Acquirer
@Acquirer
Joined Jan 23, 2014 · 9 posts
Recent posts
- Pay for Success Contracts under FAR? (Different from what we call "Performance Based")
I don't have anywhere near Vern's experience or intellect, but I would do what I can with what I've got. I'd write up a normal, public-funded, FP performance-based contract, with strict quality levels
in Contract Administration · 4y ago
- Novation or Change-of-Name Agreements?
I would do a Novation (changing the name), after the JV and both entities sign off that they transferred all performance assets and responsibilities to the Italian firm and attesting that they release
in Contract Administration · 4y ago
- eCMRA
In the old system, the contractor could add the contract and all the details themselves. If that's no longer the case, I would screenshot the reports page to show the contract is not there and email i
in Contract Administration · 5y ago
- Mechanism to Reduce Hassle by Awarding Best Value As If It Were LPTA
Most Contracting professionals I've worked with in Government contracting, at least those trained through DAU, no longer work in Government contracting and refuse to go back to it. Even if it pays be
in Contract Award Process · 5y ago
- Mechanism to Reduce Hassle by Awarding Best Value As If It Were LPTA
Joel: What happened is that the agency head demands that it be done as "best value where technical is more important than price," or to write that in so it looks that way, but those lower in the food
in Contract Award Process · 5y ago
- Mechanism to Reduce Hassle by Awarding Best Value As If It Were LPTA
Wow, Vern. I truly appreciate your gracing my question with your attention. Your knowledge, deductive reasoning, and advice is unparalleled, as always. I don't really want to do this thing. I'm i
in Contract Award Process · 5y ago
- Mechanism to Reduce Hassle by Awarding Best Value As If It Were LPTA
The requirement is a somewhat complex service with some unique military requirements and systems, but we consider it commercial. LPTA is a big no-no. I am ordered to do a best value tradeoff with pa
in Contract Award Process · 5y ago
- Mechanism to Reduce Hassle by Awarding Best Value As If It Were LPTA
If a C.O. wants to award LPTA, but the agency doesn't allow it (politics!), instead requiring a time-consuming Best Value analysis where past performance is more important than price, does anything st
in Contract Award Process · 5y ago
- FAR Part 19 applicability in Foreign Countries
The FAR Council ruled that FAR 19 does not apply to work performed overseas. When the SBA debated the point, the GAO ruled in favor of the FAR Council. [http://www.gao.gov/assets/660/657944.pdf](http
in Small Business Socioeconomic Programs · 12y ago