What is the authority used for a modification after award, which fixes an admin error unrelated to paying, appropriation office, etc.

Started by K. Williams · Mar 25, 2022 · 1 replies

  1. K

    K. Williams

    Mar 25, 2022 · 4y ago

    Original post

    What is the authority used for a modification after award, which fixes an admin error for a change to a construction POP.  This error was realized after award and based on the Govt. answering a PPI for additional time needed by the contractor.  The TO was awarded with the original time not the agreed to time.

  2. V

    Vern Edwards

    Mar 25, 2022 · 4y ago

    Standard Form 30, block 13, says to use 43.103(b) as authority for an administrative change.

    But if you issued a task order that stated an erroneous period of performance you should prepare a supplemental (bilateral) agreement rather than an administrative change, state in the mod that the change was made to correct an error, and get the contractor to sign it.