CREATIVE CONTRACT PRICING ARRANGEMENT

Started by neecai · Apr 20, 2009 · 1 replies

  1. n

    neecai

    Apr 20, 2009 · 17y ago

    Original post

    I am wondering if I award a Time and Material base ID/IQ contract, that when I have a specific task order to let, that I could request a quote for the specific SOW, and request a FFP for that order.

  2. f

    formerfed

    Apr 20, 2009 · 17y ago

    I am wondering if I award a Time and Material base ID/IQ contract, that when I have a specific task order to let, that I could request a quote for the specific SOW, and request a FFP for that order.

    Yes, assuming that the ordering provision (and any other pertinent clauses) allows FFP orders. If not, you may have to negotiate a revision to the contract to allow it.