There is this clause for acceptance in the contract: **CONSTRUCTIVE ACCEPTANCE** ".......**acceptance of services required herein shall be deemed to have occurred constructively on the 7th calendar
in Contract Administration · 7mo ago
- 252.232-7998 Obligations in Advance of Fiscal Year 2026 Funding (Deviation 2026-O0001) & Invoicing Submissions
Thank you [@formerfed](/u/formerfed) As long as the government does not "accept" the invoices, the clock doesn't start is what I took from that. I appreciate the response. "**Jared Serbu** I’m so gla
in Contract Administration · 7mo ago
- 252.232-7998 Obligations in Advance of Fiscal Year 2026 Funding (Deviation 2026-O0001) & Invoicing Submissions
I did not see any previous posts when searching, so I apologize if this is posted elsewhere. I included the complete text of the clause at the end for ease of reference. My question is: Does this cla
in Contract Administration · 7mo ago
- Budget Authority Issue?
I’ll try the NCMA forums, thanks Vern.
in About the Regulations · 3y ago
- Budget Authority Issue?
Do contractors not have a duty to say something or the right to investigate on matters? As a contractor the CO actions (if inappropriate) can cause consequences that jeopardize our award, obviously no
in About the Regulations · 3y ago
- Budget Authority Issue?
Thank you, Vern! I have seen the Redbook referenced before; I will take the time to see if I can learn from that now that my curiosity has led me in that direction. I also appreciate your opinion th
in About the Regulations · 3y ago
- Budget Authority Issue?
Hi Retreadfed - The funding is ALL at the Task Order level, but all Task Orders are added up and it goes against the ceiling values at the contract level. My comment is that with each funding action/
in About the Regulations · 3y ago
- Budget Authority Issue?
Thank you for the questions, Vern. The best question that I think you asked was if it was all on the same account line - which I know as fund cites - which would be certified through the certifying o
in About the Regulations · 3y ago
- Budget Authority Issue?
Scenario: Competitive Single award CPAF contract, Base +4 Option Periods. Mostly services but does have ceiling lines for ODCs, Travel, Materials, Labor, Award Fee at the contract level for each per
in About the Regulations · 3y ago
- Removed
<removed>
in Contract Administration · 3y ago
- 52.204-14 - Question
Thank you. We decided that the clause would be applicable, but not until we "invoiced" since Progress Payments are a financing tool. To comply, we reported zeros in SAM. I appreciate the responses.
in Contract Administration · 5y ago
- 52.204-14 - Question
Thank you here\_2\_help, it confirms my understanding of the progress payments and how I view the total invoiced amount being zero. Maybe someone else knows more about the service reporting to see if
in Contract Administration · 5y ago
- 52.204-14 - Question
A task order awarded in 2016 has just now hit our Service Contract Reporting list in SAM. However, this is a FPIF task order and we are working on "progress payments" not "invoices" as we are deliver
in Contract Administration · 5y ago
- CDRL vs PWS
I am not sure if this helps with the facts, and to be quite honest I feel I must be missing something major. Would Product Support be something totally different than the Service Agreements - even th
in Contract Administration · 7y ago
- CDRL vs PWS
Hi, It seems we have found ourselves in a situation where a CDRL is calling out an additional requirement that the Government wants but it is not stated in the PWS. Specifically, a longer duration o
in Contract Administration · 7y ago
- Progress Payments by CLIN
Postaward - Unfortunately all CLIN types were funded with 1 ACRN, I have inquired if we could go back and have separate ACRNS for each CLIN but was told by our former ACO it was too much work and cou
in Contract Administration · 8y ago
- Progress Payments by CLIN
I guess I am hoping that if I can have the PCO put clear language in the contract, then that will tell the ACO how to enter it into the system, which should tell DFAS how to pay it. A wish and a pray
in Contract Administration · 8y ago
- Progress Payments by CLIN
ji20874 - Thank you for the language! Thanks to everyone for weighing in, I do appreciate it. I am going to see if the PCO could agree to the language offered by ji20874 and let him know it has also
in Contract Administration · 8y ago
- Progress Payments by CLIN
Thanks for the responses, I am going with the first Q, here\_2\_help asked and I was wondering if anyone could weigh in on the language that I would like to propose to our PCO to add. I do not know i
in Contract Administration · 8y ago
- Progress Payments by CLIN
Hi! I have a situation where it seems DFAS/ACO/PCO/Contractor have a different expectation of how progress payments should work on this program. I am looking for guidance that could help everyone ha