Construction MATOC Task Orders

Started by dkubis · Nov 9, 2010 · 4 replies

  1. d

    dkubis

    Nov 9, 2010 · 15y ago

    Original post

    To issue a TO off of a Construction MATOC, is it really necessary to issue a 1442? It just seems like that's extra work and defeats the purpose. To me if it's already on an IDIQ it would be enough to just issue a Task Order, assuming all the terms and conditions are met. Am I wrong or what?

  2. C

    Cajuncharlie

    Nov 23, 2010 · 15y ago

    Expect every agency has its own practice. I am accustomed to seeing DD Form 1155 task or delivery orders.

  3. G

    Guest Vern Edwards

    Nov 23, 2010 · 15y ago

    See FAR 52.216-1 and 52.236-1(d). DOD uses DD 1155 instead of OF 347.

  4. F

    FSCO

    Nov 23, 2010 · 15y ago

    Vern, I believe you mean 53.216-1 and 53.236-1(d). I also suggest reviewing FAR Part 36.7 in conjunction with 36.101.

    If you follow the interpretation that a task order is a "contract" for policy purposes (i.e. for interpreting and applying the regulations), then you should be using the SF 1442 if the orders are above the SAT (you can use OF-347 if below the SAT). If you believe that a task order is not a "contract" for policy purposes, then you can use the OF-347.

  5. G

    Guest Vern Edwards

    Nov 23, 2010 · 15y ago

    Yep, I meant 53. Thanks.