Sr. Manager / Contracting Officer
Started by Vonda L. Thomas · Oct 29, 2020 · 3 replies
- VOriginal post
Vonda L. Thomas
Oct 29, 2020 · 5y ago
Presented with an out of scope/Cardinal change to an existing Contract that was procured as a Sole Source. Is the original Sole Source determination sufficient to cover all requirements/activities under the contract? Note the out of scope work will likely be justified as sole source as well.
- N
Neil Roberts
Oct 29, 2020 · 5y ago
FAR 6.001 might provide an answer for you.
- N
Neil Roberts
Oct 29, 2020 · 5y ago
Then, FAR 6.302-1
- j
joel hoffman
Oct 30, 2020 · 5y ago
If this is a Part 19 sole source contract, then it might be added using an out of scope sole source, supplemental agreement for administrative purposes.
6.302-5 Authorized or Required by Statute