- Renegotiating Cost and Fee
> > Retreadfed said: > > > What do you mean by "requirements"? To me, that refers to the work the contractor is to do. Therefore, a change in the work the contractor is required to do could be impl
in Contract Administration · 2y ago
- Renegotiating Cost and Fee
> > Retreadfed said: > > > Does the contract contain FAR 52.232-20? If so, how do you reconcile that clause with what is quoted above? Is the quoted language from a deviation to the FAR? Negative,
in Contract Administration · 2y ago
- Renegotiating Cost and Fee
Thanks for the reply! No, the contractor did not notify the Government. It is the COR/technical wanting to get the fee back. After doing the analysis, Overall costs are well under – around 30% - wel
in Contract Administration · 2y ago
- Renegotiating Cost and Fee
Hi All - Currently have a CPFF contract that is in its 2nd option year. The contract is currently under running. 2 statements are in the contract which the contractor acknowledges: 1\. "If the esti
in Contract Administration · 2y ago
- Getting Contractor to Accept FPRR
Thanks for the input Vern!
in Contract Pricing including CAS & Allowable Costs · 3y ago
- Getting Contractor to Accept FPRR
Hello - I am currently preparing for negotiations with a large defense contractor for the next phase of my CPFF contract. Certified cost or pricing data will not be required. There is no FPRA on fi
in Contract Pricing including CAS & Allowable Costs · 3y ago
- Realignment of Funds on CPFF Task Order
Hi, I wanted to follow up on this. If there is a need to realign funds from cost to fee, without increasing the overall ceiling of a particular CPFF task order, does the period of obligation matter o
in Contract Administration · 5y ago
- Multiple Award IDIQ using FAR 35 & Broad Agency Announcements (BAA) Procedures
> > Don Mansfield said: > > > So the task order competition would be like a mini-BAA? You'd get varying proposals within a broad research area? > > > > I don't see a problem with that. Awesome - th
in Contract Administration · 5y ago
- Multiple Award IDIQ using FAR 35 & Broad Agency Announcements (BAA) Procedures
Thanks Don. Yes, in terms of "multiple award" we want to award multiple awards of indefinite-quantity contracts under a single solicitation for the same or similar supplies or services to two or more
in Contract Administration · 5y ago
- Multiple Award IDIQ using FAR 35 & Broad Agency Announcements (BAA) Procedures
Hello - I'm in the beginning phases of the acquisition process and am exploring whether there is anything precluding me from awarding a multiple award IDIQ contract off of a BAA using FAR 35 and spec
in Contract Administration · 5y ago
- CLIN Structuring - CPFF Task Order
Hi All, I am currently in the process of beginning to work a pre-award for a CPFF Task Order. I am currently in a debate with my COR who seems to think that having one CLIN for all of the work is su
in Contract Award Process · 5y ago
- Realignment of Funds on CPFF Task Order
> > Don Mansfield said: > > > If you deobligate funds from a task order, those funds may not be available for obligation on another task order because the period for obligation expired. Thank you so
in Contract Administration · 5y ago
- Realignment of Funds on CPFF Task Order
Hi All, I am fairly new to the contracting world, so excuse my ignorance. I manage 6 CPFF task orders under a Base IDIQ. If we have to realign funds from one task order to another, is there anythin