Applying Indirects to ODCs

Started by Nicole1986 · Jul 30, 2020 · 4 replies

  1. N

    Nicole1986

    Jul 30, 2020 · 5y ago

    Original post

    Hoping for some insight from others! Recently asked for clarification from the government on the following question - c_an the contractor and subcontractors take their federally approved indirect cost rate on other direct costs?_

    To which the government replied - GSA rates only; must be as identified in the GSA contract. 

    Does this mean that the schedule must specify that indirects can be applied to ODCs?

  2. j

    ji20874

    Jul 30, 2020 · 5y ago

    Are we talking about a T&M schedule contract?  See FAR 52.212-4 with its Alternate I, para. (i)(ii)(D)(1) and (2).  

    Nicole1986 said:

    Does this mean that the schedule must specify that indirects can be applied to ODCs?

    Yes -- and even then, not as a rate but as a fixed dollar amount.

  3. N

    Nicole1986

    Jul 30, 2020 · 5y ago

    ji20874 said:

    Are we talking about a T&M schedule contract?  See FAR 52.212-4 with its Alternate I, para. (i)(ii)(D)(1) and (2).  

    Yes -- and even then, not as a rate but as a fixed dollar amount.

    My apologies, yes this is a T&M schedule contract. Hmmm, I have never seen a schedule that specifies dollar amounts for ODCs. Thank you so much, I will review that FAR clause.

  4. j

    ji20874

    Jul 30, 2020 · 5y ago

    It seems a lot of government contracting officers are not aware of Alt I to FAR 52.212-4, and even of those that are, some are not aware that para. (i)(ii)(D)(1) and (2) require contracting officer fill-ins.

  5. N

    Nicole1986

    Jul 30, 2020 · 5y ago

    ji20874 said:

    It seems a lot of government contracting officers are not aware of Alt I to FAR 52.212-4, and even of those that are, some are not aware that para. (i)(ii)(D)(1) and (2) require contracting officer fill-ins.

    Thanks again for the help!