Use of CPFF option line items
Started by Rachel_CO · Jun 11, 2021 · 3 replies
- ROriginal post
Rachel_CO
Jun 11, 2021 · 4y ago
In what circumstances would a CO use a CPFF task order with CPFF option line items instead of incrementally funding a CPFF task order for a two-year systems engineering requirement when funding is allotted for only one year at a time? I am unfamiliar with the use of cost-type options and what advantage they offer.
- V
Vern Edwards
Jun 12, 2021 · 4y ago
Is the work for a capital project or is it severable support?
- R
Rachel_CO
Dec 2, 2021 · 4y ago
Let's assume for the purpose of this question that the requirement is for severable services.
- j
ji20874
Dec 2, 2021 · 4y ago
Severable services? My first thought would be to use an option for the second year.