- T&M Rate Evaluation During Award
> > joel hoffman said: > > > Mannaf, Is there a defined or open ended scope for the T& M effort? The scope is defined and each CLIN has a ceiling for the effort.
in Contract Pricing including CAS & Allowable Costs · 3y ago
- T&M Rate Evaluation During Award
> > Vern Edwards said: > > > [@Mannaf](/u/mannaf)A T&M contract is like a cost-reimbursement (CR) contract in that the contractor promises to make its best effort to complete the work within the ceil
in Contract Pricing including CAS & Allowable Costs · 3y ago
- T&M Rate Evaluation During Award
@Vern Edwards Yes, all assumptions your made in response to my question are accurate. FAR 16.601 (b)(1) states, "Direct labor hours at specified fixed hourly rates that include wages, overhead, gene
in Contract Pricing including CAS & Allowable Costs · 3y ago
- T&M Rate Evaluation During Award
How would you treat a T&M rate proposed by a subcontractor during cost evaluation for award under a CPFF type contract? This is a competitive effort and the prime submitted some of its subcontractor p
in Contract Pricing including CAS & Allowable Costs · 3y ago