use judgement. It all depends on the exact nature of the requirement and what the incumbent possesses in terms of techniques, skills, methodologies , expertise, and approaches.