FAR threshold updates on current contracts

Started by brad · Jun 1, 2020 · 1 replies

  1. b

    brad

    Jun 1, 2020 · 6y ago

    Original post

    Can the contracting officer update FAR thresholds on existing contracts?   for example... the micro was at 3k at award but is now 10k?

  2. j

    ji20874

    Jun 2, 2020 · 6y ago

    I don't understand the question.  If the purchase order (contract) is already awarded, leave it alone.  Thresholds such as the micro-purchase threshold apply in pre-award situations (before contracts are awarded) to settle on clauses, competition requirements, and so forth -- all of which is water under the bridge once the contract is awarded.  Leave it alone, and enforce it as it is written and as it was agreed to.