Subcontractor Tina threshold when prime issues 2 different RFQ's for 2 differnet part numbers
Started by kelly007 · Mar 18, 2020 · 34 replies
- kOriginal post
kelly007
Mar 18, 2020 · 6y ago
the USG has an RFP to a prime contractor where the prime issued 2 different RFQ's to one of its subcontractors. This sub provides 2 different parts. One part meets the TINA threshold and the other does not. The USG is asking for c&p data based on combining the 2 parts together under the primes proposal. The sub is pushing back and saying not required.
Thoughts?
- h
here_2_help
Mar 18, 2020 · 6y ago
The threshold applies to individual solicitations, obviously. Whether the prime should have combined the P/Ns seems to be a bit of Monday-morning quarterbacking. The fact is, two individual solicitations were issued. Done.
Now, what happens if the prime decides to cancel its two solicitations and reissue as one combined solicitation? What does the subK do then? That will be an interesting situation.
- R
Retreadfed
Mar 19, 2020 · 6y ago
Recognizing that there can be valid reasons for the prime to issue to RFQs to the same subcontractor, a fundamental question that needs to be answered is what prohibits a prime contractor from breaking up a subcontract procurement in order to avoid having to submit subcontractor cost or pricing data?
- h
here_2_help
Mar 19, 2020 · 6y ago
Retreadfed said:
Recognizing that there can be valid reasons for the prime to issue [two] RFQs to the same subcontractor, a fundamental question that needs to be answered is what prohibits a prime contractor from breaking up a subcontract procurement in order to avoid having to submit subcontractor cost or pricing data?
I am unaware of any prohibition that might apply, especially so if the procurement was broken up in order to maximize potential competition. (Doubtful that would apply in this particular case, but still ….)
- R
Retreadfed
Mar 19, 2020 · 6y ago
here_2_help said:
I am unaware of any prohibition that might apply,
Agree. I should have been clearer and stated that my question was directed toward Kelly.
- j
joel hoffman
Mar 19, 2020 · 6y ago
But the USG can ask for data other than C or P data for the second part, if deemed to be necessary.
- R
Retreadfed
Mar 19, 2020 · 6y ago
joel hoffman said:
But the USG can ask for data other than C or P data for the second part, if deemed to be necessary.
What requires the prime to get such data from a sub?
- j
joel hoffman
Mar 19, 2020 · 6y ago
On 3/19/2020 at 4:54 PM, Retreadfed said:
What requires the prime to get such data from a sub?
“15.403-3 Requiring data other than certified cost or pricing data.
(a)(1) In those acquisitions that do not require certified cost or pricing data, the contracting officer shall—
(i) Obtain whatever data are available from Government or other secondary sources and use that data in determining a fair and reasonable price;
(ii) Require submission of data other than certified cost or pricing data, as defined in 2.101, from the offeror to the extent necessary to determine a fair and reasonable price (10 U.S.C. 2306a(d)(1) and 41 U.S.C. 3505(a)) if the contracting officer determines that adequate data from sources other than the offeror are not available. This includes requiring data from an offeror to support a cost realism analysis;
(iii) Consider whether cost data are necessary to determine a fair and reasonable price when there is not adequate price competition;
(iv) Require that the data submitted by the offeror include, at a minimum, appropriate data on the prices at which the same item or similar items have previously been sold, adequate for determining the reasonableness of the price unless an exception under 15.403-1(b)(1) or (2) applies; and
(v) Consider the guidance in section 3.3, chapter 3, volume I, of the Contract Pricing Reference Guide cited at 15.404-1(a)(7) to determine the data an offeror shall be required to submit.
(2) The contractor's format for submitting the data should be used (see 15.403-5(b)(2)).
(3) The contracting officer shall ensure that data used to support price negotiations are sufficiently current to permit negotiation of a fair and reasonable price. Requests for updated offeror data should be limited to data that affect the adequacy of the proposal for negotiations, such as changes in price lists.
(4) As specified in section 808 of the Strom Thurmond National Defense Act for Fiscal Year 1999 (Pub. L. 105-261), an offeror who does not comply with a requirement to submit data for a contract or subcontract in accordance with paragraph (a)(1) of this subsection is ineligible for award unless the HCA determines that it is in the best interest of the Government to make the award to that offeror, based on consideration of the following:
(i) The effort made to obtain the data.
(ii) The need for the item or service.
(iii) Increased cost or significant harm to the Government if award is not made“
15.404-3 Subcontract pricing considerations.
(a) The contracting officer is responsible for the determination of a fair and reasonable price for the prime contract, including subcontracting costs. The contracting officer should consider whether a contractor or subcontractor has an approved purchasing system, has performed cost or price analysis of proposed subcontractor prices, or has negotiated the subcontract prices before negotiation of the prime contract, in determining the reasonableness of the prime contract price. This does not relieve the contracting officer from the responsibility to analyze the contractor's submission, including subcontractor's certified cost or pricing data.
(b) The prime contractor or subcontractor shall—
(1) Conduct appropriate cost or price analyses to establish the reasonableness of proposed subcontract prices;
(2) Include the results of these analyses in the price proposal; and
(3) When required by paragraph (c) of this subsection, submit subcontractor certified cost or pricing data to the Government as part of its own certified cost or pricing data.
(c) Any contractor or subcontractor that is required to submit certified cost or pricing data also shall obtain and analyze certified cost or pricing data before awarding any subcontract, purchase order, or modification expected to exceed the certified cost or pricing data threshold, unless an exception in 15.403-1(b) applies to that action.
(1) The contractor shall submit, or cause to be submitted by the subcontractor(s), certified cost or pricing data to the Government for subcontracts that are the lower of either—
(i) $13.5 million or more; or
(ii) Both more than the pertinent certified cost or pricing data threshold and more than 10 percent of the prime contractor's proposed price, unless the contracting officer believes such submission is unnecessary.
2) The contracting officer should require the contractor or subcontractor to submit to the Government (or cause submission of) subcontractor certified cost or pricing data below the thresholds in paragraph (c)(1) of this subsection and data other than certified cost or pricing data that the contracting officer considers necessary for adequately pricing the prime contract.
(3) Subcontractor certified cost or pricing data shall be submitted in the format provided in Table 15-2 of 15.408 or the alternate format specified in the solicitation.
(4) Subcontractor certified cost or pricing data shall be current, accurate, and complete as of the date of price agreement, or, if applicable, an earlier date agreed upon by the parties and specified on the contractor's Certificate of Current Cost or Pricing Data. The contractor shall update subcontractor's data, as appropriate, during source selection and negotiations.
(5) If there is more than one prospective subcontractor for any given work, the contractor need only submit to the Government certified cost or pricing data for the prospective subcontractor most likely to receive the award.“
**(**If this is a DoD contract, then also refer to the relevant DFARS and PGI paragraphs.
The contractor is responsible for providing adequate data for the government to determine that the pricing is fair and reasonable whether zero or one hundred percent of the effort is subcontracted. And it made no difference to me whether our primes had already negotiated subcontract pricing in mod or claims actions or for sole source negotiated contracts for that matter. It’s not up to the KO to justify the contractor’s prices.
As for “What requires” the prime to get such data from a sub, I suppose whatever clause provides for a price adjustment as well as case law that establishes or reinforces principles that the party seeking a price adjustment ultimately has to justify that the proposed price is fair and reasonable. Those are the standards which expand upon the basic requirement to justify a price adjustment or equitable adjustment, depending upon the action.
- j
joel hoffman
Mar 19, 2020 · 6y ago
Splitting requirements to avoid cost or pricing thresholds can sometimes be an “indicator” of possible procurement fraud or impropriety by contractors .
Here is an example where DoD required higher levels of scrutiny of a contractor supplying parts to DoD:
- j
joel hoffman
Mar 20, 2020 · 6y ago
Of course, if the parts are commercial items then cost or pricing data aren’t required but the KO can require A reasonable amount of other than cost or pricing data if necessary to determine reasonableness of the prices
However in the instant case, the parts being acquired do not appear to be commercial items. The original poster indicated that cost and pricing data were provided for one of the parts and that cost or pricing data weren’t provided for the second part because the order had been split so that the second part would cost less than the threshold price from the subcontractor.
- h
here_2_help
Mar 20, 2020 · 6y ago
joel hoffman said:
Of course, if the parts are commercial items then cost or pricing data aren’t required but the KO can require A reasonable amount of other than cost or pricing data if necessary to determine reasonableness of the prices
However in the instant case, the parts being acquired do not appear to be commercial items. The original poster indicated that cost and pricing data were provided for one of the parts and that cost or pricing data weren’t provided for the second part because the order had been split so that the second part would cost less than the threshold price from the subcontractor.
Joel, I didn't get that the "order had been split" to avoid the threshold. Not sure where you got that in the OP. Instead, I thought the prime had issued two solicitations for two parts -- one valued over the threshold and one under. Not sure why "splitting" would make sense since one part was over the threshold even after the "split." Now, if both parts had been individually under but, when combined, they were over, then I might go along with your speculation. But not as originally posted. Just doesn't make sense to me.
- N
Neil Roberts
Mar 20, 2020 · 6y ago · edited 6y ago
On 3/18/2020 at 5:27 AM, kelly007 said:
Thoughts?
My thought is that a business minded prime and subcontractor would honor the USG request if the parts do not qualify as an exception to certified cost or pricing data. Also, I would expect a business minded prime would look into the matter to determine how this situation happened, present it to the subcontractor, and be prepared to explain it to the USG. Finally, if the subcontractor still was pushing back after the explanation (assuming there is no reasonable basis for the prime to resist) , I would cancel the solicitation and find other sources.
- j
joel hoffman
Mar 20, 2020 · 6y ago
here_2_help said:
Joel, I didn't get that the "order had been split" to avoid the threshold. Not sure where you got that in the OP. Instead, I thought the prime had issued two solicitations for two parts -- one valued over the threshold and one under. Not sure why "splitting" would make sense since one part was over the threshold even after the "split." Now, if both parts had been individually under but, when combined, they were over, then I might go along with your speculation. But not as originally posted. Just doesn't make sense to me.
Perhaps. At any rate, I mentioned that the USG can obtain other than cost or pricing data for the other part.
It is true that we don’t know why the prime split the order.
This action was a single RFP, so there seemingly shouldn’t have been a reason why the Prime would split the order for two parts. But we don’t know all the facts. I agree with Neil that the KO should ask the Prime why the single RFP has been split into two RFQ’s from the one sub. It may be that the second RFQ could have been the result of competition. But that wasn’t mentioned.
EDIT: By the actions of the USG, it appears that the KO views the Contractor’s action as splitting one contract action into two separate RFQ’s from one sub/supplier.
- j
joel hoffman
Mar 20, 2020 · 6y ago
On 3/18/2020 at 6:57 PM, here_2_help said:
The threshold applies to individual solicitations, obviously. Whether the prime should have combined the P/Ns seems to be a bit of Monday-morning quarterbacking. The fact is, two individual solicitations were issued. Done.
Now, what happens if the prime decides to cancel its two solicitations and reissue as one combined solicitation? What does the subK do then? That will be an interesting situation.
On 3/19/2020 at 8:59 AM, Retreadfed said:
Recognizing that there can be valid reasons for the prime to issue to RFQs to the same subcontractor, a fundamental question that needs to be answered is what prohibits a prime contractor from breaking up a subcontract procurement in order to avoid having to submit subcontractor cost or pricing data?
On 3/19/2020 at 9:26 AM, here_2_help said:
I am unaware of any prohibition that might apply, especially so if the procurement was broken up in order to maximize potential competition. (Doubtful that would apply in this particular case, but still ….)
H2H didn’t limit lack of awareness of any prohibition to only a procurement broken up to maximize Potential competition.
If the price for the second part was competed with the expectation of maximized competition, it could Reasonably be solicited separately from the first part.
Retreadfed stated that the challenge was directed to the OP:
On 3/19/2020 at 10:19 AM, Retreadfed said:
Agree. I should have been clearer and stated that my question was directed toward Kelly.
Then Retreadfed challenged me to justify what requires a prime to require other than cost or pricing data to support a subs price.
Retreadfed said:
What requires the prime to get such data from a sub?
The facts remain: This is one contract action. The Prime Issued two separate RFQ’s to one sub.
The prime can be required to justify why this has been done or is necessary - for a single contract action.
The government can - at the least- require the contractor to provide Data other than C or P if necessary to determine the reasonableness of the price of the second part
In addition, the prime is required to evaluate the reasonableness of the subs quote.
Both the OP and I were challenged to justify our posts.
The two of you seem to feel that nothing prohibits a contractor from splitting an order to avoid submitting some or all C or P data In response to an RFP for a single contract action .
I don’t agree with those opinions.
A fact is that it could have the appearance of a split order to avoid cost or pricing feor the second part. You both hinted at that.
The DoD appears to be concerned about such tactics. I found an instance and shared it.
- R
Retreadfed
Mar 20, 2020 · 6y ago
joel hoffman said:
As for “What requires” the prime to get such data from a sub, I suppose whatever clause provides for a price adjustment
The government is not entitled to a price adjustment if data other than certified cost or pricing data is defective. Such an adjustment is permitted only if certified cost or pricing data are defective. The requirement for submission of certified cost or pricing data for a new contract is found in the solicitation provision FAR 52.215-20. That provision states that if an exception to the submission of certified cost or pricing data does not apply, "The offeror shall prepare and submit certified cost or pricing data, data other than certified cost or pricing data, and supporting attachments in accordance with the instructions contained in Table 15-2 of FAR 15.408, " Table 14-2 directs offerors to "Submit the subcontractor certified cost or pricing data and data other than certified cost or pricing data as part of your own certified cost or pricing data as required in paragraph IIA(2) of this table." It goes on to state "You must also submit any data other than certified cost or pricing data obtained from a subcontractor, either actually or by specific identification, along with the results of any analysis performed on that data." These are the only references to submission of data other than certified cost or pricing data in 15-2. Nothing in 15-2 or 52.215-20 requires a prime contractor to obtain other than certified cost or pricing data from subcontractors.
- D
Don Mansfield
Mar 20, 2020 · 6y ago
Retreadfed said:
Nothing in 15-2 or 52.215-20 requires a prime contractor to obtain other than certified cost or pricing data from subcontractors.
The CO could use Alternate IV of FAR 52.215-20 to require submission of such data.
- N
Neil Roberts
Mar 20, 2020 · 6y ago
joel hoffman said:
This action was a single RFP, so there seemingly shouldn’t have been a reason why the Prime would split the order for two parts. But we don’t know all the facts. I agree with Neil that the KO should ask the Prime why the single RFP has been split into two RFQ’s from the one sub. It may be that the second RFQ could have been the result of competition. But that wasn’t mentioned.
My experience is these kinds of situations can happen when procurement requests may be routed to different procurement representatives based on part type, physical location, program or other. They do not talk to each other or even know whether the same subcontractor is being solicited.
- R
Retreadfed
Mar 20, 2020 · 6y ago
Don Mansfield said:
The CO could use Alternate IV of FAR 52.215-20 to require submission of such data.
If the criteria for such use are met. FAR 15.408 says "Replace the basic clause with its Alternate IV if certified cost or pricing data are not expected to be required because an exception may apply, but data other than certified cost or pricing data will be required ." Even if Alt IV is used, the contracting officer would have to specifically state that the contractor is required to get similar data from subcontractors. My point is there is no standard FAR provision or clause that specifically requires contractors to get other than certified cost or pricing data from subcontractors.
- j
joel hoffman
Mar 20, 2020 · 6y ago
Retreadfed said:
The government is not entitled to a price adjustment if data other than certified cost or pricing data is defective. Such an adjustment is permitted only if certified cost or pricing data are defective. The requirement for submission of certified cost or pricing data for a new contract is found in the solicitation provision FAR 52.215-20. That provision states that if an exception to the submission of certified cost or pricing data does not apply, "The offeror shall prepare and submit certified cost or pricing data, data other than certified cost or pricing data, and supporting attachments in accordance with the instructions contained in Table 15-2 of FAR 15.408, " Table 14-2 directs offerors to "Submit the subcontractor certified cost or pricing data and data other than certified cost or pricing data as part of your own certified cost or pricing data as required in paragraph IIA(2) of this table." It goes on to state "You must also submit any data other than certified cost or pricing data obtained from a subcontractor, either actually or by specific identification, along with the results of any analysis performed on that data." These are the only references to submission of data other than certified cost or pricing data in 15-2. Nothing in 15-2 or 52.215-20 requires a prime contractor to obtain other than certified cost or pricing data from subcontractors.
Huh?? I wasn’t referring to a price adjustment for defective pricing. You asked me what requires a contractor to obtain other than cost or pricing data. I was referring to whatever clause would provide a price adjustment to the contract, such as the changes clause or a differing site condition. Both of those clauses provide for an equitable adjustment , based upon the cost impact to the contractor due to the changed condition or change. Between the applicable clause, FAR subpart 15.4, subpart 31.2, agency supplements, caselaw etc. the contractor would have to provide adequate detail for the contracting officer to determine the reasonableness of the cost adjustment.
That’s all I meant.
- j
joel hoffman
Mar 20, 2020 · 6y ago
Retreadfed said:
If the criteria for such use are met. FAR 15.408 says "Replace the basic clause with its Alternate IV if certified cost or pricing data are not expected to be required because an exception may apply, but data other than certified cost or pricing data will be required ." Even if Alt IV is used, the contracting officer would have to specifically state that the contractor is required to get similar data from subcontractors. My point is there is no standard FAR provision or clause that specifically requires contractors to get other than certified cost or pricing data from subcontractors.
You are correct. The FAR clauses don’t literally state every single element of the modification process. For instance, the FAR Changes clause doesn’t even cover a change that isn’t ordered until the parties pre-price it. It doesn’t cover RFP’s for proposed changes. That has been discussed in the Nash and Cibinic Report and Vern Edwards has mentioned it in this Forum too. Those are but a few examples. I’m not sure if Unabsorbed home office overhead is covered in FAR, certainly not in FAR clauses. But it and the conditions necessary to establish it were formed and defined in caselaw.
The FAR itself may cover stuff not in a clause. Established caselaw may define requirements also. Caselaw defines principles of contract interpretation.
Caselaw holds that the party seeking an adjustment must reasonably justify the amounts otherwise due. Etc., Etc.
Many requirements of FAR part 15.4 are not stated in the contract but are generally consistent with Statutes and caselaw. Many of the principles of fair and reasonableness are outlined in Subpart 31.2, which is often or usually applicable by reference.
It would take books six feet thick to cover every requirement by reference.
One can’t rely solely on a literal reading of contract clauses.
- R
Retreadfed
Mar 21, 2020 · 6y ago
joel hoffman said:
I wasn’t referring to a price adjustment for defective pricing. You asked me what requires a contractor to obtain other than cost or pricing data. I was referring to whatever clause would provide a price adjustment to the contract, such as the changes clause or a differing site condition.
Why bring this up? The OP indicated a new contract was being issued. I do not see any reference to a modification to an existing contract.
- j
joel hoffman
Mar 21, 2020 · 6y ago
Retreadfed said:
Why bring this up? The OP indicated a new contract was being issued. I do not see any reference to a modification to an existing contract.
“the USG has an RFP to a prime contractor where the prime issued 2 different RFQ's to one of its subcontractors.”
I must have misread this post to think that “a prime contractor “ is a contractor under a Government contract and that it has a “subcontractor”. - j
joel hoffman
Mar 21, 2020 · 6y ago
I just checked Kelly’s profile and he/she has only one post. It didn’t mention any negotiation of or issuance of a new contract. Pretty darned sure that “a prime contractor” is what I think it is and that “one of his subcontractors” is a sub under the prime contract.
But if it is for a proposed contract, I included applicable references for that too, including this Statutory reference, which you may have overlooked earlier:
“15.403-3 Requiring data other than certified cost or pricing data...
...(a)(4) As specified in section 808 of the Strom Thurmond National Defense Authorization Act for Fiscal Year 1999 (Pub. L. 105-261), an offeror who does not comply with a requirement to submit data for a contract or subcontrac****t in accordance with paragraph (a)(1) of this subsection is ineligible for award unless the HCA determines that it is in the best interest of the Government to make the award to that offeror...”
- j
joel hoffman
Mar 21, 2020 · 6y ago
On 3/19/2020 at 5:51 PM, joel hoffman said:
2) The contracting officer should require the contractor or subcontractor to submit to the Government (or cause submission of) subcontractor certified cost or pricing data below the thresholds in paragraph (c)(1) of this subsection and data other than certified cost or pricing data that the contracting officer considers necessary for adequately pricing the prime contract.
This would actually answer the original question regarding requiring c or p data for both parts.
- R
Retreadfed
Mar 22, 2020 · 6y ago
joel hoffman said:
a)(4) As specified in section 808 of the Strom Thurmond National Defense Authorization Act for Fiscal Year 1999 (Pub. L. 105-261), an offeror who does not comply with a requirement to submit data for a contract or subcontrac****t in accordance with paragraph (a)(1) of this subsection is ineligible for award unless the HCA determines that it is in the best interest of the Government to make the award to that offeror...”
Notice that this paragraph references paragraph (a)(1). Paragraph (a)(1) begins by stating "In those acquisitions that do not require certified cost or pricing data, the contracting officer shall." However, it appears that in Kelly's case, that cost or pricing data are required at the prime level. Therefore, I do not see that (a)(4) is applicable.
- j
joel hoffman
Mar 23, 2020 · 6y ago
The subcontractor (and maybe the prime?) are maintaining that c or p data isn’t required (reason not described).
H2H thinks that there are 2 separate solicitations involved because the second part was separately solicited by the prime. There is but one contract action.
There is but one RFP for an acquisition of 2 parts by the government.
If a prime contractor can break down one single acquisition/contract action/government solicitation into multiple orders from the same supplier or subcontractor producer to keep individual prices below subcontract TINA thresholds, it would be easy to nullify the intent, purpose and requirements of TINA. If the OP is with the government, they should seek legal counsel.
In addition, some here seem to think that the prime and it’s sub don’t have to provide any data at all to justify the reasonableness of prices beneath the threshold.
Voila! Successfully manipulating a single action, avoiding not only c or p but other data necessary to determine price reasonableness!
I don’t agree with the idea that paragraph (a)(4) isn’t applicable because (a)(1) is applicable only at the prime level, even when part of the order doesn’t require c or p data. Thus, a contractor is required to provide c or p but isn’t required to provide c or p data and when not required to provide c or p, isn’t required to provide data other than c or p data.
If the contractor is maintains that it doesn’t have to provide c or p data for the second part, then -if necessary - the contractor must provide data other than c or p data to justify the reasonableness
The Contractor must also evaluate subcontract prices and provide the results. When cost or pricing data are not required for part of a proposal, the FAR explains what type of minimum information is required.
I really think that the KO can require c or p for both parts. But I didn’t press that in my first post. I merely said okay then, require data other than C or P to justify the price of the second part.
After all, how often is there any government action taken to investigate whether there is defective pricing for most contract actions? The OP apparently didn’t ask their legal counsel and hasn’t participated in this discussion, since the first post. He or she just asked for “thoughts”.
My thoughts are 1) make the contractor justify splitting the action into two separate orders,
remind the contractor that this is one contract action, one solicitation, one acquisition.
If the contractor says that they competed the purchase of the second part, then they still have to evaluate the reasonableness and provide the results- including the basis for their determination.
If they didn’t compete the second part, then AT LEAST, require the prime to obtain and provide data other than cost or pricing from the sub, IF necessary to determine the reasonableness. Simply stonewalling isn’t an option.
If the government really feels that c or p are required for the second part, Consult your lawyer - insist that they investigate whether a contractor can simply split up purchases from any sub to negate TINA or to avoid providing any data from that sub to justify its price to the prime.
Just lifting up your arms and saying “Oh well! isn’t acceptable.
- R
Retreadfed
Mar 23, 2020 · 6y ago
joel hoffman said:
If a prime contractor can break down one single acquisition/contract action/government solicitation into multiple orders from the same supplier or subcontractor producer to keep individual prices below subcontract TINA thresholds, it would be easy to nullify the intent, purpose and requirements of TINA.
This goes back to the original question - other than your outrage, what tells a contractor that it cannot do this? I'm not arguing what should be, but what is. I cannot find any such prohibition in FAR 52.215-20, or Table 15-2.
- j
joel hoffman
Mar 23, 2020 · 6y ago
Retreadfed said:
This goes back to the original question - other than your outrage, what tells a contractor that it cannot do this? I'm not arguing what should be, but what is. I cannot find any such prohibition in FAR 52.215-20, or Table 15-2.
I told you that the clause doesn’t provide every detail for a mod action.
For that matter neither do the Changes or differing site conditions clauses.
Doesnt mean that there are no other actions that can be required of a contractor to substantiate or for the KO to be able to determine the fair and reasonableness of an offer.
So, you are essentially saying that
a contractor can circumvent Cost or pricing data simply by splitting up a subs proposal into two or more orders. (I didn’t initially assert that. I merely said have the sub submit other Data.)
Nothing requires a contractor or it’s sub to provide other data to allow the contractor or the government to determine that the offer is fair and reasonable.
Or did you drop the second part of your assertions? The clause at 52.215-20 does say that the government can require other data than cost or pricing data for both the prime and sub. In addition it does say that the KO could require c and p data below the threshold if necessary.
- h
here_2_help
Mar 23, 2020 · 6y ago
Joel,
It very much seems that, somehow, you've gotten confused between the government solicitation to the prime contractor--which is certainly one contract action--and the prime contractor's solicitations to its potential subcontractors--of which there are multiple. There are likely multiple potential subcontractors, but the OP postulated one subcontractors that received two separate prime contractor solicitations for two separate parts. One of the prime contractor solicitations for one part breached the TINA threshold and certified cost or pricing data was provided to the prime. The other prime contractor solicitation was under the TINA threshold and certified cost or pricing data was not provided. We don't know whether other than certified cost or pricing data was provided.
Much of what you've posted seems to be based on that confusion.
- R
Retreadfed
Mar 23, 2020 · 6y ago
joel hoffman said:
I told you that the clause doesn’t provide every detail for a mod action.
You keep coming back to a mod. I do not read the original post as referring to a mod since it uses the term RFP. However, even if we are talking about a mod, the requirement for submission of certified cost or pricing data in regard to a mod is stated in FAR 52.215-21. Again, I can find no prohibition against a contractor breaking up or splitting a requirement to a subcontractor in that clause.
- j
joel hoffman
Mar 23, 2020 · 6y ago
Retreadfed said:
You keep coming back to a mod. I do not read the original post as referring to a mod since it uses the term RFP. However, even if we are talking about a mod, the requirement for submission of certified cost or pricing data in regard to a mod is stated in FAR 52.215-21. Again, I can find no prohibition against a contractor breaking up or splitting a requirement to a subcontractor in that clause.
The term "Request for Proposals" has long been used for requesting proposals for modifications to existing contracts in the Army Corps of Engineers and is still be used for that purpose. I have a Mobile District Contract Administration Manual dated 1975 and I know for a fact that every later revision of that CA Manual still refers to that as an RFP. The South Atlantic Division Contract Administration Manual SADDM 1110-1-1, dated June 2012 and the 2017 update to the USACE Acquisition Instructions (UAI) also use that term and abbreviation.
I suspect that other government agencies use the same term to request a proposal for mods in addition to subpart 15.2 new contract proposals.
You don't normally issue an RFP for a new contract “to a prime contractor”.
- j
joel hoffman
Mar 23, 2020 · 6y ago
here_2_help said:
Joel,
It very much seems that, somehow, you've gotten confused between the government solicitation to the prime contractor--which is certainly one contract action--and the prime contractor's solicitations to its potential subcontractors--of which there are multiple. There are likely multiple potential subcontractors, but the OP postulated one subcontractors that received two separate prime contractor solicitations for two separate parts. One of the prime contractor solicitations for one part breached the TINA threshold and certified cost or pricing data was provided to the prime. The other prime contractor solicitation was under the TINA threshold and certified cost or pricing data was not provided. We don't know whether other than certified cost or pricing data was provided.
Much of what you've posted seems to be based on that confusion.
H2H, I’ve already clearly said that if the RFQ for the second part was competitive then there is no need for c or p data. I’ve also said that the OP hasn’t participated in the thread except to ask for “thoughts”. There hasn’t been any clarification at all from the OP.
- j
joel hoffman
Mar 23, 2020 · 6y ago
Retreadfed said:
You keep coming back to a mod. I do not read the original post as referring to a mod since it uses the term RFP. However, even if we are talking about a mod, the requirement for submission of certified cost or pricing data in regard to a mod is stated in FAR 52.215-21. Again, I can find no prohibition against a contractor breaking up or splitting a requirement to a subcontractor in that clause.
52.215-13 subcontractor cost or pricing data - Modifications.
“(b) Before awarding any subcontract expected to exceed the threshold for submission of certified cost or pricing data at FAR 15.403-4, on the date of agreement on price or the date of award, whichever is later; or before pricing any subcontract modification involving a pricing adjustment expected to exceed the threshold for submission of certified cost or pricing data at FAR 15.403-4, the Contractor shall require the subcontractor to submit certified cost or pricing data (actually or by specific identification in writing), in accordance with FAR 15.408, Table 15-2 (to include any information reasonably required to explain the subcontractor's estimating process such as the judgmental factors applied and the mathematical or other methods used in the estimate, including those used in projecting from known data, and the nature and amount of any contingencies included in the price), unless an exception under FAR 15.403-1 applies.”
If this is one contract action under which the government included both parts, then one would normally expect one subcontract to be awarded or one modification to an existing subcontract to be made For the one contract action. That new subcontract or mod to an a existing subcontract would exceed the threshold in aggregate. unless the second part was competed by the prime or unless the second part is a commercial item or qualified for another exemption, it will not be separately exempted from the requirement for the contractor to submit c or p data simply because two separate p.o.’s , RFQ’s or whatever you want to call the solicitations from the prime to the sub were sent to the sub.
If you are talking about a new subcontract for the two parts, the new subcontract will exceed the threshold for c&p data. The Contractor shouldn’t be awarding two subcontracts to one sub for one contract action. Both parts are included in the one prime contractor proposal.
If you’re talking about a modification to the subcontract for the two parts included in one contract action, the contractor shouldn’t be issuing two mods to the subcontract. Both parts are included in one prime contractor proposal.
- R
Retreadfed
Mar 24, 2020 · 6y ago
Joel, you still have not identified anything that prohibits a prime contractor from splitting a requirement. You keep saying what the contractor "shouldn't" do but have not identified anything that it cannot do.
As for agencies issuing RFPs for contract modifications, in my experience, that would be an unusual procedure. The Corpse of Engineers may be an outlier.
- j
joel hoffman
Mar 24, 2020 · 6y ago
Retreadfed said:
Joel, you still have not identified anything that prohibits a prime contractor from splitting a requirement. You keep saying what the contractor "shouldn't" do but have not identified anything that it cannot do.
As for agencies issuing RFPs for contract modifications, in my experience, that would be an unusual procedure. The Corpse of Engineers may be an outlier.
It isn’t a Corpse. I’d say that they are alive and well! Do you call it request a proposal “RAP”? Demand a proposal “DAP”? Send me one “SMO”? Please send a proposal “PSAP”?
Its not a “solicitation”. It’s a request for the contractor to submit a proposal for the action. The goal is to pre-price a change or other type of modification prior to ordering it; or otherwise when issuing a Change order , for instance. .