Why Not Clarify?
Started by Vern Edwards · Sep 10, 2022 · 1 replies
- VOriginal post
Vern Edwards
Sep 10, 2022 · 3y ago
See Selex ES, Inc., GAO B-420799, Sep 06, 2022.
https://www.gao.gov/products/b-420799
Can someone explain to me why the agency refused to make a very simple clarification of the RFP? The CO could have fixed the problem in an hour or so by posting a clarification at SAM.gov and avoided the cost and delay of a sustained protest.
I must be missing something. What am I missing?
- f
formerfed
Sep 10, 2022 · 3y ago
Just a guess seeing similar things in the past- a CO dealing with an issue over their head, maybe bullied by a program/technical person, and not seeing a legal view or independent opinion from another person in the contracts office.