- 52.242-14 Suspension of Work
While there were changes using the changes clause those cost were settled before the suspension. The main question is subcontractor compensation due to the suspension. I may have misunderstood the fe
in Contract Pricing including CAS & Allowable Costs · 4y ago
- 52.242-14 Suspension of Work
The correct Period of performance is April 2020-April 2021. The suspension was issued in Sept 2020.
in Contract Pricing including CAS & Allowable Costs · 4y ago
- 52.242-14 Suspension of Work
I just inherited a $1M generator installation contract. Period of performance April 2019-April 2020. In Sept 2020 a suspension of work was issued due to government delay for various reasons...change o
in Contract Pricing including CAS & Allowable Costs · 4y ago
- FFP CONSTRUCTION CONTRACT MATERIALS
Joel, I agree as the SOV are really just an estimate. Thanks for all the help.
in Contract Pricing including CAS & Allowable Costs · 4y ago
- FFP CONSTRUCTION CONTRACT MATERIALS
The government did not cause a delay. I believe the contractor is looking for extra$$. I agree that that is between the Prime and Sub. Thanks all for your feedback.
in Contract Pricing including CAS & Allowable Costs · 4y ago
- FFP CONSTRUCTION CONTRACT MATERIALS
Awarded a VA FFP construction contract Jan 2019 - Aug 2021. Contractor submitted the schedule of values and quote for door hardware in May 2019 -$62,000. Jun 2021, the contractor sent an updated quote
in Contract Pricing including CAS & Allowable Costs · 4y ago