REA - Request for Equitable Adjustment

Started by acq20wl · Mar 10, 2022 · 4 replies

  1. a

    acq20wl

    Mar 10, 2022 · 4y ago

    Original post

    Contract Type: FFP, IDIQ

    Years after the basic contract was awarded, the fees have increased that affected the pre-priced ELINs. The KTR did not notify the Govt of this price increase until a request for equitable adjustment has been submitted to pay for the difference in order to complete a final deliverable of a task order (issued under the basic contract). 

    Will the KTR's failure to notify the Govt on the increased fees impact the award of the REA mod? In addition, if the basic contract is already expired, can this REA mod still be funded? (POP of Task Order has been extended for this pending REA/final deliverable.)

  2. j

    joel hoffman

    Mar 11, 2022 · 4y ago

    acq20wl said:

    Contract Type: FFP, IDIQ

    Years after the basic contract was awarded, the fees have increased that affected the pre-priced ELINs. The KTR did not notify the Govt of this price increase until a request for equitable adjustment has been submitted to pay for the difference in order to complete a final deliverable of a task order (issued under the basic contract). 

    Will the KTR's failure to notify the Govt on the increased fees impact the award of the REA mod? In addition, if the basic contract is already expired, can this REA mod still be funded? (POP of Task Order has been extended for this pending REA/final deliverable.)

    The first question is this: What provision in the FFP ID/IQ provides for a price adjustment due to a “fee increase” (and what is the “fee”)? Can you quote the contract language? Thanks.

  3. j

    joel hoffman

    Mar 11, 2022 · 4y ago

    acq20wl said:

    if the basic contract is already expired, can this REA mod still be funded? (POP of Task Order has been extended for this pending REA/final deliverable.)

    If a task order is still open for fulfillment, the basic contract is not “expired”. Only the ordering period has “expired”. All terms and conditions of the basic contract that apply to the task order should still be effective.

  4. V

    Vern Edwards

    Mar 11, 2022 · 4y ago

    On 3/10/2022 at 12:24 PM, acq20wl said:

    the fees have increased that affected the pre-priced ELINs

    @acq20wlWhat do you mean by "fees"? What "fees"? You said your contract is firm-fixed-price. "Fee" is not ordinarily a term we use with respect to FFP contracts. What "fees" have increased?

  5. j

    joel hoffman

    Mar 12, 2022 · 4y ago

    From the WIFCON Forum terms of use:

    ”17.  Original posters must not disappear after they post a question.  Disappearing makes it impossible to provide clarifications of the original post so that others may respond intelligently.  It is normal for the original poster to be asked for clarification.”

    acq20wl, I know that you are new but would you please clarify your original post ?  Thanks.

Sign in or sign up to post a reply.