RFP for POP Extension
Started by Dom · Apr 29, 2020 · 3 replies
- DOriginal post
Dom
Apr 29, 2020 · 6y ago
Hi, I am new to this forum. I would like to know if I am required to have another set of RFP to extend the Period of Performance with cost involved.
- f
formerfed
Apr 30, 2020 · 6y ago
I assume this is an existing contract where you want to extend the performance period on a noncompetitive basis? No need for an RFP unless your agency policy requires it. Just ask the contractor to submit pricing and whatever substantiating data you need.
- j
joel hoffman
Apr 30, 2020 · 6y ago
formerfed said:
I assume this is an existing contract where you want to extend the performance period on a noncompetitive basis? No need for an RFP unless your agency policy requires it. Just ask the contractor to submit pricing and whatever substantiating data you need.
Isn’t asking the contractor to submit pricing and supporting data for a modification a request for a proposal? It is for some agencies.
Dom, is this a time extension to perform the original scope of work or is it an extension of services?
An RFP “solicitation” with all UFC sections isn’t required, if that is Dom’s question.
- j
joel hoffman
Apr 30, 2020 · 6y ago
Dear Bob, would you mind please moving this topic from “Contracting Workforce” to “contract Administration”? It has nothing to do with workforce questions or issues. Thanks!