Is a J & A needed?

Started by DonDon · Apr 6, 2022 · 3 replies

  1. D

    DonDon

    Apr 6, 2022 · 4y ago

    Original post

    J&A

  2. V

    Vern Edwards

    Apr 7, 2022 · 4y ago

    Adding some more work to a labor-hour contract is a new procurement. Adding more work is not "in scope." If you do it sole source you need a J&A.

  3. J

    Jamaal Valentine

    Apr 7, 2022 · 4y ago

    DonDon said:

    I know the contract can be modified as the additional work is in scope under the original SOW.

    First, what do you mean by this? Why do you say the additional work is in scope under the original SOW?

  4. j

    ji20874

    Apr 7, 2022 · 4y ago

    I agree that adding additional work is not "in scope." But we use terms sloppily sometimes.

    DonDon, Is the government really adding additional work?  Or does the contractor need to do additional work in order to complete the work already contracted for?  These are very different, but sometimes people can't see the difference.