- CO provided a "competitive price range" for an LPTA procurement then awarded outside of range
> > Vern Edwards said: > > > [@EZK81](/u/ezk81)For an illustration of how price realism might work in the competitive placement of an order against a GSA schedule contract, see the GAO's bid protest
in Contract Award Process · 2y ago
- CO provided a "competitive price range" for an LPTA procurement then awarded outside of range
> > Jamaal Valentine said: > > > You would have to explain what you mean by unrealistic. For example, under FAR 15.404-1(d)(1), “Cost realism analysis is the process of independently reviewing and ev
in Contract Award Process · 2y ago
- CO provided a "competitive price range" for an LPTA procurement then awarded outside of range
> > On 3/29/2024 at 3:22 PM, C Culham said: > > > Although GSA has already negotiated **fair** and reasonable _pricing_, _ordering activities_ _may_ seek additional discounts before placing an order
in Contract Award Process · 2y ago
- CO provided a "competitive price range" for an LPTA procurement then awarded outside of range
To provide some additional context in light of the reasonableness/realism point, I looked at the evaluation factors again. Here is the language from the price evaluation factor (emphasis added). It do
in Contract Award Process · 2y ago
- CO provided a "competitive price range" for an LPTA procurement then awarded outside of range
> > Jamaal Valentine said: > > > Remember, price fair and reasonableness is only concerned with a price being too high. That's an extremely helpful citation, thank you. I had mistakenly been conflat
in Contract Award Process · 2y ago
- CO provided a "competitive price range" for an LPTA procurement then awarded outside of range
> > Quote > > > Was the term “competitive price range” defined anywhere in the RFQ? Unless the term signifies a mandatory requirement, I doubt that a protest over award of a lower quote would be succ
in Contract Award Process · 2y ago
- CO provided a "competitive price range" for an LPTA procurement then awarded outside of range
This is from Amendment 5 out of 6. Amendment 6 revised the SOW to remove 1 FTE, issued a new Schedule B, and extended the due date for the BAFO. _"This change is hereby issued to Solicitation No. \[
in Contract Award Process · 2y ago
- CO provided a "competitive price range" for an LPTA procurement then awarded outside of range
Hi everyone - thanks in advance for your help. I have found this forum to be an incredibly valuable resource. I work for a federal contractor, and I am looking for clarification on an LPTA situation I
in Contract Award Process · 2y ago