- Exceedance of IDIQ Capacity with Modification to Existing Task Order
One last question on this topic. If the agency has MATOC's would this change the answers to any of these questions when only one IDIQ MATOC holder would be over their capacity. If not, are there any
in Contract Administration · 3y ago
- Exceedance of IDIQ Capacity with Modification to Existing Task Order
> > Vel said: > > > I've always viewed this type of work (Title II or PCAS) as a severable service, because the benefit is received at the time the services are rendered. Depending on the type of fu
in Contract Administration · 3y ago
- Exceedance of IDIQ Capacity with Modification to Existing Task Order
> > On 12/3/2022 at 9:55 AM, Vern Edwards said: > > > Thank you for all the comments and suggestions and for providing your professional insights into the matter. I believe I have what I need to mov
in Contract Administration · 3y ago
- Exceedance of IDIQ Capacity with Modification to Existing Task Order
To add more background to the discussion, The work associated with this Task Order was originally competed amongst all of the multiple award IDIQ holders, in accordance with FAR 16.605(b)(1). In th
in Contract Administration · 3y ago
- Exceedance of IDIQ Capacity with Modification to Existing Task Order
> > joel hoffman said: > > > This is common, both for government construction contracts and especially in local government and private A/E contracting. > > > > When I was a consulting engineer in an
in Contract Administration · 3y ago
- Exceedance of IDIQ Capacity with Modification to Existing Task Order
I am also curious if they are any GAO or other court rulings that indicate it is acceptable to exceed the IDIQ contract ceiling. I have done some searching in these venues but have been unable to loc
in Contract Administration · 3y ago
- Exceedance of IDIQ Capacity with Modification to Existing Task Order
Yes we are wanting to increase the value of the task order and extend the period of performance so services can continue through the end of the construction contract. The Task Order was awarded under
in Contract Administration · 3y ago
- Exceedance of IDIQ Capacity with Modification to Existing Task Order
I am currently working on a modification to an existing Task Order for A/E Services. The A/E was selected utilizing competition under the Multiple Award contract holders established for the PD/SD and
in Contract Administration · 3y ago