    Presented with an out of scope/Cardinal change to an existing Contract that was procured as a Sole Source.  Is the original Sole Source determination sufficient to cover all requirements/activities under the contract?  Note the out of scope work will likely be justified as sole source as well.

  2. N

    Neil Roberts

    Oct 29, 2020 · 5y ago

    FAR 6.001 might provide an answer for you.

  3. N

    Neil Roberts

    Oct 29, 2020 · 5y ago

    Then, FAR 6.302-1

  4. j

    joel hoffman

    Oct 30, 2020 · 5y ago

    If this is a Part 19 sole source contract, then it might be added using an out of scope sole source, supplemental agreement for administrative purposes. 

    6.302-5 Authorized or Required by Statute