IDIQs, Excusable Delays, and the Changes Clause
Started by Philistines · Jul 17, 2020 · 36 replies
- POriginal post
Philistines
Jul 17, 2020 · 5y ago
My Agency frequently awards IDIQs. Unfortunately, we have lost a lot of design time for new Task Orders due to pandemic. Unfortunately, many IDIQs ordering periods are set to end. We are having a vigorous discussion as to whether Excusable Delays or the Changes Clauses would be appropriate to extend the ordering period. The basic arguments against using them are that IDIQs are contracts to potentially order work as opposed to an actual order for work. While that argument may make sense for a rejection of the Excusable Delays clause, it would still seem appropriate to allow for the changes clause to alter the delivery schedule of all contracts under a multiple award IDIQ. In effect, we are changing the delivery time frame for the potential work to be ordered. My questions are a) If others have had this conversation in their agencies, what was the consensus/practices adopted? and 2) Has anyone seen either of these clauses used in this type of situation?
- C
C Culham
Jul 17, 2020 · 5y ago
Folks may ask so I will pop the question first. Commercial item contracts or not? Does not make a big difference but the excusable delay and changes clauses vary between commercial and non-commercial.
- P
Philistines
Jul 17, 2020 · 5y ago
Definitely non-commercial. They are for specialized technical services almost exclusively. Typically, they are CPFF but there are some instances of FFP and T&M. Supplies can on occasion enter into the equation in combination with the services but we do not use our IDIQs for supplies.
- j
ji20874
Jul 17, 2020 · 5y ago · edited 5y ago
Philistines,
I don't think Excusable Delays will work for ordering period extensions. However, it could work for task order delivery (or performance) extensions, but you need to read the Excusable Delays text in your contract and satisfy yourself that it fits your circumstance.
I don't think the Changes clause will work for either one.
My thought: Use Excusable Delays for task order time extensions (only time, no money) (but only after you read the text in your contract and satisfy yourself that it fits). For ordering period extensions for the parent IDIQ contracts, write a J&A and proceed.
- P
Philistines
Jul 17, 2020 · 5y ago
JI20874 - That is what we are doing. Using the Delays clause to extend TOs and J&As (our JEFOs) to extend IDIQs. However, the non-comp process is purposefully burdensome and we are looking for ideas on extending ordering periods.
I haven't found a GAO case dealing with the issue so it could be territory that legal counsel has fenced off.
- j
joel hoffman
Jul 17, 2020 · 5y ago
Philistines said:
JI20874 - That is what we are doing. Using the Delays clause to extend TOs and J&As (our JEFOs) to extend IDIQs. However, the non-comp process is purposefully burdensome and we are looking for ideas on extending ordering periods.
I haven't found a GAO case dealing with the issue so it could be territory that legal counsel has fenced off.
Has your legal counsel nixed the idea and you are looking for support for your idea to convince legal?
- j
ji20874
Jul 17, 2020 · 5y ago
I don't think you will find a way around JEFOs (J&As) for real bona fide changes in scope -- and extensions of ordering periods are changes in scope, unless they can be made to fit under a contract clause that allows for adjustments or equitable adjustments. For the parent IDIQ contracts, finding a clause that will cover your ordering period extension will take some creativity.
- D
Don Mansfield
Jul 17, 2020 · 5y ago
ji20874 said:
For ordering period extensions for the parent IDIQ contracts, write a JEFO and proceed -- cite FAR 16.505(b)(2)(i)(A).
Wouldn't FAR part 6 apply to such a modification?
- j
ji20874
Jul 17, 2020 · 5y ago · edited 5y ago
Don Mansfield said:
Wouldn't FAR part 6 apply to such a modification?
Yes.
- D
Don Mansfield
Jul 17, 2020 · 5y ago
ji20874 said:
No.
How so? What exception at FAR 6.001 applies? You said that "extensions of ordering periods are changes in scope." FAR 6.001 only states an exception for modifications that are within the scope of the contract.
- j
ji20874
Jul 17, 2020 · 5y ago
You're right -- we're talking about the parent IDIQ contract (not an order) so a J&A is probably right.
- j
ji20874
Jul 17, 2020 · 5y ago
Philistines,
One class J&A instead of many individuals?
- P
Philistines
Jul 17, 2020 · 5y ago
@joel hoffman That is correct. Legal counsel and most of the the CO community wants us to write a J&A. We will but I wanted to see if anybody else had any experiences or thoughts on using either clause.
The GAO has been fairly generous towards agencies in determining when competition is triggered by the Changes clause. My thought was 'How would the competition have been impacted if this change (longer ordering period) was known at the time of the solicitation? The only impact that I see is that maybe somebody would have bid on a six year IDIQ that did not bid on a 5 year one but I consider that a stretch given the competition that we have. Only companies who did not bid would have standing to protest on that basis. None of the losing bidders could argue that they were disadvantaged by the longer extension. IMO.
I'm just fishing for thoughts or experiences.
- P
Philistines
Jul 17, 2020 · 5y ago
ji20874 - We do use those from time to time. The posting requirements still mandate multiple postings. But yes, the J&As will look incredibly similar. From a process (approval/clearance perspective), it's the same amount of work.
- D
Don Mansfield
Jul 17, 2020 · 5y ago
Is the ordering period stated with calendar dates in the contract? Or does it state that the ordering period is "12 months"? If the latter, was there a time period where the Govt. couldn't issue orders or the contractor couldn't accept them because of the pandemic?
- P
Philistines
Jul 17, 2020 · 5y ago
We have variations but typically, it states five years from the date of signature. Though some COs will put in a specific date. I do like your thinking though...
Some would say that we were open for business but if other business (pandemic response) overwhelmed us, then we could not order during that time frame.
Is that where you were going?
- D
Don Mansfield
Jul 17, 2020 · 5y ago
Yes. The way I see it, you can measure a period of time with a calendar or a stop watch. If you measure the period with a stop watch, it could read less than 12 months even though 12 months have passed on the calendar. Perhaps you had to stop the watch during the pandemic?
- C
C Culham
Jul 17, 2020 · 5y ago
Backtracking...
Excusable delay - A remedy for a CONTRACTORS failed performance, correct?
Changes (other than commercial item) - extending performance is not one of the unilateral rights granted.
Extending performance with out the blah blah blah of a J&A. Depends on scope of contract does it not? By example - if contract states it is for the purpose of providing technical assistance to accomplish 25 NEPAS and due to effects of COVID the government can only get stuff to contractor for 20 is it a change in scope to add more time to the IDIQ so the 5 can be accomplished? Maybe not.
The basic standard of GAO sticks my brain on a very interesting question posed by the OP. That standard is - if there is a material difference between the modified contract and the original contract. I would personally look to the stated scope of the contract and not just that it states a 5 year period of performance as a possible "in" to extend with a basic determination to support the mod versus a J&A.
Thoughts?
- P
Philistines
Jul 17, 2020 · 5y ago
My thought on the Changes clause is the Time of Performance. A small hook to hang my hat but I just need it to hold up for a little bit.
The actual scope meaning the work to be done doesn't change. We just need more time.
RE: Delays - We're a polite bunch. We prefer to say that the contractor could not perform rather than failed. But yes, the clause is justified when an event impacts the contractor, not the government. USG caused delays opens up the issue of equitable adjustments, which does not apply here.
- j
ji20874
Jul 17, 2020 · 5y ago
Philistines,
If I were doing an adjustment under the Excusable Delays clause, I would use the wording of the Excusable Delays clause. But that's me.
- P
Philistines
Jul 17, 2020 · 5y ago
ji20874 - Not sure the point that you are making. Perhaps you're restating that the Delays clause is not a viable choice in regards to an IDIQ ordering period. Or perhaps you are referring to the term adjustment. It is our legal team's opinion that you cannot make any adjustment but time under the 52.249-14 that we can only add time to the contract.
- j
ji20874
Jul 17, 2020 · 5y ago
No, my point was that whenever I use any contract clause as the basis for an action, I always try to use the same words that the clause uses. You said you don't like to use the word "failed" and prefer to use a more polite wording instead, but isn't a contractor failure a necessary prerequisite to using the Excusable Delays clause?
I don't know your contracts well enough to know if one of the contract clauses will allow you to extend the ordering period of the parent IDIQ contracts. IDIQ contracts seem rarely to be set up like Carl suggested, and for those, he is right -- an extension of the ordering period need not be a change in scope. If Government operations were shut down during the pandemic, you might be able to justify an extension of the ordering period as Don suggested. But for many (most?) IDIQ contracts, you might have to use a J&A.
But if your organization doesn't want to do J&As, then don't. Let the parent contracts die as scheduled. Here is a novel thought: If the contracts are important to your agency's mission, then your attorneys and everyone else should eagerly help you get the J&As done -- you shouldn't have to fight them. Just tell your agency executives now that you want to extend the ordering periods but your attorneys refuse to let you, and that the contracts will die soon.
- P
Philistines
Jul 17, 2020 · 5y ago
ji20874 - It's not the J&As are problematic in theory. We deliberately created a cumbersome process to make people not use them. Once you release the Bureaucratic Kraken though, you find it very hard to bind it again.
I am simply trying to lighten the load of an overworked 1102 workforce faithfully fighting the good fight to get the work done. Whenever I see a process that does not add value or impact outcomes, I always try to remove it.
Thank y'all for the good input.
Others feel free to opine if the feeling strikes.
- R
Retreadfed
Jul 18, 2020 · 5y ago
Philistines said:
the clause is justified when an event impacts the contractor, not the government. USG caused delays opens up the issue of equitable adjustments, which does not apply here.
Philistines, note that the Excusable Delay clause states in part that delays caused by "acts of the Government in either its sovereign or contractual capacity, epidemics and quarantine restrictions," are the types of delays that are excusable. Are you reading government caused delays our of the clause?
- D
Don Mansfield
Jul 20, 2020 · 5y ago
I think that you're under the impression that you need a contract clause to support an extension of the ordering period due to the pandemic. If that's what you think, then I disagree. Contract clauses like Excusable Delays and Changes deal with a party's right to an adjustment under prescribed conditions. The presence or absence of such clauses in a contract does not limit the parties' rights to negotiate adjustments to contract terms to adapt to conditions that they did not contemplate during contract formation. Further, such adjustments are not necessarily outside the scope of the competition.
For example, let's say the Government competitively awards a contract to Acme Corp. to deliver 100 widgets by 31 July at a price of $100K/widget. On 17 July Acme Corp. calls the contracting officer and asks if the delivery date can be moved to 31 August because they are experiencing an unusually high volume of orders. The contracting officer checks with the customer, who is ok with the later delivery. The contracting officer then agrees to adjust the delivery date if the contractor agrees to a price reduction of 5% as consideration. Contractor agrees and the contract delivery date and price are modified accordingly. The contracting officer doesn't write a J&A.
The change agreed to by the parties has nothing to do with the Excusable Delays clause, Changes clause, or any other standard FAR clause. The modification is not necessarily outside the scope of the competition. Do you think any law or regulation has been violated?
Let's say I were administering an IDIQ contract that had a 12 month ordering period and, during that period, the contractor was unable to accept orders due to circumstances beyond its control for a period of two months. I would argue that the clock on the 12 month period stopped during those two months. If someone were to argue that the 12 month period necessarily ended at the end of 12 calendar months, I would ask why a calendar (rather than a stop watch) was necessarily the correct way to measure the time period. I think you would still have two more months of ordering period at the end of 12 calendar months. If the contract had a stated end date to the ordering period, I don't think a modification to change the date would necessarily be outside the scope of the competition.
Note that this has nothing to do with the Excusable Delays clause, the Changes clause, or any other standard FAR clause. It's just the parties adapting to unforeseen conditions. That's what contract administration is all about.
- j
ji20874
Jul 20, 2020 · 5y ago
Don makes a good point that the clauses grant the contractor the right to an adjustment, but that the parties may often agree to an adjustment without invoking the clause.
- P
Philistines
Jul 20, 2020 · 5y ago
In spirit and in personal practice, I am in complete agreement with Don that we should manage contracts in a way that the government gets its needed requirements in a reasonable way without disadvantaging any of the parties including those who lost the initial competition. Simply put, do what makes sense for the government without screwing anybody over. Another good rule - If the FAR does not say NO, then it must mean YES.
Unfortunately, living in a litigious society, legal counsel will often advise a party to do things that are not necessary simply to insure legal protections against a potential future liability such as putting a warning label that says 'Contents Hot' on a cup that is also labelled 'Hot Chocolate'. A better world it would be if we were left to our own devices to learn that Hot Chocolate is indeed Hot. (But what would we do with all the empty courthouses?)
- R
Retreadfed
Jul 20, 2020 · 5y ago
Philistines said:
legal counsel will often advise a party to do things that are not necessary simply to insure legal protections against a potential future liability
The operative word in this phrase is "advise."
- j
ji20874
Jul 20, 2020 · 5y ago
Retreadfed,
In some organizations, attorneys effectively have absolute veto power over contracting officers -- that's just reality.
- P
Philistines
Jul 20, 2020 · 5y ago
ji20874 - Yes, they do. It's called a clearance (Is it legal?) but it sure looks like an approval (Should you do it?).
- f
formerfed
Jul 20, 2020 · 5y ago
There are a few agencies where only attorneys have warrants. In many agencies requiring review and approval prior to award, prior legal review is a requirement before they look at an action. One can’t usually get their approval by overriding or ignoring legal “advice.”
- C
C Culham
Jul 21, 2020 · 5y ago
ji20874 said:
attorneys effectively have absolute veto power over contracting officers
formerfed said:
There are a few agencies where only attorneys have warrants.
Philistines said:
It's called a clearance (Is it legal?)
Ergo the problem.
In this thread Philistines has presented the idea of using clauses to support extension of IDIQ's whose performance period has been affected by agency action (inaction?) due to the pandemic concentrating on use of certain contract clauses. Advice has been provided where clause use may not be appropriate coupled with advice regarding avenues where such extension could be accomplished without use or the demand of a contract "clause". Advice in my view that is sound and based on sensible and acceptable principles supported by both the FAR and case law where no statute, executive order or regulation stands in the way save as noted the possibility that a regulation requires legal review or has bestowed a warrant on legal counsel.
The advice is in vein unless Philistines takes on the monumental task of advising, counseling and to an extent insisting that the assumed blockage - legal counsel - understands the principles of contracting as noted. Sorry to be so blunt here but the Philistines of the world may actually be the road block and not the legal counsel in that the Philistines go along with the risk assessment rather than promoting that even in the light of a potential risk - a protest in this case - done right and under the right circumstances the extension of the IDIQ's might be fulfilled without the absolute risk of a protest being successful. Yep filed maybe but not successful.
"The purpose of defining the Federal Acquisition Team (Team) in the Guiding Principles is to ensure that participants in the System are identified beginning with the customer and ending with the contractor of the product or service. By identifying the team members in this manner, teamwork, unity of purpose, and open communication among the members of the Team in sharing the vision and achieving the goal of the System are encouraged. Individual team members will participate in the acquisition process at the appropriate time."
- j
joel hoffman
Jul 21, 2020 · 5y ago
Putting this thread back into perspective...
Several ID/IQ contracts ordering periods are expiring. The government has been unable to prepare follow on contracts. KO wants to extend the ordering.periods Of the existing IDIQ’s.
these actions are not changes under the changes clause. These actions are not excusable delays on the part of contractors.
These extensions would require out of scope supplemental agreements, pursuant to FAR Part 6 exceptions to full and open competition. you have said that the cause is due to the current COVID-19 pandemic, preventing the agency from competing new ID/IQ contracts.
Considering the fact that the government is trying to be very proactive concerning taking actions in response to the COVID-19 pandemic, my recommendation is to justify it based upon those impacts.
If your agency counsel doesn’t agree, tell them to solve the problem.
- P
Philistines
Jul 21, 2020 · 5y ago
Joel - We don't really have any issue with J&As. I hate doing them when other options exist. The main challenge with the orders is that we are struggling to estimate costs and requirements for implementation given all the unknowns ahead regarding the work environment.
C Culham - I suppose. A lot of agencies have policies requiring clearances on J&As, requirement statements, funding, and bathroom passes. I could go once more into the breach and again and again while pointing out how certain policies increase workload, add no value, and reduce no risk. Have done it many times. But at the end of the day, I need to get the work done so I play the hand I am dealt.
- f
formerfed
Jul 22, 2020 · 5y ago
On 7/17/2020 at 4:58 PM, ji20874 said:
If the contracts are important to your agency's mission, then your attorneys and everyone else should eagerly help you get the J&As done -- you shouldn't have to fight them. Just tell your agency executives now that you want to extend the ordering periods but your attorneys refuse to let you, and that the contracts will die soon.
This makes perfect sense. Don’t try to find other ways to extend that just aren’t proper. If the contracts are important, tell your management what’s going to happen if they don’t get extended. Also if they are important, your user program offices should be able to come up with estimates for your J&A quickly (a few days). A J&A can be processed for critical needs in a few days. You may have to post in beta.SAM but your rational seems self evident and interested companies know they will soon get a shot at a competitive award soon.
The alternative is do the competitive follow on quickly. If requirements haven’t changed much, issuing a solicitation shouldn’t take that much time. Get your management involved and get all stakeholders - legal, policy, reviewers/approves, program offices including technical personnel lined up. - j
joel hoffman
Jul 29, 2020 · 5y ago · edited 5y ago
Ran across this old thread this morning while browsing on-line users:
Inasmuch as Vern Edwards and others weighed in on the topic, it might be helpful here to answer the original questions. It doesn’t tell you what you CAN do as an alternative to the OP’s original question.
An alternative is an out of scope supplemental agreement, citing the delay due to corona virus preventing timely recompetition. Use An appropriate FAR Part 6 exception to full and open competition (e.g., 6.302-2), as well as recent government policies in response to impacts of COVID-19 that would seemingly overcome objections due to “lack of planning”. Get the lawyers to creatively write the details. Let them practice what they learned in law school to be able to argue either side of the same case.
EDIT: Ive seen some very creative justifications used for “urgent and compelling” circumstances without any industry objections, but those were for construction ID/IQ’s and single awards, not services. To quote Thomas Paine, “These are times that try men’s souls.”
http://www.thisdayinquotes.com/2011/12/times-that-try-mens-souls-summer.html?m=1
- j
joel hoffman
Jul 29, 2020 · 5y ago
Of course, the periods of performance for any open or new task orders should be very carefully limited only to anticipated time required to award replacement contracts and task orders...