Why Not Clarify?

Started by Vern Edwards · Sep 10, 2022 · 1 replies

  1. V

    Vern Edwards

    Sep 10, 2022 · 3y ago

    Original post

    See Selex ES, Inc., GAO B-420799, Sep 06, 2022.

    https://www.gao.gov/products/b-420799

    Can someone explain to me why the agency refused to make a very simple clarification of the RFP? The CO could have fixed the problem in an hour or so by posting a clarification at SAM.gov and avoided the cost and delay of a sustained protest.

    I must be missing something. What am I missing?

  2. f

    formerfed

    Sep 10, 2022 · 3y ago

    Just a guess seeing similar things in the past- a CO dealing with an issue over their head, maybe bullied by a program/technical person, and not seeing a legal view or independent opinion from another person in the contracts office.