Building up engineering cost estimates
Started by Kaseybaja · Aug 26, 2019 · 2 replies
- KOriginal post
Kaseybaja
Aug 26, 2019 · 6y ago
What are the significant factors which contractors use to build up their engineering cost estimates?
- j
joel hoffman
Aug 26, 2019 · 6y ago
Please clarify what you are referring to as an engineering cost estimate.
Are you referring to a cost estimate for engineering services or to a detailed cost estimate for something else?
From the Business Dictionary: “engineering cost estimate. Detailed cost estimate for a project, computed by estimating the cost of every activity in a work breakdown structure, summing these estimates, and adding appropriate overheads.”
The above definition should help answer your question, either way.
What do you mean by “factor”?
- h
here_2_help
Aug 27, 2019 · 6y ago
On 8/26/2019 at 12:53 PM, Kaseybaja said:
What are the significant factors which contractors use to build up their engineering cost estimates?
Have you reviewed the Air Force Institute of Technology Contract Pricing Reference Guide, Volume 3, Chapter 7?