Selling / Bid and Proposal Costs Treatment under Letter Contract
Started by Guest108830 · Mar 4, 2022 · 32 replies
- GOriginal post
Guest108830
Mar 4, 2022 · 4y ago
FAR 31.205-18 Independent research and development and bid and proposal costs defines B&P as:
Bid and proposal (B&P) costs means the costs incurred in preparing, submitting, and supporting bids and proposals (whether or not solicited) on potential Government or non-Government contracts. The term does not include the costs of effort sponsored by a grant or cooperative agreement, or required in the performance of a contract .
Small Business with a Small Business Set-Aside award. CAS does not apply to small businesses. No certified cost or pricing applies. Compensation is T&M and within DoD. The effort is for General Services (not construction, not professional services). Contract term is base 5 years with 5 one year option periods, total 10 years.
A Letter Contract (per FAR 52.215-25 Contract Definitization) has been entered into while the broader contract is being definitized / negotiated (there are some insurance anomalies associated with aircraft services).
Question - the costs (time / hours) associated with contract negotiations on the broader contract - should these hours be charged to as B&P or charged as G&A / Overhead?
Reason asking, B&P excludes costs (time / hours) associated with "performance of a contract." Does a Letter Contract constitute "performance of a contract" and thus because limited performance is taking place under the Letter Contract, therefore, any costs in furtherance of the Letter Contract, which would include negotiations of the broader contract, should be considered other than B&P?
According to DoD, contract negotiations should be considered B&P https://www.acq.osd.mil/dpap/policy/policyvault/usa002866-11-dpap.pdf
- j
ji20874
Mar 4, 2022 · 4y ago
Guest,
How do you charge costs associated with negotiations on contract modifications?
In other words, is your situation (definitizing a letter contract) analogous to a negotiation for a contract modification, or is your situation analogous to a negotiation for a new contract? Answering this question might solve your problem.
- V
Vern Edwards
Mar 4, 2022 · 4y ago
Guest108830 said:
Question - the costs (time / hours) associated with contract negotiations on the broader contract - should these hours be charged to as B&P or charged as G&A / Overhead?
Reason asking, B&P excludes costs (time / hours) associated with "performance of a contract." Does a Letter Contract constitute "performance of a contract" and thus because limited performance is taking place under the Letter Contract, therefore, any costs in furtherance of the Letter Contract, which would include negotiations of the broader contract, should be considered other than B&P?
@Guest108830If you are asking whether the cost of preparing the contract definitization proposal required by 52.215-25(a) is "bid and proposal cost" as addressed in FAR 31.205-18, then the answer is no. Bid and proposal costs as addressed in FAR 31.205-18 are costs associated with "potential contracts." A letter contract is an actual contract.
See the DCAA Guidebook, Ch. 33, which states, in part:
Quote
Contractually required proposal efforts (e.g., a contract requirement to submit a proposal for a follow-on contract) are generally direct contract costs. However, the CASB interpretation of CAS 402, under certain circumstances, permits contractors to accumulate and allocate these contractually required proposal costs to final cost objectives as an indirect cost. The interpretation explains that contractors may treat proposal preparation costs as direct or indirect depending on the circumstances under which the costs are incurred. Contractors may treat proposal preparation costs arising from a specific contract requirement as direct costs, while ordinary B&P effort (i.e., effort that is not required by a contract) is indirect. 48 CFR 9904.402.61, Interpretation, notes that contractors may elect to charge all proposal costs (including B&P costs and those required by contract) indirect, provided that the practice is applied consistently and the practice results in an equitable distribution of the costs to final cost objectives.
- G
Guest108830
Mar 4, 2022 · 4y ago
Perhaps I'm reading 31.205-18 wrong when it says "required in the performance of a contract." When I say performance, I'm saying performing a portion of the PWS. What I believe is being mentioned here, however, is where a proposal is expressly "required" to be submitted once under contract for various things.
When I look at it this way, it makes more sense. It's not the performance of work that's being referred to, but rather, whether the contract signed has a express clause requiring a proposal to be submitted for some attribute.
- V
Vern Edwards
Mar 4, 2022 · 4y ago
Guest108830 said:
When I say performance, I'm saying performing a portion of the PWS.
Well, okay. But why on earth would you say such a thing?
Under our laws a contract is "a promise or a set of promises...." Restatement, Second, Contracts § 1. Thus, performance of a contract entails doing all the work required to fulfill all of the promises included in the contract, not just the promises in the work statement.
- h
here_2_help
Mar 4, 2022 · 4y ago
Guest108830 said:
Perhaps I'm reading 31.205-18 wrong when it says "required in the performance of a contract." When I say performance, I'm saying performing a portion of the PWS. What I believe is being mentioned here, however, is where a proposal is expressly "required" to be submitted once under contract for various things.
When I look at it this way, it makes more sense. It's not the performance of work that's being referred to, but rather, whether the contract signed has a express clause requiring a proposal to be submitted for some attribute.
If the proposal is required by contract terms, then the contractor may elect (it is not required to) charge proposal preparation costs as direct contract costs. (See CAS 401, Interpretation No. 1.) However, the contractor's choice must be applied consistently to all contracts in similar circumstances.
Note that directly charged proposal preparation expenses are not B&P costs, because they don't meet the definition of B&P found in the cost principle. They are just direct contract costs.
When I explain this to folks, I tell them that it's easy to distinguish required proposals from proposals that are not required. Is the proposal a contract deliverable? Can the contractor be found to be in breach for failing to submit it? Or is the submission discretionary? Answers to those questions generally tell folks what's required, and what's not required.
- V
Vern Edwards
Mar 4, 2022 · 4y ago
here_2_help said:
Note that directly charged proposal preparation expenses are not B&P costs, because they don't meet the definition of B&P found in the cost principle. They are just direct contract costs.
@here_2_helpI don't think indirectly charged contractually-required proposal costs are B&P either. They are just contractually-required proposal costs that are allocated to an indirect cost pool. Charging such costs indirectly does not turn them into "bid and proposal costs" as defined by FAR.
Am I wrong about that?
- h
here_2_help
Mar 4, 2022 · 4y ago
Vern Edwards said:
@here_2_helpI don't think indirectly charged contractually-required proposal costs are B&P either. They are just contractually-required proposal costs that are allocated to an indirect cost pool. Charging such costs indirectly does not turn them into "bid and proposal costs" as defined by FAR.
Am I wrong about that?
No, you're not wrong, though in practice nobody really ever makes that distinction. It's simply a choice between direct contract costs and B&P. See, for example, the first sentence of Shay Assad's 10 Nov 2011 Memo "Direct and Indirect Charging of Contractor Proposal Preparation and Negotiation Support Costs".
Quote
Proposal preparation and negotiation support costs not funded by a grant or required by a contract are by definition to be indirectly charged to contracts through the Bid and Proposal (B&P) indirect cost pool.
Again, you're not wrong, but it's CAS stuff, so nobody pays much attention to the nuances.
- V
Vern Edwards
Mar 4, 2022 · 4y ago
Thanks.
As you know, I used to negotiate IR&D and B&P cost ceilings for DOD and NASA when ceilings were required. When they were required no one would have wanted to include direct proposal costs in a B&P cost pool. The ceilings were eliminated in 1996. Maybe sloppy use of terminology was the result of the elimination of the ceilings.
- j
joel hoffman
Mar 4, 2022 · 4y ago
here_2_help said:
See, for example, the first sentence of Shay Assad's 10 Nov 2011 Memo "Direct and Indirect Charging of Contractor Proposal Preparation and Negotiation Support Costs".
here_2_help said:
Proposal preparation and negotiation support costs not funded by a grant or required by a contract are by definition to be indirectly charged to contracts through the Bid and Proposal (B&P) indirect cost pool.
Isn’t Assad saying “Proposal preparation and negotiation support costs…or [not] required by a contract are by definition to be indirectly charged to contracts through the Bid and Proposal (B&P) indirect cost pool.
- h
here_2_help
Mar 4, 2022 · 4y ago
joel hoffman said:
Isn’t Assad saying “Proposal preparation and negotiation support costs…or [not] required by a contract are by definition to be indirectly charged to contracts through the Bid and Proposal (B&P) indirect cost pool.
Yes. I was replying to Vern's implied point that a contractor who elects not to charge proposal preparation costs as direct contract costs might technically not be permitted to recover such costs as B&P costs, since they are "required" by a contract even if not directly charged to that contract. CAS might require such costs to be excluded from the B&P pool and allocated separately to the (in this case, singular) benefiting contract or other final cost objective. My point to Vern was that he was technically correct; however, in practice, nobody worries about that nuance. I used Mr. Assad's memo as an example of nuance ignored.
- h
here_2_help
Mar 4, 2022 · 4y ago
Vern Edwards said:
Thanks.
As you know, I used to negotiate IR&D and B&P cost ceilings for DOD and NASA when ceilings were required. When they were required no one would have wanted to include direct proposal costs in a B&P cost pool. The ceilings were eliminated in 1996. Maybe sloppy use of terminology was the result of the elimination of the ceilings.
Yeah, I think it's basically a general ignorance of deep CAS stuff and related accounting issues. The more the KO function mimics the legal profession, the less actual business acumen seems to matter. That's a purely personal opinion, of course. I'm sure there is a myriad of exceptions to my generalization.
- j
ji20874
Mar 4, 2022 · 4y ago
here_2_help said:
The more the KO function mimics the legal profession, the less actual business acumen seems to matter.
That is a profound observation.
- V
Vern Edwards
Mar 4, 2022 · 4y ago
here_2_help said:
The more the KO function mimics the legal profession, the less actual business acumen seems to matter.
ji20874 said:
That is a profound observation.
I don't think it's profound.
If anyone thinks KOs function like lawyers, they don't know much about the legal profession. If more COs and policy people could think like lawyers there might be considerably less stupidity and litigation in government contracting. And there might be less vague regulation that people think is okay. There might be more creativity. Lawyers have been some of the most creative people I know.
The legal profession exists because there's not as much business acumen in the world as one might think or hope. Lawyers get into the game because business people can't solve their problems themselves and seek court assistance or resolution.
And by the way, we have cost accounting standards because an admiral—an engineer, not a lawyer—pushed Congress to impose them.
- j
ji20874
Mar 4, 2022 · 4y ago
Vern Edwards said:
Lawyers have been some of the most creative people I know.
Somehow, I'm not sure that this thought reflects the lived reality of many players in the federal acquisition process, but I wish it were my lived experience.
- d
dsmith101abn
Mar 4, 2022 · 4y ago
ji20874 said:
Somehow, I'm not sure that this thought reflects the lived reality of many players in the federal acquisition process, but I wish it were my lived experience.
If i don't copy and paste to a certain degree what's been done historically i can't get Sh** thru my current lawyer, tho that has not always been the case.
My favorite comment "B-xxxxxx is included in the template so it must be important". No explanation why.
- V
Vern Edwards
Mar 4, 2022 · 4y ago
ji20874 said:
Somehow, I'm not sure that this thought reflects the lived reality of many players in the federal acquisition process, but I wish it were my lived experience.
If your experience has been with government lawyers or private sector lawyers in opposition, then I understand why lawyer creativity has not been your experience.
In government procurement the role of lawyers is usually to "review" CO files for "legal sufficiency" or to contest CO decisions. Most CO's don't ask their lawyer to come to a meeting to generate ideas, but "to keep us out of trouble," i.e., to provide oversight. If that's the way you define a person's job, that's how the person will act.
I once had a government lawyer tell me that his job was not to help me, but to protect our commander from my mistakes, and that in order to do that he couldn't participate in the planning, because his job was to review our plans with an objective eye. But in the private sector lawyers are hired principally to solve problems, provide advice, and provide representation.
As a businessman, I go to my lawyer for advice about the best way to handle a complex matter or to proceed with an undertaking. I can't tell you how many times my lawyer has saved me needless work or has expedited a business process.
So I think here_2_help's comment was too broadly stated. Thinking like a lawyer can be a very, very good thing for a CO if you think like a good lawyer. I have found that legal thinking processes, legal reading, and acquaintance with top notch lawyers have made me a much better acquisition practitioner in every way. But most contract specialists start out working with lawyers whose job it is to check their work. Perhaps that's necessary because COs don't mimic lawyers.
BTW, although I am not a lawyer, I am a member of the ABA, because I like being associated in some small way with great analysts and thinkers.
- h
here_2_help
Mar 5, 2022 · 4y ago
Vern Edwards said:
So I think here_2_help's comment was too broadly stated. Thinking like a lawyer can be a very, very good thing for a CO if you think like a good lawyer. I have found that legal thinking processes, legal reading, and acquaintance with top notch lawyers have made me a much better acquisition practitioner in every way. But most contract specialists start out working with lawyers whose job it is to check their work. Perhaps that's necessary because COs don't mimic lawyers.
BTW, although I am not a lawyer, I am a member of the ABA, because I like being associated in some small way with great analysts and thinkers.
Vern, I don't know how my comment morphed in your mind from "mimic[king] the legal profession" to "thinking like a lawyer." I don't think those two phrases are equivalent. In my personal experience, the vast majority of lawyers do not focus on cost or accounting issues. The comparatively few that do, and do it well, become legends in their fields. Mel Rische and Karen Manos and Tom Lemmer spring immediately to mind - though of course there are others.
Further, in my personal experience, too many attorneys are risk averse, seeking to eliminate risk rather than to manage it. Again - not all attorneys. But many.
Anyway, I, too, am an Associate Member of the ABA, Section of Public Contract Law. I have been for two decades. In that capacity, I've attended meetings and presented a paper at a Quarterly meeting and contributed to a Section publication. Just so that we're clear that my statement was not an indictment of the legal profession.
- V
Vern Edwards
Mar 5, 2022 · 4y ago
here_2_help said:
Just so that we're clear that my statement was not an indictment of the legal profession.
Well, I'm glad you said that, even though it leaves me confused about what you meant, since the thrust of your comment seemed to be that mimicking "the legal profession" is not a good thing for COs to do.
What is it about "the legal profession" that makes it bad to mimic?
My question is strictly rhetorical. I don't ask for an answer. I think you just tossed that comment off without thinking it through, which is something that we all do from time to time. It certainly wasn't "profound."
- j
joel hoffman
Mar 5, 2022 · 4y ago
Vern Edwards said:
And by the way, we have cost accounting standards because an admiral—an engineer, not a lawyer—pushed Congress to impose them.
Admiral Hyman G. Rickover, father of the Nuclear Navy.
https://www.gao.gov/assets/094464.pdf - R
Retreadfed
Mar 5, 2022 · 4y ago
On 3/4/2022 at 11:20 AM, here_2_help said:
(See CAS 401, Interpretation No. 1.)
The contractor in question is a small business, so CAS does not apply.
- h
here_2_help
Mar 6, 2022 · 4y ago
Retreadfed said:
The contractor in question is a small business, so CAS does not apply.
Yes, true. Am I understanding your position as being that, since CAS is not applicable to the contractor, then the permissive cost accounting practices described by CAS are not available to the contractor?
- V
Vern Edwards
Mar 6, 2022 · 4y ago
here_2_help said:
Am I understanding your position as being that, since CAS is not applicable to the contractor, then the permissive cost accounting practices described by CAS are not available to the contractor?
There is no reason to think that. See FAR 31.202, Direct costs:
Quote
(a) No final cost objective shall have allocated to it as a direct cost any cost, if other costs incurred for the same purpose in like circumstances have been included in any indirect cost pool to be allocated to that or any other final cost objective . Direct costs of the contract shall be charged directly to the contract . All costs specifically identified with other final cost objectives of the contractor are direct costs of those cost objectives and are not to be charged to the contract directly or indirectly.
(b) For reasons of practicality, the contractor may treat any direct cost of a minor dollar amount as an indirect cost if the accounting treatment-
(1) Is consistently applied to all final cost objectives; and
(2) Produces substantially the same results as treating the cost as a direct cost .
This really is simple. There are two kinds of proposal costs. There are (1) the costs of proposals for new work and (2) the costs of proposals required by contract. Both types of proposal costs are allowable, but (1) is allocable only as indirect costs while (2) may be allocated as either direct or indirect under appropriate circumstances, as described in FAR 31.202.
Until 1996 there were ceilings on the costs of proposals for new work that the government would compensate, which are called B&P costs. B&P is defined such that contractually required proposal costs were not included. That's because (a) contractually required proposal costs are direct costs and (b) no one wanted the ceilings to apply to costs that had to be incurred to comply with contracts. Thus, it was important to recognize the distinction between the two kinds of costs.
When the ceilings were eliminated, the FAR councils did not change the definition of B&P. Assad's memo indicated that if the costs of proposals required by contract were to be allocated as indirects, they could both be included in a B&P pool. For many contractors, combining the two types of proposal costs was administratively easier. But Assad's memo was careless, and confusing to those unfamiliar with the cost principles.
True B&P costs, as still defined by FAR 31.205-18, must be allocated indirectly. That is usually done by maintaining a B&P cost pool and including it in the G&A cost pool.
Proposal costs required by contract are direct costs, but for the sake of convenience they may be allocated either directly or indirectly according to a contractor's consistent cost accounting practice. Assad said that could be done by including them in the B&P cost pool, which is usually part of the G&A cost pool, or by including them in their own pool and then including that pool in the G&A pool. But including the costs of proposals required by contract in the B&P pool does not make them B&P costs as defined in FAR.
Also, I have been unable to confirm that Assad's 2011 memo is still active guidance.
- h
here_2_help
Mar 6, 2022 · 4y ago
Vern Edwards said:
This really is simple.
Yes.
And to the OP's original question
Quote
Question - the costs (time / hours) associated with contract negotiations on the broader contract - should these hours be charged to as B&P or charged as G&A / Overhead?
The answer is that the contractor's own policies/procedures should define when costs associated with, but not directly a part of, proposal preparation and submission are charged to the B&P project and when they are not to be so treated. Shay Assad's directive, link provided earlier in the thread, provides that DoD will accept contract negotiation costs as being B&P costs, so long as the contractor treats them that way consistently.
- V
Vern Edwards
Mar 6, 2022 · 4y ago
here_2_help said:
Shay Assad's directive, link provided earlier in the thread, provides that DoD will accept contract negotiation costs as being B&P costs, so long as the contractor treats them that way consistently.
Emphasis added.
@here_2_helpI consider you an expert in these matters and so am hesitant to disagree with you. But I'm not certain about what you are meant by the quoted sentence. When you say "contract negotiation costs" do you mean the cost of proposals and negotiations required by contract? If so, then I must disagree with you. I wonder if I have misinterpreted you.
48 CFR 31.205-18 defines "bid and proposal costs" as follows:
Quote
Bid and proposal (B&P) costs means the costs incurred in preparing, submitting, and supporting bids and proposals (whether or not solicited) on potential Government or non-Government contracts. The term does not include the costs of effort sponsored by a grant or cooperative agreement, or required in the performance of a contract.
48 CFR 9904.420-30(a)(2) (CAS 420) defines "bid and proposal cost" as follows:
Quote
Bid and proposal (B&P) cost means the cost incurred in preparing, submitting, or supporting any bid or proposal which effort is neither sponsored by a grant, nor required in the performance of a contract.
Those regulations appear in the current Code of Federal Regulations (CFR) and have the force and effect of law.
I am holding Shay Assad's November 10, 2011 memorandum, the one you cited last Friday at 9:00 a.m. and this morning. It is entitled, "Memorandum." The word "directive" does not appear therein, neither does the word "shall." The word that I see is "guidance." It contains six paragraphs. Nowhere therein do I see any sentence that says DOD will accept the costs of proposals and negotiations required by a contract "as being B&P costs."
My point is that while the costs of preparing and negotiating a proposal that is required by contract may be charged as indirect costs under certain circumstances, as provided by FAR 31.202, charging them as such does not make them "bid and proposal costs" as defined by FAR and CAS.
That is my only point. It's a narrow point, but I think it is an important one. COs should understand the different purposes and roles of the two kinds of proposal costs.
Do you take issue with my point? Do you think that Assad said that proposal and negotiation costs required by contract can be treated "as being B&P costs" as defined by FAR and CAS? If so, would you point out the paragraph and sentence in which Assad said that? If I missed it and he did say it, do you think it was sound guidance.
I apologize if I'm just being a blockhead in the way I read and am reacting to your last post.
- j
joel hoffman
Mar 6, 2022 · 4y ago
On 3/4/2022 at 11:14 AM, joel hoffman said:
Isn’t Assad saying “Proposal preparation and negotiation support costs…or [not] required by a contract are by definition to be indirectly charged to contracts through the Bid and Proposal (B&P) indirect cost pool.
On 3/4/2022 at 11:49 AM, here_2_help said:
Yes…
- V
Vern Edwards
Mar 6, 2022 · 4y ago
The question is whether the cost of proposals and negotiations required by contract that are allocated indirectly are to be treated "as being B&P costs."
The reason why that is important is that there are distinct management issues and concerns that pertain specifically to each kind of proposal costs. See, for instance, DFARS 242.771. See also 10 USC § 3763 (formerly § 2372a).
While contractually required costs may be allocated indirectly under appropriate circumstances, such costs do not become B&P when so allocated and should not be treated "as being B&P."
- j
joel hoffman
Mar 6, 2022 · 4y ago
Vern Edwards said:
The question is whether the cost of proposals and negotiations required by contract that are allocated indirectly are to be treated "as being B&P costs."
The reason why that is important is that there are distinct management issues and concerns that pertain specifically to each kind of proposal costs. See, for instance, DFARS 242.771. See also 10 USC § 3763 (formerly § 2372a).
While contractually required costs may be allocated indirectly under appropriate circumstances, such costs do not become B&P when so allocated and should not be treated "as being B&P."
Correct. That’s what Assad said and H2H agreed with me when I asked isn’t that what Assad was saying.
- V
Vern Edwards
Mar 6, 2022 · 4y ago
@joel hoffmanWhy are you inserting yourself at this point?
This morning, H2H said:
here_2_help said:
Shay Assad's directive, link provided earlier in the thread, provides that DoD will accept contract negotiation costs as being B&P costs, so long as the contractor treats them that way consistently.
My emphasis. I've asked him for clarification. He's a big boy. He doesn't need your help. Why don't you just wait for him to respond to my query?
Stand by, for Pete's sake.
- h
here_2_help
Mar 7, 2022 · 4y ago
Vern Edwards said:
Emphasis added.
@here_2_helpI consider you an expert in these matters and so am hesitant to disagree with you. But I'm not certain about what you are meant by the quoted sentence. When you say "contract negotiation costs" do you mean the cost of proposals and negotiations required by contract? If so, then I must disagree with you. I wonder if I have misinterpreted you.
48 CFR 31.205-18 defines "bid and proposal costs" as follows:
48 CFR 9904.420-30(a)(2) (CAS 420) defines "bid and proposal cost" as follows:
Those regulations appear in the current Code of Federal Regulations (CFR) and have the force and effect of law.
I am holding Shay Assad's November 10, 2011 memorandum, the one you cited last Friday at 9:00 a.m. and this morning. It is entitled, "Memorandum." The word "directive" does not appear therein, neither does the word "shall." The word that I see is "guidance." It contains six paragraphs. Nowhere therein do I see any sentence that says DOD will accept the costs of proposals and negotiations required by a contract "as being B&P costs."
My point is that while the costs of preparing and negotiating a proposal that is required by contract may be charged as indirect costs under certain circumstances, as provided by FAR 31.202, charging them as such does not make them "bid and proposal costs" as defined by FAR and CAS.
That is my only point. It's a narrow point, but I think it is an important one. COs should understand the different purposes and roles of the two kinds of proposal costs.
Do you take issue with my point? Do you think that Assad said that proposal and negotiation costs required by contract can be treated "as being B&P costs" as defined by FAR and CAS? If so, would you point out the paragraph and sentence in which Assad said that? If I missed it and he did say it, do you think it was sound guidance.
I apologize if I'm just being a blockhead in the way I read and am reacting to your last post.
Okay. First, I used the incorrect term. I said "directive" instead of "memorandum." I was too loose with my language.
Second, I have already agreed with you regarding the distinction between directly charged proposal preparation costs and "B&P" costs. I have already agreed that there is a third category - proposal preparation costs that are required by contract but not directly charged to a contract because the contractor elects not to do so. I have pointed out that, in practice, that third category does not exist. I used the Assad MEMORANDUM to show that not even DoD makes that distinction, even though you are absolutely correct to do so.
My final point was that negotiation costs may or may not be part of B&P expenses (or, for completeness. directly charged proposal preparation expenses). A contractor's policies and procedures will control the treatment (which must be consistently applied). Some contractors will treat negotiation costs as being part of proposal preparation expenses; others will not. I pointed once again to the Assad MEMORANDUM as support for the notion that DoD will accept such support expenses as being part of B&P (or, directly charged proposal preparation expenses).
To be very clear: such costs as negotiation need not be charged direct, even if "required" because it is the contractor's consistent practice that will control. If the contractor does not charge negotiation expenses as part of B&P costs, then it will not charge them as part of directly charged proposal preparation expenses. Conversely, if it does then it will.
That's it. Those are all my points. Everything else is loose language for which I apologize if there was any confusion caused.
- V
Vern Edwards
Mar 7, 2022 · 4y ago
Thanks, H2H, but I cannot find anything in the Assad memo that supports the following assertion:
here_2_help said:
I pointed once again to the Assad MEMORANDUM as support for the notion that DoD will accept such support expenses as being part of B&P (or, directly charged proposal preparation expenses).
My emphasis.
That memo consists of exactly 20 sentences. I have read each and every one. And, unless I am losing it, or have been blinded by prejudice, not one of those 20 sentences supports that assertion. (Could we be talking about different memos?)
Maybe I just don't understand what you mean by "such support expenses." It's either that or I disagree with what you seem to be saying.
But I'll let it go. I know what I think, and that's enough for me. Costs incurred for the preparation of proposals that are required by contract are not, and by official definition cannot be, considered or treated as bid and proposal (B&P) costs. There are requirements that apply to B&P that do not apply to the other costs, no matter how they are allocated. Whether they are charged as direct or indirect depends on circumstances and the contractor's established accounting practices. See FAR 31.202. If they are charged as indirect, they are not B&P costs just for that reason.
Best,
Vern
P.S. I remember disputes such as this among the senior contract specialists when I was a newbie. They were often just matters of confusion over communications transmitted and received.
- h
here_2_help
Mar 7, 2022 · 4y ago
Vern Edwards said:
Thanks, H2H, but I cannot find anything in the Assad memo that supports the following assertion:
My emphasis.
That memo consists of exactly 20 sentences. I have read each and every one. And, unless I am losing it, or have been blinded by prejudice, not one of those 20 sentences supports that assertion. (Could we be talking about different memos?)
Maybe I just don't understand what you mean by "such support expenses." It's either that or I disagree with what you seem to be saying.
But I'll let it go. I know what I think, and that's enough for me. Costs incurred for the preparation of proposals that are required by contract are not, and by official definition cannot be, considered or treated as bid and proposal (B&P) costs. There are requirements that apply to B&P that do not apply to the other costs, no matter how they are allocated. Whether they are charged as direct or indirect depends on circumstances and the contractor's established accounting practices. See FAR 31.202. If they are charged as indirect, they are not B&P costs just for that reason.
Best,
Vern
P.S. I remember disputes such as this among the senior contract specialists when I was a newbie. They were often just matters of confusion over communications transmitted and received.
Vern, please read the first sentence of the Assad Memo one more time. The very first sentence. The one I quoted earlier in the thread.
To your point, I don't think we really have a disagreement. We are, in the vernacular, "talking past each other."
Best to you!
- V
Vern Edwards
Mar 7, 2022 · 4y ago
here_2_help said:
Vern, please read the first sentence of the Assad Memo one more time. The very first sentence. The one I quoted earlier in the thread.
The first sentence in the Assad memo says:
Quote
Proposal preparation and negotiation support costs not funded by a grant or required by a contract are by definition to be indirectly charged to contracts through the Bid and Proposal (B&P) indirect cost pool.
The definition of B&P in FAR 31.205-18:
Quote
Bid and proposal (B&P) costs means the costs incurred in preparing, submitting, and supporting bids and proposals (whether or not solicited) on potential Government or non-Government contracts. The term does not include the costs of effort sponsored by a grant or cooperative agreement, or required in the performance of a contract.
So Assad's first sentence makes sense to me.
But we have been talking about proposal preparation and negotiation costs that are required by contract. Those are ordinarily allocated as direct costs of the contract which required the proposal and negotiation support. However, FAR 31.202 says:
Quote
(b) For reasons of practicality, the contractor may treat any direct cost of a minor dollar amount as an indirect cost if the accounting treatment-
(1) Is consistently applied to all final cost objectives; and
(2) Produces substantially the same results as treating the cost as a direct cost .
Much earlier in this thread you agreed with me that charging proposal and negotiation costs required by contract does not turn them into B&P costs.
On 3/4/2022 at 8:27 AM, Vern Edwards said:
@here_2_helpI don't think indirectly charged contractually-required proposal costs are B&P either. They are just contractually-required proposal costs that are allocated to an indirect cost pool. Charging such costs indirectly does not turn them into "bid and proposal costs" as defined by FAR.
Am I wrong about that?
On 3/4/2022 at 9:00 AM, here_2_help said:
No, you're not wrong, though in practice nobody really ever makes that distinction. It's simply a choice between direct contract costs and B&P.
(I should have challenged you on that business about "in practice nobody really ever makes that distinction," because it is demonstrably false. But I let it go, because I know that people in our business can be careless about terminology.)
But then you said:
Vern Edwards said:
Shay Assad's directive, link provided earlier in the thread, provides that DoD will accept contract negotiation costs as being B&P costs, so long as the contractor treats them that way consistently.
The phrase "as being B&P costs" in that comment threw me for two reasons. First, because it seems to erase the important distinction between (1) proposal and negotiation costs that ARE required by contract and (2) B&P costs, which are such costs that are NOT required by contract. Second, it threw me because Assad's memo says no such thing! Not even close!
Yesterday, you said:
here_2_help said:
My final point was that negotiation costs may or may not be part of B&P expenses (or, for completeness. directly charged proposal preparation expenses).
My emphasis. Again, your words seem to erase the distinction between proposal and negotiation costs required by contract and B&P costs by saying that costs required by contract may or may not be "part of B&P expenses"!
I think we agree, but you have not been precise in the way you have expressed yourself in some of your posts in this thread. You know me. Imprecision can hurt businesses. That's why they have to resort to lawyers.
Words and sentences matter in the contracting world. That's why I try to "mimic" lawyers, because the best of them know that, and they have taught me. Unschooled and inexperienced people are easily confused and misled by careless language about complicated, even esoteric, business matters. We must not mislead unschooled and inexperienced readers who come to this site "to learn," as they like to say.
I shall now say what I think you mean:
Proposal and negotiation costs that are required by a contract are to be allocated as direct costs of that contract, but may in some cases—for sake of "practicality,"—be allocated as indirect costs in the same way as B&P costs. However, the two categories of cost remain distinct, even when both are allocated as indirect costs. Thus, requirements that expressly apply to B&P costs, such as 10 USC 3763, DFARS 242.771-1, and many others, do not apply to proposal and negotiation costs that are required by contract, not even when they are allocated as indirect costs.
Does that work for you? If it does, then we can close the book on this topic.
And while we're at it, "selling costs," which are mentioned in the title of this thread, are not the same as B&P costs.
I have the highest respect for you as a professional and a practitioner. Website chat sites are not the best place to discuss legally complex matters.
Best,
Vern