T&M Contracts question about tracking
Started by JLo · Dec 2, 2020 · 1 replies
- JOriginal post
JLo
Dec 2, 2020 · 5y ago
For a time & materials contract... do both labor and materials need to be tracked by task order or just by contract?
- h
here_2_help
Dec 5, 2020 · 5y ago
If you have a T&M Task Order, then you need to track all costs associated with that Task Order. However, because it's a T&M type, for purposes of complying with the requirements of 52.232-7, you need to track labor hours at the hourly billing rates while tracking material costs at actual cost. (You'll also need the labor hours at the hourly billing rate info for Schedule K of your proposal to establish final billing rates.)